Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Yawal)
|
EDS
|
User Agency (sdo0233@gmail.com)
|
09/07/2018
|
correct the area deatils
|
|
2
|
User Agency (sdo0233@gmail.com)
|
REPLY
|
DFO (Yawal)
|
13/07/2018
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (Dhule)
|
21/12/2019
|
on line proposal non forest area not shown in portal
|
|
4
|
CF (Dhule)
|
REPLY
|
Nodal Officer
|
18/01/2020
|
send
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
06/12/2021
|
Addl Info Sought
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
07/12/2021
|
pls. provide the information sought by the GoI
|
|
7
|
Nodal Officer
|
EDS
|
CF (Dhule)
|
08/12/2021
|
Query raised by this office letter dt 15-11-21.
|
|
8
|
CF (Dhule)
|
REPLY
|
Nodal Officer
|
02/03/2022
|
Query has been corrected
|
|
9
|
Nodal Officer
|
EDS
|
CF (Dhule)
|
10/03/2022
|
Query raised by this office letter dt 10-03-22
|
|
10
|
CF (Dhule)
|
EDS
|
DFO (Yawal)
|
09/06/2022
|
KML file Query raised by this office letter dt 09-06-22
|
|
11
|
DFO (Yawal)
|
REPLY
|
CF (Dhule)
|
13/06/2022
|
Query has been resolved
|
|
12
|
CF (Dhule)
|
REPLY
|
Nodal Officer
|
13/06/2022
|
Query has been resolved
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
16/06/2022
|
Query compliance
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
17/06/2022
|
for necessary action
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
13/08/2022
|
Addl Info Sought
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
21/08/2022
|
provide the indormation / documents sought by the Regional Office
|
|
17
|
Nodal Officer
|
EDS
|
CF (Dhule)
|
22/08/2022
|
For query compliance
|
|
18
|
CF (Dhule)
|
EDS
|
DFO (Yawal)
|
07/09/2022
|
Kindly resolved the query raised by nodal office
|
|
19
|
DFO (Yawal)
|
REPLY
|
CF (Dhule)
|
19/12/2022
|
Query has been resolved
|
|
20
|
CF (Dhule)
|
REPLY
|
Nodal Officer
|
20/12/2022
|
Queries has been resolved
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
22/12/2022
|
Query compliance
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
26/12/2022
|
for further necessary action
|
|
23
|
Regional Office
|
EDS
|
State secretary
|
13/01/2023
|
Addl Info Sought
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
13/01/2023
|
provide the indormation / documents sought by the Regional Office
|
|
25
|
Nodal Officer
|
EDS
|
CF (Dhule)
|
17/01/2023
|
For query compliance
|
|
26
|
CF (Dhule)
|
EDS
|
DFO (Yawal)
|
18/01/2023
|
For query compliance
|
|
27
|
DFO (Yawal)
|
REPLY
|
CF (Dhule)
|
09/03/2023
|
33 KV Transmission Electric line
|
|
28
|
CF (Dhule)
|
REPLY
|
Nodal Officer
|
09/03/2023
|
compliances been done
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
10/03/2023
|
Query Compliance
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
05/06/2023
|
for necessary action
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
08/06/2023
|
Requisite KML file has not been submitted. Kindly arrange to send the same.
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
12/06/2023
|
IRO, MOEF&CC has conveyed that requisite KML file has not been received. Kindly arrange to send the same.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
13/06/2023
|
Query Compliance
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
14/06/2023
|
for necessary action
|
|