Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Rudraprayag)
|
EDS
|
User Agency (ukhimathpwd@yahoo.in)
|
25/05/2016
|
Please EDS remove.
|
|
2
|
User Agency (ukhimathpwd@yahoo.in)
|
REPLY
|
DFO (Rudraprayag)
|
25/05/2016
|
The correction have been made as per the instruction received
|
|
3
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
28/05/2016
|
Please remove the objections. 1- Field report of trees and Evaluation of trees are not uploaded. 2- Certificate of Work started DFO unsigned uploaded.
|
|
4
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
02/06/2016
|
Sir,
Field report of trees and Evaluation of trees and Certificate of Work started DFO signed uploaded for part-II
|
|
5
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
06/06/2016
|
Plz reply to obj of RO-As per this office letter Misc/II/ROC/COP/I/2013/1846 dated 6-11-2015 the hard copy is not received through proper channel. The state Govt may advise to assure the receiving of hard copy in regional office before perusing proposal online to this office.
|
|
6
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
08/06/2016
|
Please remove the objections
|
|
7
|
DFO (Rudraprayag)
|
EDS
|
User Agency (ukhimathpwd@yahoo.in)
|
09/06/2016
|
Please sent hard copy Nodal Office.
|
|
8
|
User Agency (ukhimathpwd@yahoo.in)
|
REPLY
|
DFO (Rudraprayag)
|
04/07/2016
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
08/07/2016
|
Sir,
Hard Copy Receiving Letter Uploaded.
|
|
10
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
13/07/2016
|
Sir, Please receive information of the proposal.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
09/08/2016
|
find the letter attached.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
23/08/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
29/08/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
14
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
30/08/2016
|
Please remove the objections
|
|
15
|
DFO (Rudraprayag)
|
EDS
|
User Agency (ukhimathpwd@yahoo.in)
|
30/08/2016
|
Please remove the objections
|
|
16
|
User Agency (ukhimathpwd@yahoo.in)
|
REPLY
|
DFO (Rudraprayag)
|
09/11/2017
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
09/11/2017
|
sir,
proposal objection removed online.
|
|
18
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
13/11/2017
|
Sir please receive the information of the proposal.
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
27/11/2017
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
28/11/2017
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
19/12/2017
|
The following shortcomings are still remained in the reply.
1. The original proposal folder containing original/attested copy of all documents is not yet received in this office.
2. In reply of this office EDS dated 9-8-2016 point 3 the village level committee proceeding of village Temariya is not found attached in the FRA certificate uploaded at para k online Part I.
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
22/12/2017
|
The following shortcomings are still remained in the reply. 1. The original proposal folder containing original/attested copy of all documents is not yet received in this office. 2. In reply of this office EDS dated 9-8-2016 point 3 the village level committee proceeding of village Temariya is not found attached in the FRA certificate uploaded at para k online Part I.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
22/12/2017
|
The following shortcomings are still remained in the reply. 1. The original proposal folder containing original/attested copy of all documents is not yet received in this office. 2. In reply of this office EDS dated 9-8-2016 point 3 the village level committee proceeding of village Temariya is not found attached in the FRA certificate uploaded at para k online Part I.
|
|
24
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
22/12/2017
|
The following shortcomings are still remained in the reply. 1. The original proposal folder containing original/attested copy of all documents is not yet received in this office. 2. In reply of this office EDS dated 9-8-2016 point 3 the village level committee proceeding of village Temariya is not found attached in the FRA certificate uploaded at para k online Part I.
|
|
25
|
DFO (Rudraprayag)
|
EDS
|
User Agency (ukhimathpwd@yahoo.in)
|
22/12/2017
|
The following shortcomings are still remained in the reply. 1. The original proposal folder containing original/attested copy of all documents is not yet received in this office. 2. In reply of this office EDS dated 9-8-2016 point 3 the village level committee proceeding of village Temariya is not found attached in the FRA certificate uploaded at para k online Part I.
|
|
26
|
User Agency (ukhimathpwd@yahoo.in)
|
REPLY
|
DFO (Rudraprayag)
|
08/01/2018
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
09/01/2018
|
sir, proposal objection removed online.
|
|
28
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
15/01/2018
|
sir, please receive the information of the proposal.
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
23/01/2018
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
30/01/2018
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|