TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/39377/2019              (ii). Name of Project for which Forest Land is required : C/O Link road from Rajera (Bhaniya) bailly km 0/0 to 4/500.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Himachal Pradesh Govt. has proposed to C/O Link road from Rajera (Bhaniya) Bailly mototrable link road 0/0 to4/500 which bifuricates from Chakki Banikhet Chamba Bharmour road NH-154A. The entire length of the road involved in forest land i.e. 3.700 Kms and rest is private land is 0.800 Km. To              (iv). File no. : 8B/HP/06/32/2020/FC              (v). State : Himachal Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.37
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/39377/201912/03/201922/03/2019   06/05/2019   21/05/2019   01/07/2019 Chamba :02/07/2019Chamba:
  09/10/2019 (Chamba)

Himachal Pradesh:
21/10/2019
Himachal Pradesh:
06/02/2020
Shimla:
04/03/2020
23/07/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:30/04/2020  
Replied by State Government(Himachal Pradesh) on:10/07/2020  
Query raised by State Government (Himachal Pradesh) on:08/05/2020  
Replied by Nodal Officer (Himachal Pradesh) on:10/07/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:30/10/2019  
Replied by Circle(Chamba) on:07/12/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:16/12/2019  
Replied by Circle(Chamba) on:04/01/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:08/05/2020  
Replied by Circle(Chamba) on:01/06/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:11/06/2020  
Replied by Circle(Chamba) on:23/06/2020  
Query raised by Circle (Chamba) on:30/10/2019  
Replied by DFO (Chamba) on:30/11/2019  
Query raised by Circle (Chamba) on:16/12/2019  
Replied by DFO (Chamba) on:24/12/2019  
Query raised by Circle (Chamba) on:12/05/2020  
Replied by DFO (Chamba) on:21/05/2020  
Query raised by Circle (Chamba) on:11/06/2020  
Replied by DFO (Chamba) on:22/06/2020  
Query raised by DFO (Chamba) on:30/08/2019  
Replied by UA on :23/09/2019  
Query raised by DFO (Chamba) on:31/10/2019  
Replied by UA on :13/11/2019  
Query raised by DFO (Chamba) on:29/11/2019  
Replied by UA on :29/11/2019  
Query raised by DFO (Chamba) on:12/05/2020  
Replied by UA on :13/05/2020  
Query raised by DFO (Chamba) on:15/06/2020  
Replied by UA on :17/06/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .