Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
09/04/2021
|
Hard Copy is not received, please submit hard copy.
|
|
2
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
19/04/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
04/06/2021
|
Proposal folders submitted in O/O DFO Urban is incomplete and check list 14 was not found in the folder. You are therefore requested to submit the complete folder to this office so that if may be processed and submitted for further necessary action. Please submit the complete folders.
|
|
4
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
09/06/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
14/06/2021
|
Area recommended for diversion in the column No . 2 is not commensurate with the recommendation uploaded in shape of part-II. Please correct the same at the earliest possible.
|
|
6
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
14/06/2021
|
Revised recommendation in shape of Part-II is uploaded against the additional information details column.
|
|
7
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
02/07/2021
|
Shortcomings as attached may be attended at the earliest please.
|
|
8
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
02/07/2021
|
Shortcomings noticed by the Nodal Office FCA is attached.
|
|
9
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
02/07/2021
|
observations have been attended and hard copies of Land suitability certificate is being sent seperately.
|
|
10
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
02/07/2021
|
Hard copy of the land suitability certificate w.r.t area proposed for CA has been submitted in your good office.
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
02/08/2021
|
EDS
|
|
12
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
02/08/2021
|
ACS observations
|
|
13
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
02/08/2021
|
Shortcomings noticed by the GoHP
|
|
14
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
03/08/2021
|
shortcomings noticed by the GoHP
|
|
15
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
04/09/2021
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
13/09/2021
|
necessary correction have been made as per the instruction received
|
|
17
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
18/10/2021
|
reply attached
|
|
18
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
01/11/2021
|
The comments of CWLW stands are being sent herewith. Please upload the same against additional information details column of online Part-II under intimation to this office.
|
|
19
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
22/11/2021
|
he comments of CWLW stands are being sent herewith. Please upload the same against additional information details column of online Part-II under intimation to this office.
|
|
20
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
22/11/2021
|
Needful done now.
|
|
21
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
22/11/2021
|
Needful done now.
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
26/11/2021
|
Complete reply
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
24/02/2022
|
ACS Forest raised some observations
|
|
24
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/02/2022
|
ACS Forest raised some observations
|
|
25
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
06/03/2022
|
Shortcomings noticed as per attachment
|
|
26
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
07/03/2022
|
Shortcomings noticed as per attachment
|
|
27
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
23/04/2022
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
04/05/2022
|
The correction have been made as per the instrution
|
|
29
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
11/05/2022
|
The correction are incomplete so.
|
|
30
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
24/06/2022
|
As per EDS
|
|
31
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
21/07/2022
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
25/07/2022
|
As per EDS
|
|
33
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
26/07/2022
|
reply attached
|
|
34
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
30/07/2022
|
eds
|
|
35
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
30/07/2022
|
EDS as per attachment
|
|
36
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
02/08/2022
|
EDS attached
|
|
37
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
07/08/2022
|
The correction have been made as per the instruction received
|
|
38
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
12/08/2022
|
EDS attached
|
|
39
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
16/08/2022
|
The correction have been made as per the instruction received
|
|
40
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
16/08/2022
|
The correction have been made as per the instruction received.
|
|
41
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
16/08/2022
|
Reply of eds is attached
|
|
42
|
Nodal Officer
|
REPLY
|
State secretary
|
22/08/2022
|
Complete reply
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
01/10/2022
|
The State Government may attend the shortcomings attached herewith.
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
12/10/2022
|
EDS
|
|
45
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
14/10/2022
|
EDS
|
|
46
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
14/10/2022
|
EDS
|
|
47
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
18/10/2022
|
The correction have been made as per the instruction received
|
|
48
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
15/03/2023
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
24/03/2023
|
EDS attached
|
|
50
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
28/03/2023
|
Reply is given as per attachment
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
20/04/2023
|
Complete reply is submitted
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
20/04/2023
|
Complete reply is submitted
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
26/07/2023
|
EDS
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
31/07/2023
|
eds
|
|
55
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
31/07/2023
|
eds
|
|
56
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
01/08/2023
|
eds
|
|
57
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
26/08/2023
|
Your are requested to submit the digital map. toposheet for the CA site with KML file
|
|
58
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
20/09/2023
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
20/10/2023
|
EDS attached
|
|
60
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
25/10/2023
|
KML of ca site has not uploaded.
|
|
61
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
25/10/2023
|
KML file of CA site Same has been uploaded as per instruction
|
|
62
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
02/11/2023
|
Reply given as per attachment
|
|
63
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
14/11/2023
|
EDS
|
|
64
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
16/11/2023
|
EDS
|
|
65
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
01/12/2023
|
EDS attached
|
|
66
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
07/12/2023
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
12/12/2023
|
The correction have been made as per the instruction received (copy of reply is attached)
|
|
68
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
18/12/2023
|
Respect Sir,
Please find herewith the reply of DFO Urban on the matter cited above.
|
|
69
|
Nodal Officer
|
REPLY
|
State secretary
|
20/12/2023
|
Complete reply is submitted
|
|
70
|
State secretary
|
REPLY
|
Regional Office
|
20/12/2023
|
Complete reply is submitted
|
|
71
|
Regional Office
|
EDS
|
State secretary
|
24/01/2024
|
the State government may attend the shortcomings attached herewith.
|
|
72
|
State secretary
|
EDS
|
Nodal Officer
|
24/01/2024
|
EDS
|
|
73
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
24/01/2024
|
EDS
|
|
74
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
27/01/2024
|
Please find herewith the attachment of subject cited matter.
|
|
75
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
29/01/2024
|
EDS attached
|
|
76
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
09/07/2024
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
22/07/2024
|
as per your reply correct the area and submit the same
|
|
78
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
06/08/2024
|
The correction have been made as per the instruction received
|
|
79
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
21/08/2024
|
EDS attached
|
|
80
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
28/08/2024
|
Reply given as per attachment
|
|
81
|
Nodal Officer
|
REPLY
|
State secretary
|
10/09/2024
|
Complete reply is submitted
|
|
82
|
State secretary
|
REPLY
|
Regional Office
|
10/09/2024
|
Complete reply is submitted
|
|
83
|
Regional Office
|
EDS
|
State secretary
|
03/10/2024
|
The State Govt. may attend the shortcomings attached herewith.
|
|
84
|
State secretary
|
EDS
|
Nodal Officer
|
07/10/2024
|
EDS
|
|
85
|
Nodal Officer
|
EDS
|
CF (Shimla)
|
07/10/2024
|
EDS
|
|
86
|
CF (Shimla)
|
EDS
|
DFO (Shimla MC)
|
08/10/2024
|
eds
|
|
87
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
28/10/2024
|
EDS attached
|
|
88
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
13/11/2024
|
The correction have been made as per the instruction received
|
|
89
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
20/11/2024
|
The reply submitted by you is not satifactory. You are therefore requested to do the needfull. The hard copy of the reply submit to this office, so that further action could be taken accordingly
|
|
90
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
28/11/2024
|
The correction have been made as per the instruction received
|
|
91
|
DFO (Shimla MC)
|
EDS
|
User Agency (mcs_shimla@yahoo.com)
|
07/12/2024
|
he reply as per point No.1 isubmitted by you is not satifactory. You are therefore requested to do the needfull.t
|
|
92
|
User Agency (mcs_shimla@yahoo.com)
|
REPLY
|
DFO (Shimla MC)
|
30/12/2024
|
The correction have been made as per the instruction received
|
|
93
|
DFO (Shimla MC)
|
REPLY
|
CF (Shimla)
|
10/01/2025
|
Need full has been done
|
|
94
|
CF (Shimla)
|
REPLY
|
Nodal Officer
|
13/01/2025
|
need full has been done
|
|
95
|
Nodal Officer
|
REPLY
|
State secretary
|
15/01/2025
|
Complete reply is submitted
|
|
96
|
State secretary
|
REPLY
|
Regional Office
|
15/01/2025
|
Complete reply is submitted
|
|