TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/AP/ROAD/29874/2017              (ii). Name of Project for which Forest Land is required : Upgradation of NH-167B from Km 99/103 to 191/050 i.e from CS puram to Singarayakonda (Old NH 16 ) to two lanes with paved shoulders under NHDP IV in the State of Andhra Pradesh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The existing highway from Km.131/090 to 133/790 is passing through Botlagudur RF ,from Km.141/015 to 141/620 is passing through Bodawada RF and from Km.141/620 to 142/700 ,from 143/560 to 145/750 is passing through Malakonda RF of Kanigiri Range of Giddalur Division of Andhra Pradesh. In order to im              (iv). File no. : 4-APC129/2021-VIJ              (v). State : Andhra Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 9.33
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AP/ROAD/29874/201728/11/2017aa01/12/2017   13/12/201713/12/2017 Giddalur :13/12/2017Guntur:
  06/10/2018 (Giddalur)

Andhra Pradesh:
11/10/2018
Andhra Pradesh:
30/10/2018
Vijayawada:
07/07/2021
30/03/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Vijayawada) on:18/08/2021  
Replied by State Government(Andhra Pradesh) on:11/01/2022  
Query raised by State Government (Andhra Pradesh) on:15/03/2020  
Replied by Nodal Officer (Andhra Pradesh) on:22/06/2020  
Query raised by State Government (Andhra Pradesh) on:29/06/2020  
Replied by Nodal Officer (Andhra Pradesh) on:14/08/2020  
Query raised by State Government (Andhra Pradesh) on:01/09/2020  
Replied by Nodal Officer (Andhra Pradesh) on:20/04/2021  
Query raised by State Government (Andhra Pradesh) on:07/09/2021  
Replied by Nodal Officer (Andhra Pradesh) on:23/11/2021  
Query raised by Nodal Officer (Andhra Pradesh) on:09/10/2020  
Replied by Circle(Guntur) on:23/03/2021  
Query raised by Nodal Officer (Andhra Pradesh) on:09/09/2021  
Replied by Circle(Guntur) on:28/10/2021  
Query raised by Circle (Guntur) on:10/10/2018  
Replied by DFO (Giddalur) on:10/10/2018  
Query raised by Circle (Guntur) on:22/10/2020  
Replied by DFO (Giddalur) on:17/03/2021  
Query raised by Circle (Guntur) on:13/09/2021  
Replied by DFO (Giddalur) on:21/10/2021  
Query raised by DFO (Giddalur) on:28/10/2020  
Replied by UA on :05/11/2020  
Query raised by DFO (Giddalur) on:15/12/2020  
Replied by UA on :04/01/2021  
Query raised by DFO (Giddalur) on:07/10/2021  
Replied by UA on :08/10/2021  
NOTE:- Stage-I Approval accorded by : Regional Office .