Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
20/07/2015
|
Sir,
please upload the copy of DFO signature.
|
|
2
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
27/01/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
11/02/2016
|
sir,
Joint inspection in this case was carried out in the year 2013. After a gap of about 3 year the no and diameter cress of the trees might have changed. Hence fresh joint inspection is required in this matter which is dated on 16-02-2016.
|
|
4
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
30/09/2016
|
The correction have been made as per the instruction received
|
|
5
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
13/10/2016
|
Map of Proposed road, Plantation map and violence certificate of 1980 upload without DFO signature.
|
|
6
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
17/10/2016
|
Map of Proposed road, Plantation map and violence certificate of 1980 upload without DFO signature.
|
|
7
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
08/11/2016
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
11/11/2016
|
sir, please upload again violence certificate of 1980 with DFO Signature.
|
|
9
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
29/11/2016
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
30/11/2016
|
Sir,
Map of Proposed road, Plantation map and violence certificate of 1980 upload with DFO signature.
|
|
11
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
30/11/2016
|
Please give information own office letter with attachment.
|
|
12
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
01/12/2016
|
Sir,
Please give all objections with point wise letter.
|
|
13
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
02/12/2016
|
Please give right information own office letter with attachment.
|
|
14
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
08/12/2016
|
sir,
proposal objections removed.
|
|
15
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
16/12/2016
|
Please remove the objections
|
|
16
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
19/12/2016
|
sir, proposal objections removed online.
|
|
17
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
20/12/2016
|
Plz reply to obj of RO-In view of this office letter Misc/II/ROC/COP/1/2013/1846 dated 6-11-2015 the hard copy of the proposal is still not received in this office. Kindly, provide the same so that further action is to be taken in this matter.
|
|
18
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
22/12/2016
|
Please remove the objecitons
|
|
19
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
22/12/2016
|
Please remove the objecitons
|
|
20
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
20/05/2017
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
22/05/2017
|
Sir,
proposal objection removed.
|
|
22
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
25/05/2017
|
Sir, Please receive information of the proposal
|
|
23
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
08/06/2017
|
find the letter attached
|
|
24
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
08/06/2017
|
Please remove the objecitons
|
|
25
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
09/06/2017
|
Please remove the objecitons
|
|
26
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
06/07/2017
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
07/07/2017
|
Sir, proposal objection removed.
|
|
28
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
13/07/2017
|
Letter No. 116/12-1 Date 12.07.2017
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
24/08/2017
|
State Govt. may attend the shortcomings as per the attachment.
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
25/08/2017
|
State Govt. may attend the shortcomings as per the attachment.
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
29/08/2017
|
The State Govt. has returned the proposal to the Regional Office on 25.08.2017 without attaching the reply of this office 9 points online EDS dated 24.08.2017 instead a copy of this office EDS dated 24.08.2017 only has been attached. State Govt. may submit the reply of EDS dated 24.08.2017.
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
29/08/2017
|
The State Govt. has returned the proposal to the Regional Office on 25.08.2017 without attaching the reply of this office 9 points online EDS dated 24.08.2017 instead a copy of this office EDS dated 24.08.2017 only has been attached. State Govt. may submit the reply of EDS dated 24.08.2017.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
29/08/2017
|
State Govt. may attend the shortcomings as per the attachment.
|
|
34
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
30/08/2017
|
Please remove the objection.
|
|
35
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
30/08/2017
|
Please remove the objection.
|
|
36
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
12/01/2018
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
17/01/2018
|
Sir, proposal objection removed.
|
|
38
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
26/01/2018
|
sir please receive the information of the proposal.
|
|
39
|
Nodal Officer
|
REPLY
|
State secretary
|
02/02/2018
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
40
|
State secretary
|
REPLY
|
Regional Office
|
05/02/2018
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
41
|
Regional Office
|
EDS
|
State secretary
|
21/02/2018
|
State Govt may attend the shortcomings mentioned in attached document.
|
|
42
|
State secretary
|
EDS
|
Nodal Officer
|
22/02/2018
|
State Govt may attend the shortcomings mentioned in attached document.
|
|
43
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
24/02/2018
|
State Govt may attend the shortcomings mentioned in attached document.
|
|
44
|
CF (Garhwal)
|
EDS
|
DFO (Rudraprayag)
|
26/02/2018
|
please remove the objection.
|
|
45
|
DFO (Rudraprayag)
|
EDS
|
User Agency (eepwd_rpg@rediffmail.com)
|
26/02/2018
|
please remove the objection.
|
|
46
|
User Agency (eepwd_rpg@rediffmail.com)
|
REPLY
|
DFO (Rudraprayag)
|
20/04/2018
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Rudraprayag)
|
REPLY
|
CF (Garhwal)
|
24/04/2018
|
Sir, proposal objection removed.
|
|
48
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
28/04/2018
|
sir please receive the information of the proposal.
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
15/05/2018
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
15/05/2018
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|