Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
16/12/2015
|
Objection
|
|
2
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
12/01/2016
|
Certificate for CA attached.
|
|
3
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
03/02/2016
|
as per latter no 2852/12-1 dated-3-2-2016
|
|
4
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
05/02/2016
|
submit query.
|
|
5
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
01/03/2016
|
Letter regarding submission of Hard copy
|
|
6
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
03/03/2016
|
as per latter no 434 dated-25-02-2016
|
|
7
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
09/03/2016
|
Please edit legal status entered in Form A Part II. Enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FORESTS
|
|
8
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
14/03/2016
|
as per letter no-3365/12-1 dated-14-03-2016.
|
|
9
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
16/03/2016
|
as per latter no 4740 dated-15-03-2016
|
|
10
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
17/03/2016
|
The On line objections raised by Nodal officer/Reg. Officer on date 09.03.2016. has been clarified by DFO almora letter no 4740/12-1 dated 15-03-2016.
|
|
11
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
21/03/2016
|
Enter working plan prescriptions in serial no.5
|
|
12
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
28/03/2016
|
as per letter no-3560/12-1 dated-28-03-2016.
|
|
13
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
02/04/2016
|
as per letter no-4951/12-1(2) dated-28-03-2016.
|
|
14
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
04/04/2016
|
The On line objections raised by Nodal officer/Reg. Officer on date 21-03-2016. has been clarified by almora letter no 495/12-1 dated 03-03-2016.
|
|
15
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
26/05/2016
|
Plz reply to obj of RO-As per this office letter Misc/II/ROC/COP/I/2013/1846 dated 06/11/2015 the hard copy of the proposal is not submitted yet. above mentioned letter attached herewith.
|
|
16
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
28/05/2016
|
Plz reply to obj of RO-As per this office letter Misc/II/ROC/COP/I/2013/1846 dated 06/11/2015 the hard copy of the proposal is not submitted yet. above mentioned letter attached herewith.
|
|
17
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
30/05/2016
|
objection
|
|
18
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
15/06/2016
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
16/06/2016
|
as per letter no-6475/12-1 dated-16-06-2016.
|
|
20
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
18/06/2016
|
The On line objections raised by Nodal officer/Reg. Officer on date 26-05-2016 has been clarified by Almora letter no 6475/12-1 dated 16-06-2016
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
05/07/2016
|
find the letter attached.
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
06/07/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
11/07/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
24
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
13/07/2016
|
send back
|
|
25
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
18/07/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
26
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
20/07/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
27
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
20/07/2016
|
objection
|
|
28
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
02/08/2016
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
05/08/2016
|
as per letter no-882/12-1 dated-05-08-2016.
|
|
30
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
10/08/2016
|
As per latter no. 540/ 12-1 date 10-08-2016
|
|
31
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
16/08/2016
|
Reply is improper and does not correspond to the queries raised by regional office.
|
|
32
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
24/08/2016
|
Reply is improper and does not correspond to the queries raised by regional office.
|
|
33
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
31/08/2016
|
objection
|
|
34
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
31/08/2016
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
12/09/2016
|
as per letter no-1514/12-1 dated-07-09-2016.
|
|
36
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
20/09/2016
|
As per letter no 889/12-1 dated 20-09-2016
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
24/09/2016
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
26/09/2016
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
10/10/2016
|
State Govt. may attend to the shortcomings mentioned in the attached document.
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
13/10/2016
|
State Govt. may attend to the shortcomings mentioned in the attached document.
|
|
41
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
21/10/2016
|
State Govt. may attend to the shortcomings mentioned in the attached document.
|
|
42
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
24/10/2016
|
DFO may provide point wise reply to objections raised by Nodal Office dated 21-10-2016 objection are attached
|
|
43
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
24/10/2016
|
objection
|
|
44
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
25/10/2016
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
25/10/2016
|
as per letter no-2272/12-1 dated-24-10-2016.
|
|
46
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
27/10/2016
|
The On line objections raised by Reg. Office /Nodal officer on date 24-10-2016 has been clarified by DFO Almora letter no 2272/12-1 dated 24-10-2016
|
|
47
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
01/11/2016
|
objection not rectified
|
|
48
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
01/11/2016
|
objection not rectified
|
|
49
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
01/11/2016
|
objection not rectified
|
|
50
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
01/11/2016
|
The correction have been made as per the instruction received
|
|
51
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
02/11/2016
|
objection remove date 02-11-2016
|
|
52
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
02/11/2016
|
objection not rectified
|
|
53
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
04/11/2016
|
as per letter no-2272/12-1 dated-24-10-2016.
|
|
54
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
10/11/2016
|
The On line objections raised by Reg. Office /Nodal officer on date 24-10-2016 has been clarified by DFO Almora letter no 2272/12-1 dated 24-10-2016
|
|
55
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
14/11/2016
|
upload CA report in serial no 13 in part-ii
|
|
56
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
14/11/2016
|
upload CA report in serial no 13 in part-ii
|
|
57
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
15/11/2016
|
objection remove
|
|
58
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
15/11/2016
|
The On line objections raised by Reg. Office /Nodal officer on date 14-11-2016 has been clarified by DFO Almora letter no 2523/12-1 dated 14-11-2016
|
|
59
|
Nodal Officer
|
REPLY
|
State secretary
|
16/11/2016
|
The raised queries have been rectified as per asking & sending the concerned proposal completely online for your kind in formation&further action.
|
|
60
|
State secretary
|
REPLY
|
Regional Office
|
17/11/2016
|
The raised queries have been rectified as per asking & sending the concerned proposal completely online for your kind in formation&further action.
|
|
61
|
Regional Office
|
EDS
|
State secretary
|
25/11/2016
|
State Govt may attend to the shortcomings mentioned in the attached document.
|
|
62
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
28/11/2016
|
send back
|
|
63
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
02/12/2016
|
objection remove
|
|
64
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
07/12/2016
|
please remove the objection raised by RO
|
|
65
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
07/12/2016
|
please remove the objection raised by RO
|
|
66
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
08/12/2016
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
08/12/2016
|
The correction have been made as per the instruction received
|
|
68
|
State secretary
|
REPLY
|
Regional Office
|
13/12/2016
|
the asked queries have been corrected and attach herewith in Eds Letter column.
|
|
69
|
Regional Office
|
EDS
|
State secretary
|
16/12/2016
|
State Govt may attend shortcomings as per the attachment.
|
|
70
|
State secretary
|
EDS
|
Nodal Officer
|
19/12/2016
|
State Govt may attend shortcomings as per the attachment.
|
|
71
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
23/12/2016
|
State Govt may attend shortcomings as per the attachment.
|
|
72
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
23/12/2016
|
State Govt may attend shortcomings as per the attachment.
|
|
73
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
23/12/2016
|
State Govt. may attend shortcomings as per the attachment
|
|
74
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
24/12/2016
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Almora)
|
EDS
|
User Agency (eepdrani@yahoo.com)
|
26/12/2016
|
objection not rectified
|
|
76
|
User Agency (eepdrani@yahoo.com)
|
REPLY
|
DFO (Almora)
|
26/12/2016
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
26/12/2016
|
objection remove
|
|
78
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
27/12/2016
|
objection remove
|
|
79
|
Nodal Officer
|
REPLY
|
State secretary
|
27/12/2016
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|
80
|
State secretary
|
REPLY
|
Regional Office
|
28/12/2016
|
ShortComing in the proposal are removed as per enclosed attachemnt.
|
|