Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
27/11/2019
|
Please do necessary action and provide required information for next proceeding
|
|
2
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
20/12/2019
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
18/02/2020
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
4
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
19/02/2020
|
Hard copy of the proposals submitted by this office letter no. 1455/12-1 dt. 18.02.2020 (received in your office 19.02.2020) receiving attached
|
|
5
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
22/02/2020
|
find the letter attached
|
|
6
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
24/02/2020
|
find the letter attached
|
|
7
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
26/02/2020
|
Please correct the raised query and upload the same in Part I and submit here with for further action.
|
|
8
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
15/05/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
29/05/2020
|
please provide reply of asked 6 queries raised by nodel office dated 22-02-2020 in proper formate in online and in hardcopy for next proceedings
|
|
10
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
01/06/2020
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
22/06/2020
|
Sir,
the raised query have been rectified by user agency and this office and uploaded in part-I and II.
|
|
12
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
24/06/2020
|
Still there are some discripency in the number of trees. plz fill the correct number of trees.
|
|
13
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
29/06/2020
|
Sir,
The sought query have been rectified and updated in online Part-II for further proceedings
|
|
14
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
07/07/2020
|
Correction have been made as per instruction received.
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
14/08/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
14/08/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
17
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
17/08/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
18
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
17/08/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
19
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
18/08/2020
|
please correct the queries raised by MoEF, GOI and submit to this office for next proceedings.
|
|
20
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
24/08/2020
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
27/08/2020
|
Sir,
upon testing your proposal it was found that the kml file of CA uploaded is mismatch as per the DM, dehradun vide letter dated 30 July 2018 alloted 6.476 ha. alloted in civil land but maximum part of the polygon uplodaded shwoing in RF, please revise the same the submit the proposal in this level for further proceedings.
|
|
22
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
08/09/2020
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
11/09/2020
|
Sir,
After scrutiny of part-I compiled by you, there si discrepancy in villagewise breakup and componentwise breakup. Apart from this you have not been provided satisfactory reply in respect of query regarding mitigation of soil erosion. so, please rectified the same and submit the proposal herewith.
|
|
24
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
14/09/2020
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
16/09/2020
|
Sir,
The quries sought by MoEFCC dated 13-08-2020 have rectified by User Agency and this office and uploaded accordingly in part-I and part-II for further proceedings.
|
|
26
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
16/09/2020
|
Kindly review the EDS query number 8
|
|
27
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
16/09/2020
|
Sir,
The query has been corrected as per the instruction received and uploaded the same as a additional information in part-II
|
|
28
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
16/09/2020
|
User Agency may provide necessary corrections in Part I as per EDS received
|
|
29
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
18/09/2020
|
Sir,
The proposal is submitted for further action.
|
|
30
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
24/09/2020
|
correction have been made as per instruction received
|
|
31
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
25/09/2020
|
find the letter attached
|
|
32
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
26/09/2020
|
find the letter attached
|
|
33
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
26/09/2020
|
Sir, please remove the queries raised by Nodel office and submit to this office for futher action
|
|
34
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
27/09/2020
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
30/09/2020
|
Sir, please rectify the quey no. 3 and submit herewith for further action
|
|
36
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
30/09/2020
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
30/09/2020
|
Respected Sir,
The raised queries have been rectified by UA & this office level and accordingly updated online for further consideration
|
|
38
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
01/10/2020
|
Kindly review the point no. 6 & 8 and provide the correct information.
|
|
39
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
06/10/2020
|
Respected Sir,
The shorcoming have been removed and accordingly updated online in part-II for further action
|
|
40
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
10/10/2020
|
correction have been made as per instruction received
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
13/10/2020
|
The correction have been made as per the instruction received
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
13/10/2020
|
The correction have been made as per the instruction received
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
20/10/2020
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
27/10/2020
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
45
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
28/10/2020
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
46
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
28/10/2020
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
47
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
29/10/2020
|
Sir,
Please rectify queries raised by MoEFCC and submit here for furhter action.
|
|
48
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
05/11/2020
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
07/11/2020
|
Sir,
The pointwise compliance of EDS raised by MoEFCC dated 20-10-2020 have been uploded on parivesh portal in part-I and Par-II by user agency and this office level for further proceedings.
|
|
50
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
09/11/2020
|
plz upload revised tree list in additional iniformation
|
|
51
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
09/11/2020
|
Sir,
Revised tree list have been updated as a Additional Informaiton in Part-II for further action.
|
|
52
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
13/11/2020
|
The correction have been as per instructions received.
|
|
53
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
18/11/2020
|
find the letter attached
|
|
54
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
19/11/2020
|
find the letter attached
|
|
55
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
21/11/2020
|
Please corrct the qrueries
|
|
56
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
25/11/2020
|
The correction have been made as per the instruction received
|
|
57
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
27/11/2020
|
Sir,
Shortcomigs have been rectified and uploaded online for further proceedings.
|
|
58
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
01/12/2020
|
The correction have been as per instructions received.
|
|
59
|
Nodal Officer
|
REPLY
|
State secretary
|
09/12/2020
|
The correction have been made as per the instruction received
|
|
60
|
State secretary
|
REPLY
|
Regional Office
|
09/12/2020
|
The correction have been made as per the instruction received
|
|
61
|
Regional Office
|
EDS
|
State secretary
|
29/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
62
|
State secretary
|
EDS
|
Nodal Officer
|
29/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
63
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
29/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
64
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
30/12/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
65
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
31/12/2020
|
Please correct the queries as per the objection raised by RO
|
|
66
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
12/01/2021
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
16/01/2021
|
Sir,
Please review the objection points mentioned in eds issued by RO dated 38-08-2020 and 28-12-2020. All the points expected to be brief with detais facts, but reply on said eds forwarded by you merely a sketchy draft which need to submit in detail clrearity as required by GOI.
|
|
68
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
19/01/2021
|
The correction have been made as per the instruction received
|
|
69
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
27/01/2021
|
Sir,
The Revised muck disposal plan uploaded as Additional Information in part-I of Parivesh Portal is not accessible, please reupload the same properly and submit the proposal here for further action
|
|
70
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
28/01/2021
|
The correction have been made as per the instruction received
|
|
71
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
20/02/2021
|
Sir,
The raised queries have been rectified and uploaded in Part-I and II for further proceedings
|
|
72
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
06/03/2021
|
Sir, Shortcomigs have been rectified and uploaded online by processing Authority for further proceedings.
|
|
73
|
Nodal Officer
|
REPLY
|
State secretary
|
13/03/2021
|
The asked queries have been rectified and uploaded for further proceedings.
|
|
74
|
State secretary
|
REPLY
|
Regional Office
|
13/03/2021
|
The correction have been made as per the instruction received
|
|
75
|
Regional Office
|
EDS
|
State secretary
|
12/04/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
76
|
State secretary
|
EDS
|
Nodal Officer
|
12/04/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
77
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
12/04/2021
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
78
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
16/04/2021
|
Pl. may attend to the shortcomings mentioned in the attached document.
|
|
79
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
16/04/2021
|
Proposal No. FP/UK/ROAD/37612/2018
|
|
80
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
16/04/2021
|
Pl. may attend to the shortcomings mentioned in the attached document.
|
|
81
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
16/04/2021
|
sir, please rectify the proposal as per the letter of GOI
|
|
82
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
16/04/2021
|
The correction have been made as per the instruction received
|
|
83
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
19/04/2021
|
Sir,
the concerned proposal is not showing in edit part of this office, due to the said proposal is being sent back to you through EDS with the request that please take the please lock it again properly and submit herewith asp to this office for further action.
|
|
84
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
20/04/2021
|
The correction have been made as per the instruction received
|
|
85
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
10/05/2021
|
Sir,
As per the instruction received after the meeting convened at Regional Office of MoEFCC, Dehradun in the order of the said proposal. According to minutes issued for this purpose, the information in original should be sent to this office for further action
|
|
86
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
19/05/2021
|
The correction have been made as per the instruction received
|
|
87
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
02/06/2021
|
Sir,
The raised queries have been rectified and accordingly updated at Part-I & II
|
|
88
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
05/06/2021
|
The correction have been as per instructions received.
|
|
89
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
25/06/2021
|
find the letter attached
|
|
90
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
26/06/2021
|
find the letter attached
|
|
91
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
26/06/2021
|
Please submit the revised report with detailing on every points mentioned in eds dated 26-03-2021 and forward the same herewith for further action.
|
|
92
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
19/07/2021
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
23/07/2021
|
As per the queries raised by GoI by its vide letter dated 26-03-2021, please submit detailed muck disposal plan based on scientific study duly authenticated by forest department in reference of query no.-e and comparative chart of surveyed alternates sites duly authenticated by Forest Department and accordingly upload the details at para-D-ii in part-I in copliance of objection point-ii-a
|
|
94
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
29/07/2021
|
The correction have been made as per the instruction received
|
|
95
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
10/08/2021
|
please revised the proposal on the points discussed with the forest department and as per the instruction received from MoEFCC.
|
|
96
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
13/08/2021
|
The correction have been made as per the instruction received
|
|
97
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
16/08/2021
|
please revised the proposal on the points discussed with the forest department and as per the instruction received from MoEFCC.
|
|
98
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
21/08/2021
|
The correction have been made as per the instruction received
|
|
99
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
26/08/2021
|
After Scrutiny of Part-I of this proposal the following shortcomings are found -
1- Districtwise breakup in para b-2.2 3.238 ha RF and 4.463 ha NF mentioned and the same area updated in para-2.3 but in para B-2.4 updated as 3.238 RF & 1.925 ha NF, which is incorrect.
2- Compliance of eds raised by GOI via letter dated 26-03-2021 is submitted pointwise, that need the report in copliance of every opjection separetely.
Please rectify the reply in compliance of above objection.
|
|
100
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
31/08/2021
|
The correction have been made as per the instruction received
|
|
101
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
04/09/2021
|
Sir,
The revised information have been updated in part-I & Part-II in compliance of queries raised by GOI
|
|
102
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
09/09/2021
|
Sir. The raised queries have been rectified and accordingly updated
|
|
103
|
Nodal Officer
|
REPLY
|
State secretary
|
17/09/2021
|
The correction have been as per instructions received.
|
|
104
|
State secretary
|
REPLY
|
Regional Office
|
18/09/2021
|
The correction have been as per instructions received.
|
|
105
|
Regional Office
|
EDS
|
State secretary
|
23/09/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
106
|
State secretary
|
EDS
|
Nodal Officer
|
27/09/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
107
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
27/09/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
108
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
28/09/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
109
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
29/09/2021
|
Please remove the objections as per the EDS attached herewith.
|
|
110
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
04/10/2021
|
The correction have been made as per the instruction received
|
|
111
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
28/10/2021
|
please upload the aerial distance certificate issued by the forest department
|
|
112
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
29/10/2021
|
The correction have been made as per the instruction received
|
|
113
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
08/11/2021
|
Sir,
The raised queires have been removed and updated accrodingly in part-I and II for further necessary action
|
|
114
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
10/11/2021
|
In reply to point no. 4, details mentioned at para 4 in part II are not matching with details submitted in TEL. Details of 10-20 dia trees as per TEL mentioned in 0-30 cm column in part-II.
|
|
115
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
16/11/2021
|
Sir, The details of trees proposed for disposed in said project have been revised and accordingly updated in para 4-ii in part-II for further necessary action.
|
|
116
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
20/11/2021
|
The correction have been as per instructions received.
|
|
117
|
Nodal Officer
|
REPLY
|
State secretary
|
03/12/2021
|
The correction have been as per instructions received.
|
|
118
|
State secretary
|
REPLY
|
Regional Office
|
03/12/2021
|
The correction have been as per instructions received.
|
|
119
|
Regional Office
|
EDS
|
State secretary
|
20/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
120
|
State secretary
|
EDS
|
Nodal Officer
|
23/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
121
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
23/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
122
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
23/12/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
123
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
03/01/2022
|
Please correct the queries as per the eds attached herewith
|
|
124
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
29/03/2022
|
The correction have been made as per the instruction received
|
|
125
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
31/03/2022
|
Please correct the queries as per the eds attached herewith
|
|
126
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
08/04/2022
|
The correction have been made as per the instruction received
|
|
127
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
11/05/2022
|
Correction has been made as per given instruction
|
|
128
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
13/05/2022
|
Please Review point no. 02 & 03. The reply of point 02 & 03 is not as per instructions received from Govt. of India.
|
|
129
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
17/05/2022
|
Kindly take aerial distance certificate from I.T Cell of Forest Department
|
|
130
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
08/06/2022
|
The correction have been made as per the instruction received
|
|
131
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
16/06/2022
|
Kindly attached the copy of Aerial Distance Certificate from IT Cell of Forest Department
|
|
132
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
27/07/2022
|
The correction have been made as per the instruction received
|
|
133
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
03/08/2022
|
Your letter dated 26-7-222 the area for land transfer is incorrect
|
|
134
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
08/08/2022
|
The correction have been made as per the instruction received
|
|
135
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
27/09/2022
|
For Demo
|
|
136
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
27/09/2022
|
demo
|
|
137
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
01/10/2022
|
As you informed us the area of the projects has been revised. Kindly revised the proposal as per point no-3 as EDS raised by the MoEFCC dated 20.12.2021
|
|
138
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
13/12/2022
|
The correction have been made as per the instruction received
|
|
139
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
10/01/2023
|
Tree List not available
|
|
140
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
03/03/2023
|
The correction have been made as per the instruction received
|
|
141
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
17/03/2023
|
The correction have been made.
|
|
142
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
18/03/2023
|
find the letter attached
|
|
143
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
18/03/2023
|
Find the letter attached
|
|
144
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
21/03/2023
|
Please find the letter attached
|
|
145
|
Nodal Officer
|
REPLY
|
State secretary
|
06/04/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. kindly do the needful.
|
|
146
|
State secretary
|
REPLY
|
Regional Office
|
06/04/2023
|
The correction have been made as per the instruction received
|
|
147
|
Regional Office
|
EDS
|
State secretary
|
04/05/2023
|
The proposal was discussed in the FRCM held on 28 April 2023. State Govt is requested to attend the shortcomings as per the FRCM MoM attached herewith.
|
|
148
|
State secretary
|
EDS
|
Nodal Officer
|
09/05/2023
|
The proposal was discussed in the FRCM held on 28 April 2023. State Govt is requested to attend the shortcomings as per the FRCM MoM attached herewith.
|
|
149
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
09/05/2023
|
The proposal was discussed in the FRCM held on 28 April 2023. State Govt is requested to attend the shortcomings as per the FRCM MoM attached herewith.
|
|
150
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
10/05/2023
|
The proposal was discussed in the FRCM held on 28 April 2023. State Govt is requested to attend the shortcomings as per the FRCM MoM attached herewith.
|
|
151
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
10/05/2023
|
Answer the queries
|
|
152
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
24/07/2023
|
The correction have been made as per the instruction received
|
|
153
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
02/08/2023
|
Letter
|
|
154
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
05/08/2023
|
the reply of objection no 2,3,5 metioned in the letter received from the DFO office is not updated yet and revised data is not updated in the parivesh portal, DFO is required to correct the above mentioned point.
|
|
155
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
08/08/2023
|
The correction have been done.
|
|
156
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
09/08/2023
|
1.no signature of any forest official i.e D.F.O and Ranger are found in part 1 c iii and iv
2. Treen enumration list is not signed by DFO and there is mismatch with the part 2 para 4 ii
3. Also check point no 4 EDS raised by MOeF R.O dated on 04.05.2023
4. There is mismatch in forest area in part 2 i,ii,iii,iv
|
|
157
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
09/08/2023
|
CF has put query on these followings points 1. No signature of any forest official i.e D.F.O and Ranger are found in part 1 c iii and iv 2. Treen enumration list is not signed by DFO and there is mismatch with the part 2 para 4 ii 3. Also check point no 4 EDS raised by MOeF R.O dated on 04.05.2023 4. There is mismatch in forest area in part 2 i,ii,iii,iv
|
|
158
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
19/08/2023
|
The correction have been made as per the instruction received
|
|
159
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
21/08/2023
|
answer the query
|
|
160
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
21/08/2023
|
The correction have been made as per the instruction received
|
|
161
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
18/11/2023
|
Find the letter attached
|
|
162
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
18/11/2023
|
1.no signature of any forest official i.e D.F.O and Ranger are found in part 1 c iii and iv 2. Treen enumration list is not signed by DFO and there is mismatch with the part 2 para 4 ii 3. Also check point no 4 EDS raised by MOeF R.O dated on 04.05.2023 4. There is mismatch in forest area in part 2 i,ii,iii,iv
|
|
163
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
22/11/2023
|
Tree List updated
|
|
164
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
25/11/2023
|
PLEASE CHECK THE PROPOSAL AND ANSWER ACCORDINGLY TO FRCM MOM DATED 28 APRIL 2023 BY IRO IN THE FORWARDING LETTER
1 AREA CHANGE IN PART 1 A AND PART 2 1 IS INCORRECT
CA SUITABALITY CERTIFICATE
DFO SIGN IN MISSING IN PART 1 C iii and iv
ALSO PLEASE CHECK ANY NECESSARY CORRECTION ACCORDINGLY
|
|
165
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
18/01/2024
|
The correction have been made as per the instruction received
|
|
166
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
25/01/2024
|
The correction have been made as per the instruction received
|
|
167
|
Nodal Officer
|
REPLY
|
State secretary
|
29/02/2024
|
The correction have been made as per the instruction received
|
|
168
|
State secretary
|
REPLY
|
Regional Office
|
29/02/2024
|
The correction have been made as per the instruction received
|
|
169
|
Regional Office
|
EDS
|
State secretary
|
30/03/2024
|
EDS dated 29.03.2024 attached
|
|
170
|
State secretary
|
EDS
|
Nodal Officer
|
02/04/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
171
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
05/04/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
172
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
08/04/2024
|
DFO is requested to attend the shortcomings as per the letter attached.
|
|
173
|
DFO (Dehradun)
|
EDS
|
User Agency (eetdrksh@rediffmail.com)
|
10/04/2024
|
Letter Attached
|
|
174
|
User Agency (eetdrksh@rediffmail.com)
|
REPLY
|
DFO (Dehradun)
|
30/04/2024
|
The correction have been made as per the instruction received
|
|
175
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
21/05/2024
|
Letter
|
|
176
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
03/06/2024
|
The correction have been made as per the instruction received
|
|
177
|
Nodal Officer
|
REPLY
|
State secretary
|
15/06/2024
|
The correction have been made as per the instruction received
|
|
178
|
State secretary
|
EDS
|
Nodal Officer
|
04/07/2024
|
Nodal office, Kindly upload EDS reply duly singed by competent authority.
|
|
179
|
Nodal Officer
|
REPLY
|
State secretary
|
18/07/2024
|
As per Attachment
|
|
180
|
State secretary
|
REPLY
|
Regional Office
|
19/07/2024
|
EDS REPLY BY THE NODAL OFFICER
|
|
181
|
Regional Office
|
EDS
|
State secretary
|
02/08/2024
|
State Government is requested to submit reply as per the Agenda Item No.6 of MoM of FRCM attached herewith.
|
|
182
|
State secretary
|
EDS
|
Nodal Officer
|
05/08/2024
|
Kindly Attend EDS query
|
|
183
|
Nodal Officer
|
EDS
|
CF (Shivalik)
|
05/08/2024
|
As per attachment
|
|
184
|
CF (Shivalik)
|
EDS
|
DFO (Dehradun)
|
06/08/2024
|
As per attachment
|
|
185
|
DFO (Dehradun)
|
REPLY
|
CF (Shivalik)
|
09/09/2024
|
Query of Letter
|
|
186
|
CF (Shivalik)
|
REPLY
|
Nodal Officer
|
12/09/2024
|
as per attachment
|
|
187
|
Nodal Officer
|
REPLY
|
State secretary
|
15/10/2024
|
As per attachment
|
|
188
|
State secretary
|
REPLY
|
Regional Office
|
06/11/2024
|
EDS reply by nodal officer
|
|