Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
16/08/2022
|
There is an total area difference in the proposal to the actual extent in the field. hence kindly resubmit the proposal with the actual diversion area
|
|
2
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
19/08/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
16/09/2022
|
Resubmit the proposal with revised maps according to field verification
|
|
4
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
19/09/2022
|
The correction have been made as per the instruction received
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
13/12/2022
|
Sought details on CA, KML file, Comments of CWLW etc.
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
17/12/2022
|
eds
|
|
7
|
Nodal Officer
|
EDS
|
CF (Shimoga)
|
28/12/2022
|
EDS
|
|
8
|
CF (Shimoga)
|
EDS
|
DFO (Sagar)
|
29/12/2022
|
Submit the EDS sought by Nodal Officer
|
|
9
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
02/01/2023
|
Kindly make necessary corrections in the part-I of Parivesh and submit the detailed report with 5 set documents
|
|
10
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
11/08/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Sagar)
|
REPLY
|
CF (Shimoga)
|
11/08/2023
|
All the corrections has been made and documents attached for the queries raised by MoEF, Bangalore
|
|
12
|
CF (Shimoga)
|
REPLY
|
Nodal Officer
|
18/08/2023
|
EDS furnished by User Agency through DCF Sagara is herewith submitted for further action.
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
25/09/2023
|
EDS replied
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
09/10/2023
|
Forwarding reply of Nodal Officer
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
01/11/2023
|
Requested vide letter dated 01-11-2023 to clarify whether the already taken up CA works are for any other forest proposal and whether the CA land is suitable for planting
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
26/12/2023
|
As requested by union government, user agency name needs to be modified, and also take necessary action as requested by union Govt in their letter 1.11.2023
|
|
17
|
Nodal Officer
|
EDS
|
CF (Shimoga)
|
27/12/2023
|
EDS
|
|
18
|
CF (Shimoga)
|
EDS
|
DFO (Sagar)
|
28/12/2023
|
Submit the EDS sought by MoEF
|
|
19
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
10/01/2024
|
Kindly provide the necessary information asked by MoEF, details are in the document attached
|
|
20
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
18/04/2024
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Sagar)
|
REPLY
|
CF (Shimoga)
|
03/05/2024
|
All the queries raised by MoEF are answered and the proposal is resubmitted for further action with all relevant documents
|
|
22
|
CF (Shimoga)
|
REPLY
|
Nodal Officer
|
04/05/2024
|
EDS submitted by User Agency through DCF Sagar is herewith submitted for further needful action.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Shimoga)
|
22/05/2024
|
The proposed area has been changed to 25.266 Ha. Please edit Part-I & II
|
|
24
|
CF (Shimoga)
|
EDS
|
DFO (Sagar)
|
22/05/2024
|
Submit the EDS sought by Nodal Officer
|
|
25
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
24/05/2024
|
Kindly revise the extent of the forest area proposed as per the letter attached.
|
|
26
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
03/10/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
03/10/2024
|
Kindly upload relevant Village Maps & Topo Map of the diversion area in Part-I of the Proposal and resubmit the proposal for verification
|
|
28
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
04/10/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
07/01/2025
|
As per the field inspection report of the Range Forest Officer, Hosanagara Range, Hosanagara and the Assistant Conservator of Forests, Hosanagara Sub-Division, Hosanagara, the following shortcomings are noticed in Part-I of the proposal.
1. 0.136 Ha of forest area has to be added in Sy No 133 of Kalurukatte Village.
2. 0.136 Ha of forest area has to be reduced in Sy No. 13 of Ganganakoppa Village.
3. Necessary KML and village maps also to be corrected.
|
|
30
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
10/01/2025
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Sagar)
|
REPLY
|
CF (Shimoga)
|
11/01/2025
|
Queries raised by the GOI have been answered, and the proposed area of diversion has been revised from 18.844 Ha to 25.763 Ha and Part-II of Parivesh has been updated, and all the necessary documents have been uploaded in Part-II of the proposal. The proposal is resubmitted for further action.
|
|
32
|
CF (Shimoga)
|
EDS
|
DFO (Sagar)
|
13/01/2025
|
Provide revised enumeration list
|
|
33
|
DFO (Sagar)
|
REPLY
|
CF (Shimoga)
|
13/01/2025
|
The revised tree enumeration list is updated in Part-II of the proposal, and the proposal is resubmitted for further action.
|
|
34
|
CF (Shimoga)
|
REPLY
|
Nodal Officer
|
18/01/2025
|
User Agency has submitted revised part I through DCF Sagar, it has been verified and found acceptable.
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
05/02/2025
|
EDS Reply
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
14/02/2025
|
EDS
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
24/02/2025
|
EDS Replied
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
24/02/2025
|
EDS reply
recommended for Stage 1
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
17/04/2025
|
State Govt. has been requested vide letter dated 16.04.2025 to furnish certain additional information as sought by the REC in the meeting held on 27.03.2025.
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
24/04/2025
|
EDS
|
|
41
|
Nodal Officer
|
EDS
|
CF (Shimoga)
|
08/05/2025
|
EDS Query
|
|
42
|
CF (Shimoga)
|
EDS
|
DFO (Sagar)
|
12/05/2025
|
Kindly furnish the EDS sought by IRO at the earliest
|
|
43
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
15/05/2025
|
Kindly submit the answer to the EDS raised by IRO on 16.04.2025
|
|
44
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
16/05/2025
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Sagar)
|
EDS
|
User Agency (peerpasha1961@gmail.com)
|
28/05/2025
|
The Reply submitted by the user agency for the EDS raised by MOEF is reviwed by this office and found that following informations to be included in the EDS reply
1. Biological methods must be incorporated in Slope Stabilizatioon Plan.
2. A detailed reply for the V. Ganapathi petition to be submitted with necessary documents.
3. Wildlife mitigation plan for the movement of arboreal animals must be proposed in detail.
Kindly include all the above information in the proposal and resubmit the proposal for further action.
|
|
46
|
User Agency (peerpasha1961@gmail.com)
|
REPLY
|
DFO (Sagar)
|
31/05/2025
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Sagar)
|
REPLY
|
CF (Shimoga)
|
03/06/2025
|
All the queries raised by MOEF has been answered
|
|
48
|
CF (Shimoga)
|
REPLY
|
Nodal Officer
|
05/06/2025
|
EDS reply furnished by User Agency through Deputy Conservator of Forests Sagara is herewith submitted for further needful action
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
23/06/2025
|
EDS Replied
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
24/06/2025
|
the eds reply submited by PCCF has submitted for further necssary action
|
|