Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
10/07/2015
|
Copy attached
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
15/07/2015
|
PDF File EDS raised by GOI
|
|
3
|
Nodal Officer
|
EDS
|
CF (Kota)
|
15/07/2015
|
Please reply EDS raised by GOI on dated 9.7.15.
|
|
4
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
16/07/2015
|
Kindly submit EDS
|
|
5
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
27/07/2015
|
Reply the EDS pointwise
|
|
6
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
08/09/2015
|
observations sent by you are not readable. Please send readable copy of obersarvation
|
|
7
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
08/10/2015
|
KINDLY PROVIDE kml FILE IN SOFT AND HARD COPY IN FOUR SETS
|
|
8
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
25/04/2016
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
06/05/2016
|
As per instruction received from regional office MOEF kml and DGPS map for road and CA land should be in polygon form.
|
|
10
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
01/06/2016
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
17/06/2016
|
EDS queries incorporated in part 2 also.
|
|
12
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
28/06/2016
|
Correction have been made by DCF Baran. So proposal forwarded for n/a.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Kota)
|
13/07/2016
|
Some information are required. Kindly provide.
|
|
14
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
13/07/2016
|
Some information are required. Kindly provide.
|
|
15
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
26/08/2016
|
EDS replied and forwarded for further action.
|
|
16
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
01/09/2016
|
Correction have been made by DCF Baran. So proposal forwarded for n/a
|
|
17
|
Nodal Officer
|
EDS
|
CF (Kota)
|
21/09/2016
|
Kindly provide information as per attached document.
|
|
18
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
21/09/2016
|
Kindly provide information as per attached document.
|
|
19
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
27/09/2016
|
kindly provide the information
|
|
20
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
26/01/2017
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
26/01/2017
|
EDS replied by user agency and forwarded for further action
|
|
22
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
30/01/2017
|
The proposal has been forwarded without properly rectifying the deficiencies or shorts falls hence returned back for replying the EDS
by the Nodal Officer. Kindly examination the proposal carefully and reply the EDS.
|
|
23
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
06/02/2017
|
EDS Replied to NA please
|
|
24
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
09/05/2017
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
27/06/2017
|
The correction have been made as per the instruction received
|
|
26
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
03/07/2017
|
Correction have been made by DCF Baran for forwarded n/a
|
|
27
|
Nodal Officer
|
EDS
|
CF (Kota)
|
13/07/2017
|
Kindly provide information as per attached document.
|
|
28
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
18/07/2017
|
Kindly provide information as per attached document.
|
|
29
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
25/08/2017
|
1 The original copy of FRA is soughted 2 kml file and dgps map of diverted forest land is not same 3 the old documents should be removed 4 The 2 sets of hard copy with required sign should be send 5 the authorised signatory should be attested 6 the required information by MOEF with their letter dated 18-09-2015 should be send
|
|
30
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
14/09/2017
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
28/09/2017
|
The Essential Details have been Attached
|
|
32
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
06/10/2017
|
The correction have been made as per the instruction received
|
|
33
|
Nodal Officer
|
EDS
|
CF (Kota)
|
25/10/2017
|
Kindly provide information as per attached document.
|
|
34
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
26/10/2017
|
Kindly provide information as per attached document.
|
|
35
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
28/10/2017
|
Essential Details Sought by Forest Department sent
|
|
36
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
28/10/2017
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
30/10/2017
|
Reply is attached.
|
|
38
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
30/10/2017
|
The correction have been made as per the instruction received
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
23/01/2018
|
Reply of EDS of GOI is submitted.
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
25/01/2018
|
Agreed with the comments of APCCF & Nodal Officer FCA, Rajasthan Jaipur.
|
|
41
|
Regional Office
|
EDS
|
State secretary
|
06/03/2018
|
EDS vide letter dt.15.02.2018
|
|
42
|
State secretary
|
EDS
|
Nodal Officer
|
07/03/2018
|
Pl. Provide the required information by GoI.
|
|
43
|
Nodal Officer
|
EDS
|
CF (Kota)
|
07/03/2018
|
Kindly provide information as per attached document.
|
|
44
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
08/03/2018
|
Kindly provide information as per attached document.
|
|
45
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
14/03/2018
|
Essential Details Sought by Forest Department
|
|
46
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
24/03/2018
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
10/04/2018
|
ccf kota
|
|
48
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
11/04/2018
|
correction have been made by user agency and DCf Baran as per received instruction dt. 07.03.2018
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
13/04/2018
|
Reply is attached.
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
16/04/2018
|
Agreed with the comments of APCCF & Nodal Officer FCA, Rajasthan Jaipur.
|
|
51
|
Regional Office
|
EDS
|
State secretary
|
25/04/2018
|
EDS
|
|
52
|
State secretary
|
EDS
|
Nodal Officer
|
26/04/2018
|
Please send the required information by GoI letter dt. 23.4.2018.
|
|
53
|
Nodal Officer
|
EDS
|
CF (Kota)
|
26/04/2018
|
Kindly provide information as required by GOI
|
|
54
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
27/04/2018
|
Kindly provide information as per required by GOI
|
|
55
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
24/05/2018
|
Essential Details Sought by Forest Department
|
|
56
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
25/07/2018
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
14/02/2019
|
sir attech file
|
|
58
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
21/02/2019
|
The correction have been made as per the instruction received dt. 26.04.2018
|
|
59
|
Nodal Officer
|
EDS
|
CF (Kota)
|
29/03/2019
|
Hard copy not received of correction which you made till 29.3.2019. Kindly provide hard copy
|
|
60
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
02/04/2019
|
Hard Copy Direct sent by DCF Baran wide letter no. 1556 dt. 14.02.2019 and this office has been sent forwarding letter no. 1300 dt. 21.02.2019 with recommendation
|
|
61
|
Nodal Officer
|
EDS
|
CF (Kota)
|
19/05/2019
|
Hard copy not received of correction which you made till 29.3.2019. Kindly provide hard copy again.
|
|
62
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
20/05/2019
|
Hard copy not received of correction which you made till 29.3.2019. Kindly provide hard copy again.
|
|
63
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
17/07/2019
|
Essential Details Sought by Forest Department
|
|
64
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
12/11/2019
|
The correction have been made as per the instruction received
|
|
65
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
15/11/2019
|
sr attched file
|
|
66
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
05/01/2020
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
09/01/2020
|
Attched File
|
|
68
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
21/09/2022
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
29/09/2022
|
eds reply plz
|
|
70
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
20/10/2022
|
Kindly provide information as per attached document.
|
|
71
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
21/10/2022
|
eds reply plz
|
|
72
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
26/12/2022
|
The correction have been made as per the instruction received
|
|
73
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
26/12/2022
|
viotation riport
|
|
74
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
27/12/2022
|
The correction have been made as per the instruction received.
|
|
75
|
Nodal Officer
|
EDS
|
CF (Kota)
|
24/01/2023
|
Kindly provide information as per attached document.
|
|
76
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
27/01/2023
|
Uploaded copy of Essential Details Sought letter is not open. Please again upload and resend.
|
|
77
|
Nodal Officer
|
EDS
|
CF (Kota)
|
27/01/2023
|
kindly provide information as per attached document
|
|
78
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
01/02/2023
|
kindly provide information as per attached document
|
|
79
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
13/02/2023
|
eds reply please
|
|
80
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
29/04/2023
|
The correction have been made as per the instruction received
|
|
81
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
04/05/2023
|
The proposal has been withdrawn by the higher office, so please send the compliance report as on date 18-4-2018
|
|
82
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
27/07/2023
|
The correction have been made as per the instruction received
|
|
83
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
10/08/2023
|
Plz upload Authentic latter
|
|
84
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
01/09/2023
|
The correction have been made as per the instruction received
|
|
85
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
11/09/2023
|
EDS REPLY SR
|
|
86
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
12/09/2023
|
The reply sent by you date on 11.09.2023 is not clearly visible. Please upload the correct copy.
|
|
87
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
12/09/2023
|
eds reply sr
|
|
88
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
18/09/2023
|
The correction have been made as per the instruction received date 27.01.2023
|
|
89
|
Nodal Officer
|
EDS
|
CF (Kota)
|
25/10/2023
|
Kindly provide information as per attached document
|
|
90
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
30/10/2023
|
Kindly provide information as per attached document
|
|
91
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
30/10/2023
|
eds reply sr
|
|
92
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
25/04/2024
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
06/05/2024
|
eds reply sir
|
|
94
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
13/05/2024
|
kindly provide as per the dcf acctached document
|
|
95
|
Nodal Officer
|
EDS
|
CF (Kota)
|
30/05/2024
|
Incomplete compliance.
|
|
96
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
30/05/2024
|
Incomplete compliance.
|
|
97
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
06/06/2024
|
he correction have been made as per the instruction received
|
|
98
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
11/06/2024
|
Incomplete compliance.
|
|
99
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
13/06/2024
|
the correction have been made as per the instruction received
|
|
100
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
27/06/2024
|
The correction have been made as per the instruction received.
|
|
101
|
Nodal Officer
|
REPLY
|
State secretary
|
23/07/2024
|
Reply of EDS is attached.
|
|
102
|
State secretary
|
REPLY
|
Regional Office
|
11/09/2024
|
EDS reply
|
|
103
|
Regional Office
|
EDS
|
State secretary
|
04/11/2024
|
EDS dated 30.10.2024
|
|
104
|
State secretary
|
EDS
|
Nodal Officer
|
06/11/2024
|
Please Reply EDS
|
|
105
|
Nodal Officer
|
EDS
|
CF (Kota)
|
06/11/2024
|
Kindly provide information as per attached document
|
|
106
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
07/11/2024
|
kindly provide information as per attached document
|
|
107
|
DFO (Baran Territorial)
|
EDS
|
User Agency (ee_chhabra@rediffmail.com)
|
13/11/2024
|
eds reply sir
|
|
108
|
User Agency (ee_chhabra@rediffmail.com)
|
REPLY
|
DFO (Baran Territorial)
|
13/11/2024
|
The correction have been made as per the instruction received
|
|
109
|
DFO (Baran Territorial)
|
REPLY
|
CF (Kota)
|
14/11/2024
|
eds reply sir
|
|
110
|
CF (Kota)
|
REPLY
|
Nodal Officer
|
20/11/2024
|
eds reply sir
|
|
111
|
Nodal Officer
|
EDS
|
CF (Kota)
|
13/12/2024
|
Kindly provide information as per attached document.
|
|
112
|
CF (Kota)
|
EDS
|
DFO (Baran Territorial)
|
16/12/2024
|
Kindly provide information as per attached document.
|
|