TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/11055/2015              (ii). Name of Project for which Forest Land is required : Construction of Mamni-Uroli Motor Road under State sectore              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The length of this road is 5 Km. and it will be connect village Uroli and Ijra,Total area for diversion of forest land is 2.10 Ha.              (iv). File no. : 8B/UCP/06/17/2017/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.1
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/11055/201518/03/2015aa21/03/2015   26/03/2015 Rudraprayag :26/03/2015Garhwal:
  10/04/2015 (Rudraprayag)

Uttarakhand:
04/07/2015
Uttarakhand:
09/09/2015
Dehradun:
16/03/2017
01/12/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:07/04/2017  
Replied by State Government(Uttarakhand) on:19/05/2017  
Query raised by Regional Office (Dehradun) on:08/06/2017  
Replied by State Government(Uttarakhand) on:13/11/2017  
Query raised by State Government (Uttarakhand) on:23/05/2016  
Replied by Nodal Officer (Uttarakhand) on:26/10/2016  
Query raised by State Government (Uttarakhand) on:10/04/2017  
Replied by Nodal Officer (Uttarakhand) on:16/05/2017  
Query raised by State Government (Uttarakhand) on:12/06/2017  
Replied by Nodal Officer (Uttarakhand) on:08/11/2017  
Query raised by Nodal Officer (Uttarakhand) on:09/07/2015  
Replied by Circle(Garhwal) on:06/08/2015  
Query raised by Nodal Officer (Uttarakhand) on:15/08/2015  
Replied by Circle(Garhwal) on:27/08/2015  
Query raised by Nodal Officer (Uttarakhand) on:02/09/2015  
Replied by Circle(Garhwal) on:08/09/2015  
Query raised by Nodal Officer (Uttarakhand) on:27/05/2016  
Replied by Circle(Garhwal) on:30/09/2016  
Query raised by Nodal Officer (Uttarakhand) on:10/04/2017  
Replied by Circle(Garhwal) on:25/04/2017  
Query raised by Nodal Officer (Uttarakhand) on:19/06/2017  
Replied by Circle(Garhwal) on:28/07/2017  
Query raised by Nodal Officer (Uttarakhand) on:09/08/2017  
Replied by Circle(Garhwal) on:01/11/2017  
Query raised by Circle (Garhwal) on:16/04/2015  
Replied by DFO (Rudraprayag) on:18/06/2015  
Query raised by Circle (Garhwal) on:26/06/2015  
Replied by DFO (Rudraprayag) on:26/06/2015  
Query raised by Circle (Garhwal) on:27/06/2015  
Replied by DFO (Rudraprayag) on:30/06/2015  
Query raised by Circle (Garhwal) on:10/07/2015  
Replied by DFO (Rudraprayag) on:06/08/2015  
Query raised by Circle (Garhwal) on:17/08/2015  
Replied by DFO (Rudraprayag) on:25/08/2015  
Query raised by Circle (Garhwal) on:03/09/2015  
Replied by DFO (Rudraprayag) on:08/09/2015  
Query raised by Circle (Garhwal) on:27/05/2016  
Replied by DFO (Rudraprayag) on:22/06/2016  
Query raised by Circle (Garhwal) on:25/06/2016  
Replied by DFO (Rudraprayag) on:26/09/2016  
Query raised by Circle (Garhwal) on:11/04/2017  
Replied by DFO (Rudraprayag) on:19/04/2017  
Query raised by Circle (Garhwal) on:20/06/2017  
Replied by DFO (Rudraprayag) on:22/07/2017  
Query raised by Circle (Garhwal) on:10/08/2017  
Replied by DFO (Rudraprayag) on:27/10/2017  
Query raised by DFO (Rudraprayag) on:17/04/2015  
Replied by UA on :15/06/2015  
Query raised by DFO (Rudraprayag) on:13/07/2015  
Replied by UA on :13/07/2015  
Query raised by DFO (Rudraprayag) on:14/07/2015  
Replied by UA on :05/08/2015  
Query raised by DFO (Rudraprayag) on:01/06/2016  
Replied by UA on :09/06/2016  
Query raised by DFO (Rudraprayag) on:10/06/2016  
Replied by UA on :15/06/2016  
Query raised by DFO (Rudraprayag) on:16/06/2016  
Replied by UA on :18/06/2016  
Query raised by DFO (Rudraprayag) on:29/06/2016  
Replied by UA on :23/09/2016  
Query raised by DFO (Rudraprayag) on:12/04/2017  
Replied by UA on :17/04/2017  
Query raised by DFO (Rudraprayag) on:21/06/2017  
Replied by UA on :21/07/2017  
Query raised by DFO (Rudraprayag) on:22/07/2017  
Replied by UA on :22/07/2017  
Query raised by DFO (Rudraprayag) on:10/08/2017  
Replied by UA on :11/10/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)