  (i). Proposal No. : FP/UK/ROAD/13621/2015              (ii). Name of Project for which Forest Land is required : construction of Adichaura to Sinni Motor Road Under PMGSY.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : c/o Adichaura to Sinni M/Road Under PMGSY (13.00 km) Forest Land 20.70 hct. the Prominent point of target habitation Namik sach as Primary School, Primary Health Center, Maternity and Child Welfare centers and Post Office will be connected by this road.              (iv). File no. : 8B/UCP/06/148/2016/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 10.35
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/13621/201530/06/201505/02/2016  17/10/2015  18/08/2015  11/08/2015  11/07/2015  03/07/2015   05/04/2016  15/01/2016  15/10/2015  11/08/2015  20/07/2015  10/07/2015   11/04/2016   21/04/2016 Pithoragarh :02/05/2016North Kumaun:
  13/05/2016 (Pithoragarh)

Uttarakhand:
21/06/2016
Uttarakhand:
04/07/2016
Dehradun:
11/07/2016
26/09/2017
By :Regional Office
Uttarakhand
21/09/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:29/07/2016  
Replied by State Government(Uttarakhand) on:27/06/2017  
Query raised by Regional Office (Dehradun) on:11/07/2017  
Replied by State Government(Uttarakhand) on:24/07/2017  
Query raised by Regional Office (Dehradun) on:22/08/2017  
Replied by State Government(Uttarakhand) on:18/09/2017  
Query raised by State Government (Uttarakhand) on:02/08/2016  
Replied by Nodal Officer (Uttarakhand) on:24/06/2017  
Query raised by State Government (Uttarakhand) on:13/07/2017  
Replied by Nodal Officer (Uttarakhand) on:21/07/2017  
Query raised by State Government (Uttarakhand) on:23/08/2017  
Replied by Nodal Officer (Uttarakhand) on:15/09/2017  
Query raised by Nodal Officer (Uttarakhand) on:02/08/2016  
Replied by Circle(North Kumaun) on:05/04/2017  
Query raised by Nodal Officer (Uttarakhand) on:18/04/2017  
Replied by Circle(North Kumaun) on:12/06/2017  
Query raised by Nodal Officer (Uttarakhand) on:22/06/2017  
Replied by Circle(North Kumaun) on:22/06/2017  
Query raised by Nodal Officer (Uttarakhand) on:13/07/2017  
Replied by Circle(North Kumaun) on:20/07/2017  
Query raised by Nodal Officer (Uttarakhand) on:23/08/2017  
Replied by Circle(North Kumaun) on:11/09/2017  
Query raised by Circle (North Kumaun) on:05/08/2016  
Replied by DFO (Pithoragarh) on:30/03/2017  
Query raised by Circle (North Kumaun) on:19/04/2017  
Replied by DFO (Pithoragarh) on:09/06/2017  
Query raised by Circle (North Kumaun) on:22/06/2017  
Replied by DFO (Pithoragarh) on:22/06/2017  
Query raised by Circle (North Kumaun) on:13/07/2017  
Replied by DFO (Pithoragarh) on:18/07/2017  
Query raised by Circle (North Kumaun) on:23/08/2017  
Replied by DFO (Pithoragarh) on:08/09/2017  
Query raised by DFO (Pithoragarh) on:05/08/2016  
Replied by UA on :30/08/2016  
Query raised by DFO (Pithoragarh) on:02/09/2016  
Replied by UA on :07/09/2016  
Query raised by DFO (Pithoragarh) on:09/09/2016  
Replied by UA on :07/10/2016  
Query raised by DFO (Pithoragarh) on:10/10/2016  
Replied by UA on :08/03/2017  
Query raised by DFO (Pithoragarh) on:09/03/2017  
Replied by UA on :09/03/2017  
Query raised by DFO (Pithoragarh) on:19/04/2017  
Replied by UA on :06/06/2017  
Query raised by DFO (Pithoragarh) on:08/06/2017  
Replied by UA on :08/06/2017  
Query raised by DFO (Pithoragarh) on:09/06/2017  
Replied by UA on :09/06/2017  
Query raised by DFO (Pithoragarh) on:22/06/2017  
Replied by UA on :22/06/2017  
Query raised by DFO (Pithoragarh) on:26/08/2017  
Replied by UA on :08/09/2017  
Query raised by DFO (Pithoragarh) on:08/09/2017  
Replied by UA on :08/09/2017  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:06/10/2022  
Query raised by State Government (Uttarakhand) on:10/10/2022  
Query raised by Nodal Officer on:10/10/2022  
Replied by UA on :04/09/2023  
Query raised by Nodal Officer on:08/09/2023  
Replied by UA on :27/09/2023  
Query raised by Nodal Officer on:27/10/2023  
Replied by UA on :27/04/2024  
Query raised by Nodal Officer on:22/09/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .