Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
10/02/2016
|
Sir please remove the objection.
|
|
2
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
17/03/2016
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
04/04/2016
|
Please review entry in serial no. 4 of Form A Part II .Tree density entered in serial no. 2 of online Part II may be reviewed
|
|
4
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
05/04/2016
|
Please review entry in serial no. 4 of Form A Part II .Tree density entered in serial no. 2 of online Part II may be reviewed
|
|
5
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
07/04/2016
|
Sir please find the attachment.
|
|
6
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
07/04/2016
|
Sir, Please receive information of the proposal.
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
06/05/2016
|
1. Total period for which the forest land is proposed to be diverted is given as nil . This may be reviewed.
2. In the calculation of benefit-cost ratio, in part B and C, the parameters have not been quantified in monetary terms
3. The compensatory afforestation is stated to be raised in 2 patches of 6 ha and 6.9 ha while on the map one contiguous patch has been shown.
4. The ownership proof of land chosen for raising compensatory afforestation is given for only (7.694+2.953 ha). land while the CA is to be raised on 12.9 ha. Ownership of the entire area on which CA is to be raised, may be provided
5. Scanned copy of the map of the land identified for creation of Compensatory Afforestation has been given on Google Earth. This may be prepared by using GPS ot Total Sta
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
10/05/2016
|
Plz reply to obj of RO-1. Total period for which the forest land is proposed to be diverted is given as nil . This may be reviewed. 2. In the calculation of benefit-cost ratio, in part B and C, the parameters have not been quantified in monetary terms 3. The compensatory afforestation is stated to be raised in 2 patches of 6 ha and 6.9 ha while on the map one contiguous patch has been shown. 4. The ownership proof of land chosen for raising compensatory afforestation is given for only (7.694+2.953 ha). land while the CA is to be raised on 12.9 ha. Ownership of the entire area on which CA is to be raised, may be provided 5. Scanned copy of the map of the land identified for creation of Compensatory Afforestation has been given on Google Earth. This may be prepared by using G
|
|
9
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
11/05/2016
|
Plz reply to obj of RO-1. Total period for which the forest land is proposed to be diverted is given as nil . This may be reviewed. 2. In the calculation of benefit-cost ratio, in part B and C, the parameters have not been quantified in monetary terms 3. The compensatory afforestation is stated to be raised in 2 patches of 6 ha and 6.9 ha while on the map one contiguous patch has been shown. 4. The ownership proof of land chosen for raising compensatory afforestation is given for only (7.694+2.953 ha). land while the CA is to be raised on 12.9 ha. Ownership of the entire area on which CA is to be raised, may be provided 5. Scanned copy of the map of the land identified for creation of Compensatory Afforestation has been given on Google Earth. This may be prepared by using
|
|
10
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
11/05/2016
|
Plz reply to obj of RO-1. Total period for which the forest land is proposed to be diverted is given as nil . This may be reviewed. 2. In the calculation of benefit-cost ratio, in part B and C, the parameters have not been quantified in monetary terms 3. The compensatory afforestation is stated to be raised in 2 patches of 6 ha and 6.9 ha while on the map one contiguous patch has been shown. 4. The ownership proof of land chosen for raising compensatory afforestation is given for only (7.694+2.953 ha). land while the CA is to be raised on 12.9 ha. Ownership of the entire area on which CA is to be raised, may be provided 5. Scanned copy of the map of the land identified for creation of Compensatory Afforestation has been given on Google Earth. This may be prepared by using
|
|
11
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
12/05/2016
|
Sir please find the attachments
|
|
12
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
12/05/2016
|
Sir, Please receive information of the proposal.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
17/05/2016
|
Plz reply to obj of RO-1. Total period for which the forest land is proposed to be diverted is given as nil . This may be reviewed. 2. In the calculation of benefit-cost ratio, in part B and C, the parameters have not been quantified in monetary terms 3. The compensatory afforestation is stated to be raised in 2 patches of 6 ha and 6.9 ha while on the map one contiguous patch has been shown. 4. The ownership proof of land chosen for raising compensatory afforestation is given for only (7.694+2.953 ha). land while the CA is to be raised on 12.9 ha. Ownership of the entire area on which CA is to be raised, may be provided 5. Scanned copy of the map of the land identified for creation of Compensatory Afforestation has been given on Google Earth. This may be prepared by using shape file f
|
|
14
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
18/05/2016
|
lz reply to obj of RO-1. Total period for which the forest land is proposed to be diverted is given as nil . This may be reviewed. 2. In the calculation of benefit-cost ratio, in part B and C, the parameters have not been quantified in monetary terms 3. The compensatory afforestation is stated to be raised in 2 patches of 6 ha and 6.9 ha while on the map one contiguous patch has been shown. 4. The ownership proof of land chosen for raising compensatory afforestation is given for only (7.694+2.953 ha). land while the CA is to be raised on 12.9 ha. Ownership of the entire area on which CA is to be raised, may be provided 5. Scanned copy of the map of the land identified for creation of Compensatory Afforestation has been given on Google Earth. This may be prepared by using shape file f
|
|
15
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
19/05/2016
|
sir please remove the objections.
|
|
16
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
31/05/2016
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
31/05/2016
|
Please remove the objections no. 3, 4, and 5 properly. CA patches not revised all above points. kml file and map show different CA lands.
|
|
18
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
16/06/2016
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
16/06/2016
|
Sir please find the attachments.
|
|
20
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
17/06/2016
|
Sir, Please receive information of the proaposal.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
11/07/2016
|
CF may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
22
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
12/07/2016
|
DFO may provide detailed point wise reply along with corrections and numbered annexure in support of the same
|
|
23
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
12/07/2016
|
please may provide detailed point wise reply along with corrections and numbered annexure in support of the same.
|
|
24
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
14/07/2016
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
15/07/2016
|
please may provide detailed point wise reply along with corrections and numbered annexure in support of the same. and please give answar according to the guidelines given by nodal office training dated 22th june 2016 workshop.
|
|
26
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
20/07/2016
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
21/07/2016
|
Sir,
Please find attachment.
|
|
28
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
23/07/2016
|
Sir, Please receive information of the proposal.
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
28/07/2016
|
Required documents uploaded for your further necessary action.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
29/07/2016
|
Required documents uploaded for your further necessary action.
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
12/08/2016
|
find the letter attached.
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
29/08/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
31/08/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
34
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
01/09/2016
|
Please remove the objections
|
|
35
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
03/09/2016
|
Please remove the objection.
|
|
36
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
27/09/2016
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
13/10/2016
|
Sir, Please find attachment.
|
|
38
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
14/10/2016
|
Please upload answer showing with serial no Part-1 and Part-2
|
|
39
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
15/10/2016
|
Please upload answer showing with serial no Part-1
|
|
40
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
19/11/2016
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
13/12/2016
|
please proper reply your letter 1557 date 27-09-2016 with upload answer serial number wise attached part I and additional information uploaded showing with serial no Part I . please
|
|
42
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
26/12/2016
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
31/12/2016
|
Sir Please find the attachment.
|
|
44
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
04/01/2017
|
Sir, Please receive information of the proposal.
|
|
45
|
Nodal Officer
|
REPLY
|
State secretary
|
21/01/2017
|
Required documents uploaded for your further necessary action.
|
|
46
|
State secretary
|
REPLY
|
Regional Office
|
23/01/2017
|
Required documents uploaded for your further necessary action.
|
|
47
|
Regional Office
|
EDS
|
State secretary
|
10/02/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
48
|
State secretary
|
EDS
|
Nodal Officer
|
20/02/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
49
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
21/02/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
50
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
22/02/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
51
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
23/02/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
52
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
06/03/2017
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
25/03/2017
|
Please objection remove letter attached in additional information part I.
|
|
54
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
01/04/2017
|
The correction have been made as per the instruction received
|
|
55
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
12/04/2017
|
Please remove objection. has uploaded in additional information Part II Sr no. 2
|
|
56
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
17/04/2017
|
Please send soft copy of the proposal in our office Email id
|
|
57
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
24/04/2017
|
Please send soft copy of the proposal in our office Email id
|
|
58
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
11/06/2017
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
12/06/2017
|
Please remove the objection
|
|
60
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
14/06/2017
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
28/06/2017
|
objection remove have done. soft copy your email id.
|
|
62
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
29/06/2017
|
Please send soft copy of the proposal in our office Email id
|
|
63
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
06/07/2017
|
send soft copy your email id.
|
|
64
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
13/07/2017
|
Letter No 201/12-1 Date 13.07.2017
|
|
65
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
03/08/2017
|
find the letter attached
|
|
66
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
04/08/2017
|
Please remove the objection
|
|
67
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
04/08/2017
|
Please remove the objection.
|
|
68
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
17/08/2017
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
21/08/2017
|
Sir, EDS objection reply.
|
|
70
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
12/09/2017
|
Sir please receive the information of proposal.
|
|
71
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
03/10/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
72
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
03/10/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
73
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
04/10/2017
|
State Government is required to made necessary corrections and submit documents oblique clarifications oblique information as discussed in the Regional Empowered Committee meeting held on 06.02.2017.
|
|
74
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
10/10/2017
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
15/11/2017
|
Sir, EDS objection reply.
|
|
76
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
09/03/2018
|
Sir
Please receive the information of the proposal
|
|
77
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
21/03/2018
|
find the letter attached
|
|
78
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
24/03/2018
|
please remove the objection.
|
|
79
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
02/04/2018
|
Please remove the objection.
|
|
80
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
12/04/2018
|
The correction have been made as per the instruction received
|
|
81
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
14/06/2018
|
Sir, EDS Objection removed.
|
|
82
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
28/06/2018
|
Sir Please receive the information of the proposal
|
|
83
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
05/07/2018
|
the said document is not upload
|
|
84
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
06/07/2018
|
Sir Please receive the information of the proposal
|
|
85
|
Nodal Officer
|
REPLY
|
State secretary
|
18/07/2018
|
Required documents uploaded for your further necessary action.
|
|
86
|
State secretary
|
EDS
|
Nodal Officer
|
25/07/2018
|
plz checa the uploaded letter
|
|
87
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
25/07/2018
|
find the letter attached
|
|
88
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
26/07/2018
|
please remove the objection.
|
|
89
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
07/08/2018
|
Please remove the objection.
|
|
90
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
07/08/2018
|
The correction have been made as per the instruction received
|
|
91
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
23/08/2018
|
Sir, EDS objection reply.
|
|
92
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
10/09/2018
|
Sir Please receive the information of the proposal
|
|
93
|
Nodal Officer
|
REPLY
|
State secretary
|
13/09/2018
|
The correction have been made as per the instruction received
|
|
94
|
State secretary
|
REPLY
|
Regional Office
|
14/09/2018
|
The correction have been made as per the instruction received
|
|
95
|
Regional Office
|
EDS
|
State secretary
|
28/09/2018
|
State Govt. forwarded the letter adressed to user agency to this office. Please provide reply of this office.
|
|
96
|
State secretary
|
EDS
|
Nodal Officer
|
01/10/2018
|
State Govt. forwarded the letter adressed to user agency to this office. Please provide reply of this office.
|
|
97
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
01/10/2018
|
find the letter attached
|
|
98
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
01/10/2018
|
please remove the objection
|
|
99
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
01/10/2018
|
please remove the objection.
|
|
100
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
12/10/2018
|
The correction have been made as per the instruction received
|
|
101
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
29/10/2018
|
Sir,
EDS objection reply;.
|
|
102
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
05/11/2018
|
Sir Please receive the information of the proposal
|
|
103
|
Nodal Officer
|
REPLY
|
State secretary
|
14/11/2018
|
The correction have been made as per the instruction received
|
|
104
|
State secretary
|
REPLY
|
Regional Office
|
15/11/2018
|
The correction have been made as per the instruction received
|
|
105
|
Regional Office
|
EDS
|
State secretary
|
07/12/2018
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
106
|
State secretary
|
EDS
|
Nodal Officer
|
16/12/2018
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
107
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
17/12/2018
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
108
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
17/12/2018
|
please remove the objection
|
|
109
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
19/12/2018
|
PLease EDS objection removed.
|
|
110
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
26/12/2018
|
The correction have been made as per the instruction received
|
|
111
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
09/01/2019
|
Sir, EDS objection has been removed.
|
|
112
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
15/02/2019
|
sir please receive the information of the proposal.
|
|
113
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
10/03/2019
|
CF may attend the shortcoming as per attachment.
|
|
114
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
12/03/2019
|
remove the objection.
|
|
115
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepwdgauchar@rediffmail.com)
|
12/03/2019
|
please removed the objection.
|
|
116
|
User Agency (eepwdgauchar@rediffmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
22/04/2019
|
The correction have been made as per the instruction received
|
|
117
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
09/05/2019
|
Sir
user agency has been objection removed.
|
|
118
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
17/06/2019
|
sir please receive the information of the proposal.
|
|
119
|
Nodal Officer
|
REPLY
|
State secretary
|
01/07/2019
|
The correction have been made as per the instruction received
|
|
120
|
State secretary
|
REPLY
|
Regional Office
|
02/07/2019
|
The correction have been made as per the instruction received
|
|