TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/TRANS/149711/2021              (ii). Name of Project for which Forest Land is required : : Construction of 132 KV DC Line on DC Tower from existing 132/33 KV Phulbani, Kandhamal district Grid Sub-Station to 132/33 KV Grid Sub-Station at Boudh, Boudh district.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : In order to improve the quality and reliability of power supply to the transmission line from existing 132/33KV Phulbani Grid Sub-Station, Kandhamal district to 132/33KV Grid Sub-Station at Boudh, Boudh district.              (iv). File no. : 5-ORC592/2023-BHU              (v). State : Orissa              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 30.469
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/TRANS/149711/202130/11/2021aa02/12/2021   15/07/2022

Boudh :18/07/2022


Phulbani :18/07/2022

Berhampur:
  15/04/2023 (Boudh)

Berhampur:
  22/04/2023 (Phulbani)

Orissa:
26/06/2023
Orissa:
16/08/2023
Bhubaneswar:
18/08/2023
27/11/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhubaneswar) on:31/08/2023  
Replied by State Government(Orissa) on:12/03/2024  
Query raised by State Government (Orissa) on:12/09/2023  
Replied by Nodal Officer (Orissa) on:04/03/2024  
Query raised by Nodal Officer (Orissa) on:06/07/2023  
Replied by Circle(Berhampur) on:11/08/2023  
Query raised by Nodal Officer (Orissa) on:16/09/2023  
Replied by Circle(Berhampur) on:04/03/2024  
Query raised by Circle (Berhampur) on:04/05/2023  
Replied by DFO (Boudh) on:21/06/2023  
Query raised by Circle (Berhampur) on:11/07/2023  
Replied by DFO (Boudh) on:27/07/2023  
Query raised by Circle (Berhampur) on:11/07/2023  
Replied by DFO (Phulbani) on:04/08/2023  
Query raised by Circle (Berhampur) on:21/09/2023  
Replied by DFO (Boudh) on:01/02/2024  
Query raised by Circle (Berhampur) on:21/09/2023  
Replied by DFO (Phulbani) on:01/03/2024  
Query raised by DFO (Boudh) on:03/08/2022  
Replied by UA on :04/04/2023  
Query raised by DFO (Boudh) on:22/05/2023  
Replied by UA on :21/06/2023  
Query raised by DFO (Boudh) on:13/07/2023  
Replied by UA on :25/07/2023  
Query raised by DFO (Boudh) on:01/12/2023  
Replied by UA on :31/01/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .