A. General Details
  (i). Proposal No. : FP/TG/ROAD/31490/2018              (ii). Name of Project for which Forest Land is required : Formation of approach road to main work "Construction of HLB across Manjeera river from Dharmareddy to Muddapur via Venkampally road PR road in Kamareddy District" - 2.121 Ha              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 2.121 Ha of Forest land in Kamareddy division for formation of approach road to main work Construction of HLB across Manjeera river from Dharmareddy to Muddapur via Venkampally road Pr road in Kamareddy District in favour of R&B Departent              (iv). State : Telangana              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 2.121
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/TG/ROAD/31490/201825/01/201806/02/2018   28/01/2022   28/01/2022   28/01/2022 Kamareddy :28/01/2022Nizamabad:
  28/01/2022 (Kamareddy)

Telangana:
28/01/2022
Telangana:
28/01/2022
Hyderabad:
28/01/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Hyderabad) on:22/02/2022  
Replied by State Government(Telangana) on:20/07/2022  
Query raised by Regional Office (Hyderabad) on:30/08/2022  
Replied by State Government(Telangana) on:06/07/2023  
Query raised by Regional Office (Hyderabad) on:14/12/2023  
Replied by State Government(Telangana) on:02/05/2025  
Query raised by Regional Office (Hyderabad) on:13/05/2025  
Query raised by State Government (Telangana) on:18/06/2022  
Replied by Nodal Officer (Telangana) on:20/07/2022  
Query raised by State Government (Telangana) on:08/09/2022  
Replied by Nodal Officer (Telangana) on:07/01/2023  
Query raised by State Government (Telangana) on:18/10/2024  
Replied by Nodal Officer (Telangana) on:19/02/2025  
Query raised by Nodal Officer (Telangana) on:20/07/2022  
Replied by Circle(Nizamabad) on:20/07/2022  
Query raised by Nodal Officer (Telangana) on:08/09/2022  
Replied by Circle(Nizamabad) on:07/01/2023  
Query raised by Nodal Officer (Telangana) on:21/10/2024  
Replied by Circle(Nizamabad) on:25/01/2025  
Query raised by Circle (Nizamabad) on:20/07/2022  
Replied by DFO (Kamareddy) on:20/07/2022  
Query raised by Circle (Nizamabad) on:13/09/2022  
Replied by DFO (Kamareddy) on:07/01/2023  
Query raised by Circle (Nizamabad) on:23/10/2024  
Replied by DFO (Kamareddy) on:25/01/2025  
Query raised by DFO (Kamareddy) on:20/07/2022  
Replied by UA on :20/07/2022  
Query raised by DFO (Kamareddy) on:23/10/2024  
Replied by UA on :25/01/2025  
NOTE:- Proposal is pending at State Government due to EDS raised by Regional Office .