Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Boudh)
|
EDS
|
User Agency (ehtc.div.ang@optcl.co.in)
|
03/08/2022
|
Comply the observations
|
|
2
|
User Agency (ehtc.div.ang@optcl.co.in)
|
REPLY
|
DFO (Boudh)
|
04/04/2023
|
The correction have been made as per the instruction received
|
|
3
|
CF (Berhampur)
|
EDS
|
DFO (Boudh)
|
04/05/2023
|
you are requested to submit a report about violation committed in details
|
|
4
|
DFO (Boudh)
|
EDS
|
User Agency (ehtc.div.ang@optcl.co.in)
|
22/05/2023
|
Comply the observations
|
|
5
|
User Agency (ehtc.div.ang@optcl.co.in)
|
REPLY
|
DFO (Boudh)
|
21/06/2023
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Boudh)
|
REPLY
|
CF (Berhampur)
|
21/06/2023
|
EDS complied
|
|
7
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
06/07/2023
|
Please comply the EDS vide this office Memo No. 13518 dated 06.07.2023
|
|
8
|
CF (Berhampur)
|
EDS
|
DFO (Boudh)
|
11/07/2023
|
Requsted to upload Part-I KML file of Phulbani Division
|
|
9
|
CF (Berhampur)
|
EDS
|
DFO (Phulbani)
|
11/07/2023
|
Requsted to upload Part-I KML file of Phulbani Division
|
|
10
|
DFO (Boudh)
|
EDS
|
User Agency (ehtc.div.ang@optcl.co.in)
|
13/07/2023
|
Comply the observations
|
|
11
|
User Agency (ehtc.div.ang@optcl.co.in)
|
REPLY
|
DFO (Boudh)
|
25/07/2023
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Boudh)
|
REPLY
|
CF (Berhampur)
|
27/07/2023
|
Observations complied
|
|
13
|
DFO (Phulbani)
|
REPLY
|
CF (Berhampur)
|
04/08/2023
|
Village wise KML file uploaded
|
|
14
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
11/08/2023
|
Village wise KML file uploaded by the DFO Phulbani & Boudh Division
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
31/08/2023
|
Addl information sought from the State Govt.
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
12/09/2023
|
For necessary compliance
|
|
17
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
16/09/2023
|
Please comply the EDS vide this office Memo No. 18684 dated 15.09.2023
|
|
18
|
CF (Berhampur)
|
EDS
|
DFO (Boudh)
|
21/09/2023
|
The DFO Phulbani & Boudh division may be requested to submit the compliance report
|
|
19
|
CF (Berhampur)
|
EDS
|
DFO (Phulbani)
|
21/09/2023
|
The DFO Phulbani & Boudh division may be requested to submit the compliance report
|
|
20
|
DFO (Boudh)
|
EDS
|
User Agency (ehtc.div.ang@optcl.co.in)
|
01/12/2023
|
You are requested to submit the geo location of all the Transmission towers erected on the forest land within the ambit of Boudh Forest Division for taking further action at this end.
|
|
21
|
User Agency (ehtc.div.ang@optcl.co.in)
|
REPLY
|
DFO (Boudh)
|
31/01/2024
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Boudh)
|
REPLY
|
CF (Berhampur)
|
01/02/2024
|
Observations complied
|
|
23
|
DFO (Phulbani)
|
REPLY
|
CF (Berhampur)
|
01/03/2024
|
Action taken report by Collector, Kandhamal
|
|
24
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
04/03/2024
|
The DFO Boudh Division has submitted the point wise compliance as sought by Govt of India
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
04/03/2024
|
Compliance submitted to GoI, MOEF & CC vide this office Memo No.2320 dated 06.02.2024.
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
12/03/2024
|
Compliance furnished by PCCF (FD&NO, FC Act), O/o the PCCF & HoFF, Odisha vide letter dtd.06.02.2024
|
|