| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
03/09/2021
|
Check Case
|
|
|
2
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
03/09/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
09/11/2021
|
38 No Check list incomplete
|
|
|
4
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
27/11/2021
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
29/11/2021
|
38 No check list not correct
|
|
|
6
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
01/12/2021
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
02/12/2021
|
check list Correction.
|
|
|
8
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
02/12/2021
|
The correction have been made as per the instruction received
|
|
|
9
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
14/12/2021
|
EDS
|
|
|
10
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
17/12/2021
|
In online part I signature has been left which may be done.
|
|
|
11
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
17/12/2021
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
30/12/2021
|
EDS Reply.
|
|
|
13
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
01/01/2022
|
EDS
|
|
|
14
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
13/01/2022
|
EDS Raised.
|
|
|
15
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
03/02/2022
|
The correction have been made as per the instruction received
|
|
|
16
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
24/02/2022
|
Proposed road alignment and alternate are not match
|
|
|
17
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
04/03/2022
|
The correction have been made as per the instruction received
|
|
|
18
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
07/03/2022
|
p
|
|
|
19
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
07/03/2022
|
The correction have been made as per the instruction received
|
|
|
20
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
07/03/2022
|
EDS Reply.
|
|
|
21
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
07/03/2022
|
Please upload all requisite document.
|
|
|
22
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
07/03/2022
|
EDS Reply.
|
|
|
23
|
State secretary
|
EDS
|
Nodal Officer
|
28/05/2022
|
ACS observations
|
|
|
24
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
28/05/2022
|
ACS raised some observations
|
|
|
25
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
30/05/2022
|
EDS
|
|
|
26
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
31/05/2022
|
Please attend the observation
|
|
|
27
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
13/06/2022
|
The correction have been made as per the instruction received
|
|
|
28
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
17/06/2022
|
Needful has been done
|
|
|
29
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
22/06/2022
|
EDS
|
|
|
30
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
24/06/2022
|
You are requested to provide the location of the village i.e.Jabbal Ka bag,Kandaiwala, Kharkon, with all alignments considered and also the status of forest land involved ,RF,PF,UPF etc on the KML file to justify the proposal.
|
|
|
31
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
27/08/2022
|
The correction have been made as per the instruction received
|
|
|
32
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
30/08/2022
|
Needful has been done
|
|
|
33
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
12/09/2022
|
Reclamation plan has not been uploaded, please upload.
|
|
|
34
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
12/09/2022
|
Needful has been done
|
|
|
35
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
14/09/2022
|
Needful has been done.
|
|
|
36
|
Nodal Officer
|
REPLY
|
State secretary
|
30/09/2022
|
Complete reply is submitted please.
|
|
|
37
|
Regional Office
|
EDS
|
State secretary
|
05/12/2022
|
EDS
|
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
06/12/2022
|
EDS
|
|
|
39
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
06/12/2022
|
EDS
|
|
|
40
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
08/12/2022
|
EDS
|
|
|
41
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
12/12/2022
|
Please attend the observation
|
|
|
42
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
20/11/2023
|
The correction have been made as per the instruction received
|
|
|
43
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
22/12/2023
|
Please submit Soil and Moisture conservation plan.
|
|
|
44
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
08/01/2024
|
The correction have been made as per the instruction received
|
|
|
45
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
10/01/2024
|
Please attend the observation raised by Integrated Regional Office Shimla ,MOEF Shimla letter No. FC/HPC/06/172/2022 dated 05.12.2022
Point No. 7,8,9 and 10
|
|
|
46
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
12/02/2024
|
The correction have been made as per the instruction received
|
|
|
47
|
DFO (Nahan)
|
EDS
|
User Agency (raujifsheikh@gmail.com)
|
15/02/2024
|
Dumping site has not been mentioned in KML File
|
|
|
48
|
User Agency (raujifsheikh@gmail.com)
|
REPLY
|
DFO (Nahan)
|
13/03/2024
|
The correction have been made as per the instruction received
|
|
|
49
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
18/04/2024
|
Needful has been done
|
|
|
50
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
26/04/2024
|
Needful has been done.
|
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
15/05/2024
|
Complete reply is submitted
|
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
15/05/2024
|
Complete reply is submitted
|
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
19/07/2024
|
The State Government may attend the sortcomings attached herewith.
|
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
19/07/2024
|
eds
|
|
|
55
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
19/07/2024
|
eds
|
|
|
56
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
19/07/2024
|
EDS
|
|
|
57
|
DFO (Nahan)
|
EDS
|
User Agency (hp-nah@nic.in)
|
20/07/2024
|
Please attend the observation
|
|
|
58
|
User Agency (hp-nah@nic.in)
|
REPLY
|
DFO (Nahan)
|
31/08/2024
|
The correction have been made as per the instruction received
|
|
|
59
|
DFO (Nahan)
|
EDS
|
User Agency (hp-nah@nic.in)
|
06/09/2024
|
Please submit the correct KML File and submit the reply of Point No.1
|
|
|
60
|
User Agency (hp-nah@nic.in)
|
REPLY
|
DFO (Nahan)
|
22/09/2024
|
The correction have been made as per the instruction received
|
|
|
61
|
DFO (Nahan)
|
EDS
|
User Agency (hp-nah@nic.in)
|
27/09/2024
|
Please submit the correct the dumping site in KML File
|
|
|
62
|
User Agency (hp-nah@nic.in)
|
REPLY
|
DFO (Nahan)
|
07/10/2024
|
The correction have been made as per the instruction received
|
|
|
63
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
08/10/2024
|
Needful has been done
|
|
|
64
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
10/10/2024
|
In reference to the observation No. 1, The comments of DFO concerned is not mentioned in the letter.
|
|
|
65
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
25/10/2024
|
Needful has been done
|
|
|
66
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
28/10/2024
|
Needful has been done.
|
|
|
67
|
Nodal Officer
|
EDS
|
CF (Nahan)
|
06/11/2024
|
The reply of observation No. 1 is incomplete, the reply is silent about the detail of violation as asked by GoI vide letter dated 5-12-2022, necessary comments/ detail of violation may be provided.
|
|
|
68
|
CF (Nahan)
|
EDS
|
DFO (Nahan)
|
06/11/2024
|
The reply of observation No. 1 is incomplete, the reply is silent about the detail of violation as asked by GoI vide letter dated 5-12-2022, necessary comments/ detail of violation may be provided.
|
|
|
69
|
DFO (Nahan)
|
EDS
|
User Agency (hp-nah@nic.in)
|
06/11/2024
|
The reply of observation No. 1 is incomplete, the reply is silent about the detail of violation as asked by GoI vide letter dated 5-12-2022, necessary comments/ detail of violation may be provided.
|
|
|
70
|
User Agency (hp-nah@nic.in)
|
REPLY
|
DFO (Nahan)
|
21/11/2024
|
The correction have been made as per the instruction received
|
|
|
71
|
DFO (Nahan)
|
REPLY
|
CF (Nahan)
|
27/11/2024
|
Needful has been done
|
|
|
72
|
CF (Nahan)
|
REPLY
|
Nodal Officer
|
28/11/2024
|
Needful has been done.
|
|
|
73
|
Nodal Officer
|
REPLY
|
State secretary
|
04/12/2024
|
Complete reply is submitted
|
|
|
74
|
State secretary
|
REPLY
|
Regional Office
|
04/12/2024
|
Complete reply is submitted
|
|