Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Kundapur)
|
EDS
|
User Agency (varahisubdivisionno3@gmail.com)
|
03/02/2022
|
As per letter
|
|
2
|
User Agency (varahisubdivisionno3@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
05/02/2022
|
The correction have been made as per the instruction received
|
|
3
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
19/05/2022
|
As small portion of land belongs to KCDC. the user agency needs to obtain NOC from KCDC Ltd.
|
|
4
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
19/05/2022
|
As per letter
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
25/11/2022
|
State Government has been requested vide letter dated 25-11-2022 to furnish the justification given by User Agency that by avoiding forest area, details on discarding the alternatives, examination of quantifiable assessment of feasible alternatives and authentication of compliance report by State Government.
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
06/12/2022
|
eds
|
|
7
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
15/12/2022
|
please obtain revised information from DCF and UA
|
|
8
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
20/12/2022
|
kindly provide revised information
|
|
9
|
DFO (Kundapur)
|
EDS
|
User Agency (varahisubdivisionno3@gmail.com)
|
20/12/2022
|
Principal Chief Conservator of Forests FC and Nodal Officer FCA Bangalore in his letter dated 14-12-2022 asked to provide Clarification-information
|
|
10
|
User Agency (varahisubdivisionno3@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
23/12/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
29/12/2022
|
As per letter
|
|
12
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
31/12/2022
|
Submitted the compliance report after obtaining from DCF Kundapura
|
|
13
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
03/02/2023
|
please obtain the rquired information from DCF and Field officers
|
|
14
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
04/02/2023
|
kindly provide required information
|
|
15
|
DFO (Kundapur)
|
EDS
|
User Agency (varahisubdivisionno3@gmail.com)
|
13/02/2023
|
As per letter
|
|
16
|
User Agency (varahisubdivisionno3@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
15/02/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
22/02/2023
|
As per letter
|
|
18
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
01/03/2023
|
Information obtained from DCF is hereby submitted
|
|
19
|
Nodal Officer
|
REPLY
|
State secretary
|
05/04/2023
|
the information sought by GOI is hereby enclosed
|
|
20
|
State secretary
|
REPLY
|
Regional Office
|
24/04/2023
|
eds
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
12/05/2023
|
State Government has been requested vide letter dated 12-05-2023 to furnish the certified complete compliance report in respect of diversion of 15.4 ha and 129.60 ha.
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
17/05/2023
|
eds
|
|
23
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
03/06/2023
|
please submit the information sought by GOI
|
|
24
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
16/06/2023
|
Kindly provide required information
|
|
25
|
DFO (Kundapur)
|
EDS
|
User Agency (varahisubdivisionno3@gmail.com)
|
30/06/2023
|
As per letter
|
|
26
|
User Agency (varahisubdivisionno3@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
23/08/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
28/08/2023
|
As per letter
|
|
28
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
31/08/2023
|
Information obtained from DCF is hereby submitted
|
|
29
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
25/09/2023
|
please obtain the complete information from DCF and UA
|
|
30
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
27/09/2023
|
Kindly Provide required information
|
|
31
|
DFO (Kundapur)
|
EDS
|
User Agency (varahisubdivisionno3@gmail.com)
|
10/10/2023
|
As per letter
|
|
32
|
User Agency (varahisubdivisionno3@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
16/01/2024
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Kundapur)
|
EDS
|
User Agency (varahisubdivisionno3@gmail.com)
|
03/04/2024
|
As per letter
|
|
34
|
User Agency (varahisubdivisionno3@gmail.com)
|
REPLY
|
DFO (Kundapur)
|
04/04/2025
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Kundapur)
|
REPLY
|
CF (Mangalore)
|
27/05/2025
|
As per letter
|
|
36
|
CF (Mangalore)
|
REPLY
|
Nodal Officer
|
31/05/2025
|
The EDS report received from the Deputy Conservator of Forests, Kundapura Division, Kundapura is here with submitted for further needful action.
|
|
37
|
Nodal Officer
|
EDS
|
CF (Mangalore)
|
05/07/2025
|
Please submit the complete CA land details 15.04 ha and 129 ha in attached format and compliance to the GOI monitoring report dated 03-02-2023
|
|
38
|
CF (Mangalore)
|
EDS
|
DFO (Kundapur)
|
09/07/2025
|
You are directed to submit complete CA land details pertaining to the diversion of 15.4 ha and 129.60 ha along with compliance report pertaining to the 129.60 ha based on the monitoring report of the Government of India communicated vide letter dated 03-02-2023. CA land details must include status of transfer, mutation and notification in the attached format.
|
|