TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/40975/2019              (ii). Name of Project for which Forest Land is required : Construction of Chinyalisaur-Jogath motor road to Pujargaon Bhadeshwar mandir motor road in Chinyalisaur Block under State Sector.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The length of this motor road is 1.825 km, Whereby village Pungargaon will be connected directly to the block Chinyalisaur. the creation of this motor road, villagers will be able to carry their cash crops and carry the daily commodity's goods. The ancient Bhadeshwar temple situated in Pujaragaon, w              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.4385
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/40975/201902/07/201905/07/2019   12/03/2020  14/11/2019   20/03/2020   06/06/2020 Uttarkashi :16/07/2020Bhagirathi:
  07/10/2020 (Uttarkashi)

Uttarakhand:
04/11/2020
Uttarakhand:
01/12/2021
Dehradun:
22/12/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:28/12/2021  
Replied by State Government(Uttarakhand) on:29/06/2023  
Query raised by Regional Office (Dehradun) on:13/07/2023  
Query raised by State Government (Uttarakhand) on:29/12/2021  
Replied by Nodal Officer (Uttarakhand) on:15/06/2023  
Query raised by State Government (Uttarakhand) on:18/07/2023  
Query raised by Nodal Officer (Uttarakhand) on:04/11/2020  
Replied by Circle(Bhagirathi) on:04/05/2021  
Query raised by Nodal Officer (Uttarakhand) on:10/06/2021  
Replied by Circle(Bhagirathi) on:11/06/2021  
Query raised by Nodal Officer (Uttarakhand) on:18/06/2021  
Replied by Circle(Bhagirathi) on:08/07/2021  
Query raised by Nodal Officer (Uttarakhand) on:12/07/2021  
Replied by Circle(Bhagirathi) on:20/11/2021  
Query raised by Nodal Officer (Uttarakhand) on:29/12/2021  
Replied by Circle(Bhagirathi) on:06/10/2022  
Query raised by Nodal Officer (Uttarakhand) on:20/10/2022  
Replied by Circle(Bhagirathi) on:01/06/2023  
Query raised by Nodal Officer (Uttarakhand) on:18/07/2023  
Replied by Circle(Bhagirathi) on:13/12/2024  
Query raised by Circle (Bhagirathi) on:08/10/2020  
Replied by DFO (Uttarkashi) on:19/10/2020  
Query raised by Circle (Bhagirathi) on:06/11/2020  
Replied by DFO (Uttarkashi) on:19/04/2021  
Query raised by Circle (Bhagirathi) on:20/04/2021  
Replied by DFO (Uttarkashi) on:26/04/2021  
Query raised by Circle (Bhagirathi) on:29/04/2021  
Replied by DFO (Uttarkashi) on:04/05/2021  
Query raised by Circle (Bhagirathi) on:19/06/2021  
Replied by DFO (Uttarkashi) on:07/07/2021  
Query raised by Circle (Bhagirathi) on:13/07/2021  
Replied by DFO (Uttarkashi) on:28/10/2021  
Query raised by Circle (Bhagirathi) on:29/10/2021  
Replied by DFO (Uttarkashi) on:30/10/2021  
Query raised by Circle (Bhagirathi) on:01/01/2022  
Replied by DFO (Uttarkashi) on:17/05/2022  
Query raised by Circle (Bhagirathi) on:19/05/2022  
Replied by DFO (Uttarkashi) on:24/05/2022  
Query raised by Circle (Bhagirathi) on:25/05/2022  
Replied by DFO (Uttarkashi) on:02/09/2022  
Query raised by Circle (Bhagirathi) on:31/10/2022  
Replied by DFO (Uttarkashi) on:24/04/2023  
Query raised by Circle (Bhagirathi) on:24/07/2023  
Replied by DFO (Uttarkashi) on:11/01/2024  
Query raised by Circle (Bhagirathi) on:20/03/2024  
Replied by DFO (Uttarkashi) on:01/04/2024  
Query raised by Circle (Bhagirathi) on:12/07/2024  
Replied by DFO (Uttarkashi) on:20/07/2024  
Query raised by Circle (Bhagirathi) on:09/08/2024  
Replied by DFO (Uttarkashi) on:26/10/2024  
Query raised by DFO (Uttarkashi) on:04/08/2020  
Replied by UA on :07/08/2020  
Query raised by DFO (Uttarkashi) on:05/09/2020  
Replied by UA on :10/09/2020  
Query raised by DFO (Uttarkashi) on:18/09/2020  
Replied by UA on :30/09/2020  
Query raised by DFO (Uttarkashi) on:09/11/2020  
Replied by UA on :23/03/2021  
Query raised by DFO (Uttarkashi) on:27/03/2021  
Replied by UA on :15/04/2021  
Query raised by DFO (Uttarkashi) on:29/06/2021  
Replied by UA on :02/07/2021  
Query raised by DFO (Uttarkashi) on:05/07/2021  
Replied by UA on :07/07/2021  
Query raised by DFO (Uttarkashi) on:14/07/2021  
Replied by UA on :06/09/2021  
Query raised by DFO (Uttarkashi) on:14/09/2021  
Replied by UA on :21/10/2021  
Query raised by DFO (Uttarkashi) on:04/01/2022  
Replied by UA on :29/04/2022  
Query raised by DFO (Uttarkashi) on:04/06/2022  
Replied by UA on :29/07/2022  
Query raised by DFO (Uttarkashi) on:03/11/2022  
Replied by UA on :22/12/2022  
Query raised by DFO (Uttarkashi) on:11/01/2023  
Replied by UA on :20/04/2023  
Query raised by DFO (Uttarkashi) on:26/07/2023  
Replied by UA on :22/08/2023  
Query raised by DFO (Uttarkashi) on:21/09/2023  
Replied by UA on :27/09/2023  
Query raised by DFO (Uttarkashi) on:07/11/2023  
Replied by UA on :22/12/2023  
Query raised by DFO (Uttarkashi) on:22/08/2024  
Replied by UA on :04/10/2024  
Query raised by DFO (Uttarkashi) on:04/10/2024  
Replied by UA on :16/10/2024  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .