Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
26/02/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
27/02/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
3
|
Nodal Officer
|
EDS
|
CF (Western)
|
01/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
4
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
02/03/2021
|
As per letter attached do the needful.
|
|
5
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
05/03/2021
|
As per letter attached do the needful.
|
|
6
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
17/03/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
23/03/2021
|
Sir
Correction has been done and attached document are enclose
|
|
8
|
CF (Western)
|
REPLY
|
Nodal Officer
|
25/03/2021
|
As per EDS necessary shortcomings has been rectified by the Concerned Authority as letter attached. Please do the needful.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Western)
|
12/04/2021
|
find the letter attached
|
|
10
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
17/04/2021
|
As per letter attached do the needful.
|
|
11
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
01/05/2021
|
As per letter attached do the needful.
|
|
12
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
26/06/2021
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
19/07/2021
|
Sir,
objection has been remove
|
|
14
|
CF (Western)
|
REPLY
|
Nodal Officer
|
24/07/2021
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Western)
|
29/07/2021
|
• please submit hard copy of the compliance for EDS raised by reginal office on dated 26-02--21 to nodal office for perusing proposal to RO office.
|
|
16
|
CF (Western)
|
REPLY
|
Nodal Officer
|
05/08/2021
|
Hard copy of the compliance has been submitted with letter no. 161/12-1 dated 23-07-2021 as letter attached. Please do the needful.
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
17/08/2021
|
The correction have been made as per the instruction received
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
17/08/2021
|
The correction have been made as per the instruction received
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
31/08/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
01/09/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
21
|
Nodal Officer
|
EDS
|
CF (Western)
|
01/09/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
22
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
01/09/2021
|
As per letter attached do the needful.
|
|
23
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
01/09/2021
|
As per letter attached do the needful.
|
|
24
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
28/09/2021
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
11/10/2021
|
Sir
all required correction has been done
|
|
26
|
CF (Western)
|
REPLY
|
Nodal Officer
|
25/10/2021
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
27
|
Nodal Officer
|
EDS
|
CF (Western)
|
22/11/2021
|
• please submit hard copy of the compliance for EDS raised by GOI office on dated 31-08-21 to nodal office for perusing proposal to GOI office.
|
|
28
|
CF (Western)
|
REPLY
|
Nodal Officer
|
23/11/2021
|
Hard copy has been submitted vide letter no. 593/12-1 dated 14-10-2021 as letter attached. Please do the needful.
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
03/12/2021
|
The correction have been made as per the instruction received
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
03/12/2021
|
The correction have been made as per the instruction received
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
16/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
18/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
33
|
Nodal Officer
|
EDS
|
CF (Western)
|
22/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
34
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
27/12/2021
|
As per letter attached do the needful.
|
|
35
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
03/01/2022
|
As per letter attached do the needful.
|
|
36
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
09/06/2022
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
20/06/2022
|
The correction have been made as per the instruction received.
|
|
38
|
CF (Western)
|
REPLY
|
Nodal Officer
|
29/06/2022
|
As per EDS necessary shortcomings has been rectified as per letter attached. Please do the needful.
|
|
39
|
Nodal Officer
|
EDS
|
CF (Western)
|
12/07/2022
|
find the letter attached
|
|
40
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
13/07/2022
|
As per letter attached, do the needful.
|
|
41
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
15/07/2022
|
As per letter attached, do the needful
|
|
42
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
29/09/2022
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
10/10/2022
|
Correction has been made
|
|
44
|
CF (Western)
|
REPLY
|
Nodal Officer
|
15/10/2022
|
As per EDS necessary shortcomings has been rectified. Please do the needful.
|
|
45
|
Nodal Officer
|
EDS
|
CF (Western)
|
29/10/2022
|
find the letter attached
|
|
46
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
31/10/2022
|
Please do the needful.
|
|
47
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
03/11/2022
|
Please do the needful.
|
|
48
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
02/12/2022
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
27/12/2022
|
the correction has been made as per the instruction received
|
|
50
|
CF (Western)
|
REPLY
|
Nodal Officer
|
31/12/2022
|
As per EDS necessary shortcomings has been rectified as letter attached. Kindly do the needful.
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
13/01/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. Kindly do the needful.
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
13/01/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. Kindly do the needful.
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
02/02/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
04/02/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
55
|
Nodal Officer
|
EDS
|
CF (Western)
|
04/02/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
56
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
06/02/2023
|
As per EDS attached, kindly do the needful.
|
|
57
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
06/02/2023
|
As per EDS attached, kindly do the needful.
|
|
58
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
28/02/2023
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
02/03/2023
|
The correction have been made as per the instruction received
|
|
60
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
10/03/2023
|
As per EDS do the needful.
|
|
61
|
DFO (Tarai Central,Haldwani)
|
REPLY
|
CF (Western)
|
14/03/2023
|
The correction have been made as per the instruction received
|
|
62
|
CF (Western)
|
REPLY
|
Nodal Officer
|
21/03/2023
|
In reply to EDS dated 04-02-2023 necessary shortcomings has been rectified as letter attached. Kindly do the needful.
|
|
63
|
Nodal Officer
|
REPLY
|
State secretary
|
01/04/2023
|
The correction have been made as per the instruction received
|
|
64
|
State secretary
|
REPLY
|
Regional Office
|
01/04/2023
|
The correction have been made as per the instruction received
|
|
65
|
Regional Office
|
EDS
|
State secretary
|
09/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
66
|
State secretary
|
EDS
|
Nodal Officer
|
09/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
67
|
Nodal Officer
|
EDS
|
CF (Western)
|
11/05/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
68
|
CF (Western)
|
EDS
|
DFO (Tarai Central,Haldwani)
|
12/05/2023
|
As per letter attached, kindly do the needful.
|
|
69
|
DFO (Tarai Central,Haldwani)
|
EDS
|
User Agency (principal.gmchld@rediffmail.com)
|
19/05/2023
|
As per letter attached, kindly do the needful.
|
|
70
|
User Agency (principal.gmchld@rediffmail.com)
|
REPLY
|
DFO (Tarai Central,Haldwani)
|
16/01/2025
|
The correction have been made as per the instruction received
|
|