Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
12/06/2015
|
As per enclose letter no 2909/12-1 dated 12-06-2015
|
|
2
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
23/06/2015
|
As per your letter 2909/12-1 date 12-06-2015 we have fill all details in pdf form
|
|
3
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
24/06/2015
|
plz upload correct SIR report
|
|
4
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
25/06/2015
|
As per your letter 2909/12-1 date 12-06-2015 we have fill all details in pdf form
|
|
5
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
26/06/2015
|
As per enclose letter no 3072/12-1 dated 26-06-2015
|
|
6
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
30/06/2015
|
As per your letter 3072/12-1 date 26-06-2015 we have fill all details in pdf form
|
|
7
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
03/07/2015
|
plz upload correct SIR report Date
|
|
8
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
10/07/2015
|
Please find the attached file of SIR REPORT
|
|
9
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
13/07/2015
|
Please attached SIR REPORT fOrm A part II
|
|
10
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
15/07/2015
|
please find enclosed
|
|
11
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
20/07/2015
|
As per enclosed letter no 197/12-1 dated 20-07-2015
|
|
12
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
24/07/2015
|
please find enclosed
|
|
13
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
26/08/2015
|
II Alignment tree list Attached
|
|
14
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
26/08/2015
|
please find attachment
|
|
15
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
27/08/2015
|
plz re-upload pdf file need and clean
|
|
16
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
02/09/2015
|
please find attachment
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
15/09/2015
|
1.Please review entry in serial no. 5,6,7,12,13 of Form A Part II 2. Please enter Revenue Forests for Civil soyam forests in serial no.2 regarding legal status of forests3.Please provide compartment wise area details of RF involved.4. recommendation of DFO is erroneous
|
|
18
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
16/09/2015
|
As per letter no 1087/12-1 dated 16-09-2015
|
|
19
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
18/09/2015
|
please find enclosed
|
|
20
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
21/10/2015
|
objection removed
|
|
21
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
23/10/2015
|
please find enclosed and ensure resolution of point number three given in the letter
|
|
22
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
03/11/2015
|
objection removed
|
|
23
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
09/11/2015
|
please find enclosed
|
|
24
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
16/11/2015
|
The On line objections raised by Nodal officer/Reg. Officer on date 15.09.2015 has been clarified by DFO Bageshwar latter no 1624/12-1 dated 07-11-2015
|
|
25
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
17/11/2015
|
Kindly provide compartment wise area details of Reserved Forests involved in the proposal
|
|
26
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
19/11/2015
|
As per letter no 1952/12-1 dated 19-11-2015
|
|
27
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
20/11/2015
|
please find enclosed
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
21/11/2015
|
The On line objections raised by Nodal officer/Reg. Officer on date 17.11.2015 has been clarified by DFO Bageshwar latter no 1686/12-1 dated 19-11-2015
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
04/12/2015
|
The online proposal is returned back since hard copy has not been submitted to this office simultaneously. State Govt. may resubmit the proposal online after hard copy has been provided in Regional Office. As a proof scanned copy of the receipt of hard copy from the Regional Office may also be uploaded along with online proposal. Attached Letter No. Misc./II/ROC/COP/1/2013/1846 Dated 06.11.2015 may also be referred in this regard.
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
07/12/2015
|
Plz reply to obj of RO-The online proposal is returned back since hard copy has not been submitted to this office simultaneously. State Govt. may resubmit the proposal online after hard copy has been provided in Regional Office. As a proof scanned copy of the receipt of hard copy from the Regional Office may also be uploaded along with online proposal. Attached Letter No. Misc./II/ROC/COP/1/2013/1846 Dated 06.11.2015 may also be referred in this regard.
|
|
31
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
14/12/2015
|
Plz reply to obj of RO-The online proposal is returned back since hard copy has not been submitted to this office simultaneously. State Govt. may resubmit the proposal online after hard copy has been provided in Regional Office. As a proof scanned copy of the receipt of hard copy from the Regional Office may also be uploaded along with online proposal. Attached Letter No. Misc./II/ROC/COP/1/2013/1846 Dated 06.11.2015 may also be referred in this regard.
|
|
32
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
15/12/2015
|
As per latter no 2265/12-1 dated 15-12-2015
|
|
33
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
15/12/2015
|
please find enclosed
|
|
34
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
10/02/2016
|
Hard Copy of Proposal is being sand Latter No 172/2E.F.L., Dt. 01.02.2016
|
|
35
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
15/02/2016
|
please provide additional hard copy of the proposal not the hard copy you submitted in our office.
|
|
36
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
24/02/2016
|
additional hard copy already received by Nodal Office Deharadun on Dt. 03.02.2016 Vide Latter No 172/2E.F.L., Dt. 01.02.2016
|
|
37
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
25/02/2016
|
please provide acknowledgement latter received form nodal office
|
|
38
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
26/02/2016
|
additional hard copy already received by Nodal Office Deharadun on Dt. 03.02.2016 Vide Latter No 172/2E.F.L., Dt. 01.02.2016 acknowledgement latter received form nodal office
|
|
39
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
27/02/2016
|
please find enclosed
|
|
40
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
27/02/2016
|
The On line objections raised by Nodal officer/Reg. Officer on date 14.12.2015 has been clarified by DFO bageshwar latter no 2470/12-1 dated 25-02-2016.
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
03/03/2016
|
Correction has done. You are requested to do the needfull.
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
09/03/2016
|
Correction has done. You are requested to do the needfull.
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
21/03/2016
|
find the letter attached.
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
21/03/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
45
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
31/03/2016
|
Plz reply to obj of RO-find the letter attached.
|
|
46
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
01/04/2016
|
as per letter no-3626/12-1 dated-01-04-2016.
|
|
47
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
04/04/2016
|
please find enclosed
|
|
48
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
04/05/2016
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
07/05/2016
|
please find enclosed
|
|
50
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
03/06/2016
|
as per letter no 4409/12-1 dated 31-05-2016
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
08/06/2016
|
Required documents uploaded for your further necessary action.
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
10/06/2016
|
Required documents uploaded for your further necessary action.
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
17/06/2016
|
In the reply of the State Govt vide letter dated 8-06-2016 uploaded on 10-06-2016, the reply submitted only for 5 points of this EDS dated 21-03-2016. point no.6 to 9 are remained unattended by the State Govt. The State Govt may review this office EDS dated 21-03-2016 and submit complete reply to this office for further action.
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
17/06/2016
|
Plz reply to obj of RO-In the reply of the State Govt vide letter dated 8-06-2016 uploaded on 10-06-2016, the reply submitted only for 5 points of this EDS dated 21-03-2016. point no.6 to 9 are remained unattended by the State Govt. The State Govt may review this office EDS dated 21-03-2016 and submit complete reply to this office for further action.
|
|
55
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
22/06/2016
|
Plz reply to obj of RO-In the reply of the State Govt vide letter dated 8-06-2016 uploaded on 10-06-2016, the reply submitted only for 5 points of this EDS dated 21-03-2016. point no.6 to 9 are remained unattended by the State Govt. The State Govt may review this office EDS dated 21-03-2016 and submit complete reply to this office for further action.
|
|
56
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/06/2016
|
Plz reply to obj of RO-In the reply of the State Govt vide letter dated 8-06-2016 uploaded on 10-06-2016, the reply submitted only for 5 points of this EDS dated 21-03-2016. point no.6 to 9 are remained unattended by the State Govt. The State Govt may review this office EDS dated 21-03-2016 and submit complete reply to this office for further action.
|
|
57
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
23/06/2016
|
Plz reply to obj of RO-In the reply of the State Govt vide letter dated 8-06-2016 uploaded on 10-06-2016, the reply submitted only for 5 points of this EDS dated 21-03-2016. point no.6 to 9 are remained unattended by the State Govt. The State Govt may review this office EDS dated 21-03-2016 and submit complete reply to this office for further action.
|
|
58
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
15/07/2016
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
18/07/2016
|
please check KML file ...
|
|
60
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
12/09/2016
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
27/09/2016
|
please find enclosed
|
|
62
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
01/10/2016
|
As per letter no 1029/12-1 dated 30-09-2016
|
|
63
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
07/10/2016
|
. No correction has been done by user agency in Form A part- i for points 1,2.3,5,6,7 and 8 of objections raised by regional office
|
|
64
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
10/10/2016
|
No correction has been done by user agency in Form A part- i for points 1,2.3,5,6,7 and 8 of objections raised by regional office
|
|
65
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
13/10/2016
|
No correction has been done by user agency in Form A part- i for points 1,2.3,5,6,7 and 8 of objections raised by regional office
|
|
66
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
14/10/2016
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
18/10/2016
|
please find enclosed
|
|
68
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
26/10/2016
|
As per letter no 1245/12-1 dated 24-10-2016 encloser are send in E-mail
|
|
69
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
22/11/2016
|
find the letter
|
|
70
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
25/11/2016
|
Plz Send RO
|
|
71
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
30/11/2016
|
find the letter attached
|
|
72
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
01/12/2016
|
find the letter attached
|
|
73
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
06/12/2016
|
plz find enclosed
|
|
74
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
22/12/2016
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
27/12/2016
|
please find enclosed
|
|
76
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
02/01/2017
|
As per letter no 1974/12-1 dated 02-01-2017
|
|
77
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/01/2017
|
find the letter attached
|
|
78
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
17/01/2017
|
find the letter attached
|
|
79
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
18/01/2017
|
please find enclosed
|
|
80
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
28/01/2017
|
The correction have been made as per the instruction received
|
|
81
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
09/02/2017
|
please find enclosed
|
|
82
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
20/02/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 12-01-2017 has been clarified by DFO Bageshwar letter no 2033/12-1 dated 09-02-2017
|
|
83
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
06/03/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
84
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
06/03/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The DFO may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
85
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
17/03/2017
|
The hard copy of the proposal containing original documents is not yet received to the CF office. The UA may provide original hard copy of the proposal to CF office including authenticated copy of Part I to Part V as in online web portal.
|
|
86
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
05/04/2017
|
The correction have been made as per the instruction received
|
|
87
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
15/04/2017
|
please find enclosed
|
|
88
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
17/04/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 06-03-2017 has been clarified by DFO Bageshwar letter no 2559/12-1 dated 10-04-2017
|
|
89
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
06/05/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
90
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
09/05/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
91
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
11/05/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
92
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
15/07/2017
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
10/08/2017
|
please find enclosed
|
|
94
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
11/08/2017
|
DFO may provide point wise reply to objections from regional office plz send ans in your office letter.
|
|
95
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
24/08/2017
|
please find enclosed
|
|
96
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
25/08/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 06-05-2017 has been clarified by DFO Bageshwar letter no 445/12-1 dated 24-08-2017
|
|
97
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
04/09/2017
|
find the letter attached
|
|
98
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
04/09/2017
|
find the letter attached
|
|
99
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
11/09/2017
|
please find enclosed
|
|
100
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/11/2017
|
The correction have been made as per the instruction received
|
|
101
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
08/11/2017
|
please find enclosed
|
|
102
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
09/11/2017
|
Plz attached Dfo Letter
|
|
103
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
23/11/2017
|
please find enclosed
|
|
104
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
23/11/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 04-09-2017 has been clarified by DFO Bageshwar letter no 1155/12-1 dated 22-11-2017
|
|
105
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/12/2017
|
1.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.
2.please upload C/B analysis in serial no G in form A part-i
3.Please enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FOREST
4. Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 5.Please review entries in serial 8-i regarding wildlife present and its movement.
|
|
106
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
12/12/2017
|
1.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details. 2.please upload C/B analysis in serial no G in form A part-i 3.Please enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FOREST 4. Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 5.Please review entries in serial 8-i regarding wildlife present and its movement.
|
|
107
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
14/12/2017
|
1.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details. 2.please upload C/B analysis in serial no G in form A part-i 3.Please enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FOREST 4. Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 5.Please review entries in serial 8-i regarding wildlife present and its movement
|
|
108
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
22/12/2017
|
The correction have been made as per the instruction received
|
|
109
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
22/12/2017
|
please find enclosed
|
|
110
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
22/12/2017
|
The On line objections raised by Reg. Office /Nodal officer on date 12-12-2017 has been clarified by DFO P.W.D Bageshwar letter no 7976/2 E.V.Bhu dated 21-12-2017
|
|
111
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
22/12/2017
|
objection not rectified yet-1.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details. 2.please upload C/B analysis in serial no G in form A part-i 3.Please enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FOREST 4. Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 5.Please review entries in serial 8-i regarding wildlife present and its movement.
|
|
112
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/12/2017
|
objection not rectified yet-1.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details. 2.please upload C/B analysis in serial no G in form A part-i 3.Please enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FOREST 4. Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 5.Please review entries in serial 8-i regarding wildlife present and its movement.
|
|
113
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
23/12/2017
|
objection not rectified yet-1.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details. 2.please upload C/B analysis in serial no G in form A part-i 3.Please enter VILLAGE FORESTS for Van Panchayat area instead of PROTECTED FOREST 4. Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 5.Please review entries in serial 8-i regarding wildlife present and its movement.
|
|
114
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
28/12/2017
|
The correction have been made as per the instruction received
|
|
115
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
17/03/2018
|
please find enclosed
|
|
116
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
20/03/2018
|
The On line objections raised by Reg. Office /Nodal officer on date 22-12-2017 has been clarified by DFO Bageshwar letter no 2185/12-1 dated 17-03-2018
|
|
117
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
26/03/2018
|
find the letter attached
|
|
118
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
02/04/2018
|
find the letter attached
|
|
119
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
02/04/2018
|
please find enclosed
|
|
120
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
23/05/2018
|
The correction have been made as per the instruction received
|
|
121
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
23/06/2018
|
plz find enclosed
|
|
122
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
26/06/2018
|
The On line objections raised by Reg. Office /Nodal officer on date 26-03-2018 has been clarified by DFO Bageshwar letter no 3040/12-1 dated 22-06-2018
|
|
123
|
Nodal Officer
|
REPLY
|
State secretary
|
02/07/2018
|
Required documents uploaded for your further necessary action.
|
|
124
|
State secretary
|
REPLY
|
Regional Office
|
05/07/2018
|
Required documents uploaded for your further necessary action.
|
|
125
|
Regional Office
|
EDS
|
State secretary
|
13/08/2018
|
The case was discussed in the REC meeting held on 23.07.2018 and decided to subject to fulfillment the following condition as per the minutes of REC meeting uploaded in the web portal.
|
|
126
|
State secretary
|
EDS
|
Nodal Officer
|
14/08/2018
|
The case was discussed in the REC meeting held on 23.07.2018 and decided to subject to fulfillment the following condition as per the minutes of REC meeting uploaded in the web portal.
|
|
127
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
14/08/2018
|
The case was discussed in the REC meeting held on 23.07.2018 and decided to subject to fulfillment the following condition as per the minutes of REC meeting uploaded in the web portal.
|
|
128
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/08/2018
|
The case was discussed in the REC meeting held on 23.07.2018 and decided to subject to fulfillment the following condition as per the minutes of REC meeting uploaded in the web portal.
|
|
129
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
28/08/2018
|
plz find enclosed
|
|
130
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
01/11/2018
|
The correction have been made as per the instruction received
|
|
131
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
19/11/2018
|
plz find enclosed
|
|
132
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
26/11/2018
|
The On line objections raised by Reg. Office /Nodal officer on date 14-08-2018 has been clarified by DFO Bageshwar letter no 1306/12-1 dated 19-11-2018
|
|
133
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
26/11/2018
|
State Govt. may attend the following shortcomings as per attachment.
|
|
134
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
27/11/2018
|
State Govt. may attend the following shortcomings as per attachment.
|
|
135
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
29/11/2018
|
plz find enclosed
|
|
136
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
15/12/2018
|
The correction have been made as per the instruction received
|
|
137
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
21/01/2019
|
plz find enclosed
|
|
138
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
22/01/2019
|
The On line objections raised by Reg. Office /Nodal officer on date 26-11-2018 has been clarified by DFO Bageshwar letter no 1808/12- 1 Date 21-01-2019
|
|
139
|
Nodal Officer
|
REPLY
|
State secretary
|
02/02/2019
|
Required documents uploaded for your further necessary action.
|
|
140
|
State secretary
|
REPLY
|
Regional Office
|
04/02/2019
|
Required documents uploaded for your further necessary action.
|
|