A. General Details
  (i). Proposal No. : FP/UK/ROAD/11260/2015              (ii). Name of Project for which Forest Land is required : Construction of Bhatrojkhan Nigrali-Bhikiyasain Motor Road.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : A new road of 5.00 Km length to connected Raper-Jeenapani-Majehra Motor Road Km. 16.200 via Uttarakhand Govt. order no. 2454/III-2/05-07(Pra. Aa.)/05 TC-01 dated 28-10-2005 cost Rs. 82.56 Lacs. This road will provide road connectivity to village Majhera, Kumarti, Sorai              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.963
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/11260/201529/03/201526/04/2015  07/04/2015   31/07/2015  25/04/2015   08/02/2016   15/07/2016 Almora :17/07/2016North Kumaun:
  09/01/2020 (Almora)

Uttarakhand:
15/01/2020
Uttarakhand:
21/06/2022
Dehradun:
12/07/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:26/07/2022  
Replied by State Government(Uttarakhand) on:27/08/2024  
Query raised by State Government (Uttarakhand) on:26/07/2022  
Replied by Nodal Officer (Uttarakhand) on:21/08/2024  
Query raised by Nodal Officer (Uttarakhand) on:16/01/2020  
Replied by Circle(North Kumaun) on:12/04/2021  
Query raised by Nodal Officer (Uttarakhand) on:20/04/2021  
Replied by Circle(North Kumaun) on:13/06/2022  
Query raised by Nodal Officer (Uttarakhand) on:29/07/2022  
Replied by Circle(North Kumaun) on:26/06/2024  
Query raised by Circle (North Kumaun) on:18/01/2020  
Replied by DFO (Almora) on:13/07/2020  
Query raised by Circle (North Kumaun) on:27/07/2020  
Replied by DFO (Almora) on:08/04/2021  
Query raised by Circle (North Kumaun) on:29/04/2021  
Replied by DFO (Almora) on:09/02/2022  
Query raised by Circle (North Kumaun) on:24/02/2022  
Replied by DFO (Almora) on:24/02/2022  
Query raised by Circle (North Kumaun) on:04/03/2022  
Replied by DFO (Almora) on:04/05/2022  
Query raised by Circle (North Kumaun) on:06/08/2022  
Replied by DFO (Almora) on:14/05/2024  
Query raised by Circle (North Kumaun) on:01/06/2024  
Replied by DFO (Almora) on:24/06/2024  
Query raised by DFO (Almora) on:22/07/2016  
Replied by UA on :04/02/2017  
Query raised by DFO (Almora) on:09/02/2017  
Replied by UA on :27/03/2017  
Query raised by DFO (Almora) on:28/03/2017  
Replied by UA on :05/06/2019  
Query raised by DFO (Almora) on:13/09/2019  
Replied by UA on :06/12/2019  
Query raised by DFO (Almora) on:24/01/2020  
Replied by UA on :06/07/2020  
Query raised by DFO (Almora) on:05/08/2020  
Replied by UA on :26/08/2020  
Query raised by DFO (Almora) on:12/10/2020  
Replied by UA on :03/11/2020  
Query raised by DFO (Almora) on:07/11/2020  
Replied by UA on :07/04/2021  
Query raised by DFO (Almora) on:30/04/2021  
Replied by UA on :01/07/2021  
Query raised by DFO (Almora) on:02/09/2021  
Replied by UA on :08/09/2021  
Query raised by DFO (Almora) on:10/09/2021  
Replied by UA on :05/10/2021  
Query raised by DFO (Almora) on:23/10/2021  
Replied by UA on :27/10/2021  
Query raised by DFO (Almora) on:30/10/2021  
Replied by UA on :09/11/2021  
Query raised by DFO (Almora) on:29/11/2021  
Replied by UA on :16/12/2021  
Query raised by DFO (Almora) on:04/01/2022  
Replied by UA on :11/01/2022  
Query raised by DFO (Almora) on:15/03/2022  
Replied by UA on :29/04/2022  
Query raised by DFO (Almora) on:16/08/2022  
Replied by UA on :08/09/2022  
Query raised by DFO (Almora) on:22/09/2022  
Replied by UA on :06/12/2022  
Query raised by DFO (Almora) on:02/01/2023  
Replied by UA on :19/01/2023  
Query raised by DFO (Almora) on:27/03/2023  
Replied by UA on :25/04/2023  
Query raised by DFO (Almora) on:15/05/2023  
Replied by UA on :29/04/2024  
NOTE:- Proposal is pending at Regional Office .