Sno. | State Name | Proposal No. | RO/Ministry File Number | Proposal Name | Category | User Agency Name | Area (ha.) | Proposal Status | Important Dates | Allocation of Fresh forest land (Form-A) Part-I | View Report (Part-II to Part-V and Stage-I Clearances) | Stage-II Approval on |
1
|
Andhra Pradesh
|
FP/AP/OFC/62261/2020
|
4-APB188/2022-VIJ
|
Laying of Under Ground Optical Fiber Cable (OFC) between Udayagiri-Duttalur
|
Optical Fibre Cable
|
JIO DIGITAL FIBRE PRIVATE LIMITED
|
0.19
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Nov 2020
|
Stage-I Approval on
|
:
|
26 Sep 2022
|
Compliance Report Submitted by User Agency on
|
:
|
31 Oct 2023
|
|
|
|
|
2
|
Andhra Pradesh
|
FP/AP/TRANS/25855/2017
|
G.O.Rt.No.127
|
132KV DC/SC line from 132/33KV SS Vengalayapalem to 25KV RTSS, Nallapadu
|
Transmission Line
|
EXECUTIVE ENGINEER CONSTRUCTION DIVISION APTRANSCO GUNTUR
|
0.51
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
26 Apr 2017
|
Stage-I Approval on
|
:
|
22 Jun 2017
|
Compliance Report Submitted by User Agency on
|
:
|
20 Nov 2019
|
|
|
|
|
3
|
Andhra Pradesh
|
FP/AP/QRY/37853/2018
|
4-APB095/2019-CHNpart
|
Dara Apparao Quarry Lease
|
Quarrying
|
DARA APPARAO
|
4.49
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Dec 2018
|
Stage-I Approval on
|
:
|
13 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
23 May 2025
|
|
|
|
|
4
|
Andhra Pradesh
|
FP/AP/OFC/41711/2019
|
4-APB122/202-VIJ
|
BSNL OPTICAL FIBRE CABLE LAYING
|
Optical Fibre Cable
|
DET OFP BSNL VIJAYAWADA
|
0.21
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
03 Sep 2019
|
Stage-I Approval on
|
:
|
24 May 2021
|
Compliance Report Submitted by User Agency on
|
:
|
09 Dec 2021
|
|
|
|
|
5
|
Andhra Pradesh
|
FP/AP/OFC/128499/2021
|
4-APB140/2021-VIJ
|
Execution of optical Fiber Network (IPI.) Project Nellore District, Andhra Pradesh State.
|
Optical Fibre Cable
|
M/S VINDHYA TELELINKS LTD
|
0.12
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
11 Mar 2021
|
Stage-I Approval on
|
:
|
22 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
29 Apr 2025
|
|
|
|
|
6
|
Andhra Pradesh
|
FP/AP/Others/144722/2021
|
4-APB212/2023-VIJ
|
Krishnapatnam Hyderabad Pipeline project
|
Others
|
BHARAT PETROLEUM CORP LTD
|
2.72
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
13 Jul 2021
|
Stage-I Approval on
|
:
|
16 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
31 Oct 2023
|
|
|
|
|
7
|
Bihar
|
FP/BR/ROAD/21381/2016
|
FP/BR/ROAD/21381/2016
|
Baysi-Bahadurganj-Dighalbank section of SH-99
|
Road
|
BIHAR STATE ROAD DEVELOPMENT CORPORATION
|
69.178
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
13 Sep 2016
|
Stage-I Approval on
|
:
|
04 Oct 2023
|
Compliance Report Submitted by User Agency on
|
:
|
14 Nov 2023
|
|
|
|
|
8
|
Chhattisgarh
|
FP/CG/MIN/41389/2019
|
8-41/2017-FC Vol.
|
GEVRA OPENCAST PROJECT
|
Mining
|
SOUTH EASTERN COALFIELDS LTD
|
94.293
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Nov 2019
|
Stage-I Approval on
|
:
|
09 Feb 2024
|
Compliance Report Submitted by User Agency on
|
:
|
08 Jul 2025
|
|
|
|
|
9
|
Chhattisgarh
|
FP/CG/Others/27773/2017
|
FC-I/IROCH-07/2021
|
govt polytechnic building for skill upgradation
|
Others
|
GOVTPOLYKANKER
|
4.309
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 Aug 2017
|
Stage-I Approval on
|
:
|
08 Feb 2022
|
Compliance Report Submitted by User Agency on
|
:
|
16 Apr 2025
|
|
|
|
|
10
|
Goa
|
FP/GA/ROAD/19984/2016
|
F.No.GOC1237/2020-BAN
|
FDP:NH-17, Goa
|
Road
|
PUBLIC WORKS DEPARTMENT
|
29.836
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 Jun 2016
|
Stage-I Approval on
|
:
|
10 Oct 2022
|
Compliance Report Submitted by User Agency on
|
:
|
17 Dec 2024
|
|
|
|
|
11
|
Gujarat
|
FP/GJ/Others/39408/2019
|
FC-6/GJB-2/2022-GNR
|
Proposal for laying OFC for Reliance Jio Infocomm Limited 4G Kutch District
|
Others
|
RELIANCE JIO INFOCOMM LTD
|
0.2138
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Mar 2019
|
Stage-I Approval on
|
:
|
25 Jan 2022
|
Compliance Report Submitted by User Agency on
|
:
|
09 May 2025
|
|
|
|
|
12
|
Gujarat
|
FP/GJ/WATER/82029/2020
|
6-GJB051/2021-BHO
|
Diversion of 0.098 Ha. Forest land for laying Two 6" (inch) dia PVC pipeline for irrigation and drinking water
|
Drinking Water
|
KHUNTI RANMALBHAI
|
0.098
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
10 Dec 2020
|
Stage-I Approval on
|
:
|
13 May 2021
|
Compliance Report Submitted by User Agency on
|
:
|
15 Jul 2022
|
|
|
|
|
13
|
Gujarat
|
FP/GJ/TRANS/143615/2021
|
FC-6/GJB-47/2022-GNR
|
Construction of 33 kV transmission line from Ratadiya PSS to WTG locations of Adani Wind Energy Kutchh Five Limited
|
Transmission Line
|
ADANI WIND ENERGY KUTCH FIVE LIMITED
|
0.0346
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
17 Jun 2021
|
Stage-I Approval on
|
:
|
21 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
17 Dec 2022
|
|
|
|
|
14
|
Gujarat
|
FP/GJ/ROAD/47665/2020
|
8-108/1993-FC Vol.
|
Construction of Ambaji Bypass Road ( k.m. 2/950 to 5/150 ) on himmatnagar-Kheroj-Ambaji-Aburoad Road S.H.-9
|
Road
|
PUBLIC WORK DEPARTMENT
|
9.9
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Jul 2020
|
Stage-I Approval on
|
:
|
21 Apr 2022
|
Compliance Report Submitted by User Agency on
|
:
|
14 Dec 2022
|
|
|
|
|
15
|
Gujarat
|
FP/GJ/TRANS/140743/2021
|
6-GJB096/2021-BHO
|
66KV S/C Kangashiyali (220KV) (GETCO) - Siddheshwar underground cable line with 1C x 630 sq mm (3+1 spare) XLPE power cable line
|
Transmission Line
|
GUJARAT ENERGY TRANSMISSION CORP LTD
|
0.427
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
06 Apr 2021
|
Stage-I Approval on
|
:
|
03 Jan 2022
|
Compliance Report Submitted by User Agency on
|
:
|
25 Jan 2022
|
|
|
|
|
16
|
Gujarat
|
FP/GJ/Others/50281/2020
|
FC-6/GJB-40/2022-GNR
|
Proposal for laying OFC for Jio Digital Fibre Pvt. Ltd. Patan District
|
Others
|
JIO DIGITAL FIBER PRIVATE LIMITED
|
0.2934
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Sep 2020
|
Stage-I Approval on
|
:
|
05 Sep 2022
|
Compliance Report Submitted by User Agency on
|
:
|
26 Apr 2024
|
|
|
|
|
17
|
Gujarat
|
FP/GJ/ROAD/38381/2019
|
6-GJC059/2019-BHO
|
Proposal for diversion of protected forest land for the project of Four laning of Pragatipath section Suigam - Limbuni - Masali - Madhpura - Boru - Dudhosan road Ch. 0/00 to 20/750
|
Road
|
EXECUTIVE ENGINEER, BANASKANTHA
|
22.44375
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
17 Jan 2019
|
Stage-I Approval on
|
:
|
30 Oct 2020
|
Compliance Report Submitted by User Agency on
|
:
|
16 Feb 2024
|
|
|
|
|
18
|
Gujarat
|
FP/GJ/WATER/65572/2020
|
6-GJC037/2021-BHO
|
Drinking Water Supply to population of Gandhinagar City (24 x 7) under Smart City
|
Drinking Water
|
GUJARAT WATER SUPPLY & SEWARAGE BOARD
|
9.9372
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
27 Nov 2020
|
Stage-I Approval on
|
:
|
27 May 2021
|
Compliance Report Submitted by User Agency on
|
:
|
17 Jul 2025
|
|
|
|
|
19
|
Haryana
|
FP/HR/WATER/37285/2018
|
9045
|
DRINKING WATER PIPELINE FROM JANAULI TO ASAOTI
|
Drinking Water
|
PUBLIC HEALTH ENGINEERING DIVISION PALWAL
|
0.702
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
02 Dec 2018
|
Stage-I Approval on
|
:
|
16 Nov 2019
|
Compliance Report Submitted by User Agency on
|
:
|
27 May 2024
|
|
|
|
|
20
|
Haryana
|
FP/HR/WATER/36116/2018
|
9-HRB002-2019-CHA
|
Masitan Water Works
|
Drinking Water
|
EXECUTIVE ENGINEER PUBLIC HEALTH
|
0.5548
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Sep 2018
|
Stage-I Approval on
|
:
|
17 Jan 2019
|
Compliance Report Submitted by User Agency on
|
:
|
27 Jun 2025
|
|
|
|
|
21
|
Haryana
|
FP/HR/ROAD/151320/2022
|
D-III-10324
|
Diversion of 0.7934 hac. of Forest Land for construction of 2 Lane ROB on LC No. – 114 on Mandi Adampur to Daroli Road at Adampur in Distt. - Hisar (HR).
|
Road
|
PROVINCIAL DIVISION PWD B&R BR., HISAR
|
0.7934
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Jan 2022
|
Stage-I Approval on
|
:
|
06 Jul 2022
|
Compliance Report Submitted by User Agency on
|
:
|
16 Jan 2025
|
|
|
|
|
22
|
Haryana
|
FP/HR/ROAD/145587/2021
|
10152
|
Widening and strengthening of road from Narwana to Tohana MDR-111 district Jind Haryana.
|
Road
|
SDE PWD B&R NARWANA
|
0.85
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Aug 2021
|
Stage-I Approval on
|
:
|
15 Dec 2021
|
Compliance Report Submitted by User Agency on
|
:
|
12 May 2024
|
|
|
|
|
23
|
Haryana
|
FP/HR/Approach/49517/2020
|
9-HRB001-2021-CHA
|
Om Parkash Education Society
|
Approach Access
|
OM PARKASH EDUCATION SOCIETY
|
0.003
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Sep 2020
|
Stage-I Approval on
|
:
|
03 Feb 2021
|
Compliance Report Submitted by User Agency on
|
:
|
11 Sep 2025
|
|
|
|
|
24
|
Himachal Pradesh
|
FP/HP/ROAD/150882/2022
|
FC/HPB/06/06/144/2022
|
Construction of Ghat Paucha Pai Road
|
Road
|
HIMACHAL PRADESH PUBLIC WORK DEPARTMENT
|
2.462
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Jan 2022
|
Stage-I Approval on
|
:
|
01 Mar 2024
|
Compliance Report Submitted by User Agency on
|
:
|
08 Oct 2025
|
|
|
|
|
25
|
Himachal Pradesh
|
FP/HP/HYD/36856/2018
|
8B/HP/01/57/2020/FC
|
Grahan Kasol Hydro Power
|
Hydel
|
M/S DINESH BUTAIL
|
1.6201
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
18 Nov 2018
|
Stage-I Approval on
|
:
|
22 Jan 2025
|
Compliance Report Submitted by User Agency on
|
:
|
08 Oct 2025
|
|
|
|
|
26
|
Jammu and Kashmir
|
FP/JK/ROAD/142163/2021
|
FST-Land0FC/91/2021-02
|
BRO PROJECT SAMPARK 31TF 110 RCC CONSTRUCTION OF MALAI BRIDGE(KM 55.05),KHURD(KM 53.45) BRIDGE ON RAM(REASI ARNAS MAHORE) ROAD
|
Road
|
BRO, 110 RCC
|
0.362
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
17 May 2021
|
Stage-I Approval on
|
:
|
06 Oct 2021
|
Compliance Report Submitted by User Agency on
|
:
|
20 Sep 2025
|
|
|
|
|
27
|
Jammu and Kashmir
|
FP/JK/ROAD/149888/2021
|
9-JKC-004/2023- Jammu
|
Construction/Improvement from CL-09 to NHDL specifications of road Dayalchak-Ramkot (Challan) KM 8.00 to KM 25.421 (Net length 17.421 Km) in J&K (UT)
|
Road
|
69 RCC BORDER ROADS ORGANIZATION
|
12.0147
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Dec 2021
|
Stage-I Approval on
|
:
|
12 Jun 2023
|
Compliance Report Submitted by User Agency on
|
:
|
20 Jun 2025
|
|
|
|
|
28
|
Jharkhand
|
FP/JH/TRANS/31258/2018
|
FP/JH/TRANS/31258/2018
|
JUSNL-NIT-43-220KV-Jasidih-Giridih Transmission Line
|
Transmission Line
|
JUSNL
|
53.7504
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
30 Mar 2018
|
Stage-I Approval on
|
:
|
03 May 2019
|
Compliance Report Submitted by User Agency on
|
:
|
26 Dec 2024
|
|
|
|
|
29
|
Jharkhand
|
FP/JH/MIN/8374/2014
|
8-62/2018-FC
|
K.D Hesalong opencast project
|
Mining
|
CENTRAL COALFIELDS LIMITED
|
126.72
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
05 Dec 2014
|
Stage-I Approval on
|
:
|
27 Feb 2023
|
Compliance Report Submitted by User Agency on
|
:
|
09 Oct 2023
|
|
|
|
|
30
|
Jharkhand
|
FP/JH/Others/27162/2017
|
FP/JH/Others/27162/2017
|
Jagdishpur-Haldia-Bokaro-Dhamra Pipeline (JHBDPL) Project of GAIL
|
Others
|
GAIL INDIA LIMITED
|
113.4947
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
01 Sep 2017
|
Stage-I Approval on
|
:
|
28 Jul 2019
|
Compliance Report Submitted by User Agency on
|
:
|
06 Aug 2025
|
|
|
|
|
31
|
Karnataka
|
FP/KA/TRANS/152682/2022
|
F. No.4-KRC1468/2023-BAN
|
Construction of 137.701 Kms of 400 KV Quad D/C Koppal PS- Narendra (New) Transmission Line passing through forest land in Sy No. 50/1 Mannerala Village and Sy No. 70/1,70/2, 70/3, 71, 73 and 89 of Mavinaitagi Village, Hanamasagara Hobli, Kushtagi Taluk, Koppal District for a length of 1.644 Kms (7.562 Ha.) by Koppal-Narendra Transmission Limited
|
Transmission Line
|
KOPPAL-NARENDRA TRANSMISSION LIMITED
|
7.562
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
22 Feb 2022
|
Stage-I Approval on
|
:
|
02 Aug 2023
|
Compliance Report Submitted by User Agency on
|
:
|
13 Sep 2025
|
|
|
|
|
32
|
Karnataka
|
FP/KA/IRRIG/45295/2020
|
No.4-KRB1253/2020-BAN
|
Laying of 490 mm Dia MS Pipe Line for Lifting / pumping the secondary treated water from Kandavara lake to Poornasagara kere and onwards to fill tanks in Chikkaballapura Districts
|
Irrigation
|
EXECUTIVE ENGINEER MINOR IRRIGATION AND GROUD WATER RESOURCE DIVISION CHIKKABALAPURA
|
0.15
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Apr 2020
|
Stage-I Approval on
|
:
|
12 Aug 2020
|
Compliance Report Submitted by User Agency on
|
:
|
21 Aug 2025
|
|
|
|
|
33
|
Karnataka
|
FP/KA/WATER/39356/2019
|
F.No.4-KRB1309/2021-BAN
|
Construction of Jack well, Panel Room with allied components and laying of Pipe lines in Chliandavadi State Forest, Muguru State Forest, Bilikal State Forest for Providing Drinking Water supply for Kodihalli & 298 Habitations under DBOT in Kanakapura Taluka Ramanagara District”
|
Drinking Water
|
EXECUTIVE ENGINEER RDWSD RAMNAGARA
|
3.61
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
09 Mar 2019
|
Stage-I Approval on
|
:
|
25 Sep 2023
|
Compliance Report Submitted by User Agency on
|
:
|
05 Apr 2025
|
|
|
|
|
34
|
Karnataka
|
FP/KA/IRRIG/35763/2018
|
4-KRB1221/2020
|
Laying of pipeline to fill 60 tanks of Harpanahalli Taluk from Tungabhadra River
|
Irrigation
|
EXECUTIVE ENGINEER KNNL BHADRA CANAL DIVISION DAVANGERE
|
0.54
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
19 Sep 2018
|
Stage-I Approval on
|
:
|
29 Jan 2020
|
Compliance Report Submitted by User Agency on
|
:
|
22 Aug 2025
|
|
|
|
|
35
|
Karnataka
|
FP/KA/MIN/35480/2018
|
8-95/1994-FC Vol.
|
Downhill pipe conveyor belt
|
Mining
|
M/S VEERBHADRAPPA SANGAPPA & COMPANY
|
14.8457
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Aug 2018
|
Stage-I Approval on
|
:
|
15 Oct 2019
|
Compliance Report Submitted by User Agency on
|
:
|
12 Jun 2025
|
|
|
|
|
36
|
Ladakh
|
FP/LA/ROAD/152696/2022
|
o 9-JKA-001/2024-Jammu
|
Construction of Re-Alignment Of Various Stretches Between Pandrass - Pashkyum (Net Length – 31.00 Kms) on Road Zozila – Kargil – Leh (NH-1) To NHDL Specifications Through EPC Mode Under Project Vijay
|
Road
|
HQ 762 BRTF C/O 56 APO
|
0.3625
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
15 Mar 2022
|
Stage-I Approval on
|
:
|
04 Oct 2024
|
Compliance Report Submitted by User Agency on
|
:
|
29 May 2025
|
|
|
|
|
37
|
Maharashtra
|
FP/MH/OFC/37697/2018
|
FC-I/MH-203/2020-NGP
|
Proposal for the Diversion of 1.12295 Ha. Forest Land For Laying Underground Optical Fiber Cable NH-8, SH-29 & MDR-15, From Route Charoti – Khambale in Tal. Dahanu, Jawhar & Vikramgad, Dist. Palghar
|
Optical Fibre Cable
|
RJIL
|
1.12295
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
25 Dec 2018
|
Stage-I Approval on
|
:
|
29 Jan 2021
|
Compliance Report Submitted by User Agency on
|
:
|
08 Oct 2025
|
|
|
|
|
38
|
Maharashtra
|
FP/MH/Others/26782/2017
|
FLD-3617/CR-332/F-10
|
Pusad-Bhojala-Jamsetpur-Chikhali-Parwa-Lakhi of Reliance Jio Infocomm Ltd for Optical Fiber cable
|
Others
|
RJIL
|
0.118
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Jun 2017
|
Stage-I Approval on
|
:
|
11 Sep 2017
|
Compliance Report Submitted by User Agency on
|
:
|
08 Oct 2025
|
|
|
|
|
39
|
Maharashtra
|
FP/MH/ROAD/34626/2018
|
FC-II/MH-139/2021-NGP
|
Diversion of 6.38 ha. of Forest Land for Aurangabad Jalgaon Road Secition- 1 (Aurangabad to Sillod)
|
Road
|
PUBLIC WORKS DEPARTMENT NATIONAL HIGHWAYS AURANGABAD MAHARASHTRA
|
6.38
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
24 Jul 2018
|
Stage-I Approval on
|
:
|
31 Mar 2021
|
Compliance Report Submitted by User Agency on
|
:
|
29 Sep 2025
|
|
|
|
|
40
|
Maharashtra
|
FP/MH/RAIL/43265/2019
|
FC-II/MH-156/2021-NGP
|
Diversion Of Forest Land For Panvel - Karjat Doubling Railway Line (Panvel - Karjat Section) In Raigad Dist
|
Railway
|
MUMBAI RAILWAY VIKAS CORPORATION LIMITED
|
9.1321
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
07 Dec 2019
|
Stage-I Approval on
|
:
|
30 May 2022
|
Compliance Report Submitted by User Agency on
|
:
|
17 Sep 2025
|
|
|
|
|
41
|
Orissa
|
FP/OR/ROAD/7575/2014
|
5-ORC259/2015-BHU
|
Bankibahal to kanika Railway siding Road
|
Road
|
EXECUTIVE ENGINEER
|
39.98
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
17 Oct 2014
|
Stage-I Approval on
|
:
|
14 Oct 2015
|
Compliance Report Submitted by User Agency on
|
:
|
06 Dec 2024
|
|
|
|
|
42
|
Orissa
|
FP/OR/Pipeline/148595/2021
|
5-ORB557/2023-BHU
|
Dhamra - Haldia Pipeline Project (Odisha)
|
Pipeline
|
GAIL (INDIA) LIMITED (DHPL-OD)
|
1.849
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
21 Oct 2021
|
Stage-I Approval on
|
:
|
08 Jan 2025
|
Compliance Report Submitted by User Agency on
|
:
|
30 Apr 2025
|
|
|
|
|
43
|
Rajasthan
|
FP/RJ/ROAD/10911/2015
|
8B/Raj/06/35/2015/FC
|
Construction of road from Hinglot to madnakheri
|
Road
|
EXECUTIVE ENGINEER PWD DIV CHHABRA
|
2.27
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
14 Mar 2015
|
Stage-I Approval on
|
:
|
03 Sep 2020
|
Compliance Report Submitted by User Agency on
|
:
|
12 Jun 2025
|
|
|
|
|
44
|
Rajasthan
|
FP/RJ/ROAD/7000/2014
|
8B/RJ/06/19/2015
|
Road from Gordhanpura to Kali mati
|
Road
|
PUBLIC WORKS DEPARTMENT
|
2.98
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Sep 2014
|
Stage-I Approval on
|
:
|
04 Aug 2016
|
Compliance Report Submitted by User Agency on
|
:
|
05 Jun 2025
|
|
|
|
|
45
|
Rajasthan
|
FP/RJ/ROAD/7759/2014
|
1(46)forest/2015
|
A/R to Nayagoav Bhanpura
|
Road
|
EXECUTIVE ENGINEER
|
0.2
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Oct 2014
|
Stage-I Approval on
|
:
|
03 Mar 2015
|
Compliance Report Submitted by User Agency on
|
:
|
23 Jul 2025
|
|
|
|
|
46
|
Rajasthan
|
FP/RJ/ROAD/7757/2014
|
1(52)Forest/2015
|
Approch road Barodiya to Jatamari
|
Road
|
EXECUTIVE ENGINEER
|
0.994
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
29 Oct 2014
|
Stage-I Approval on
|
:
|
18 Mar 2015
|
Compliance Report Submitted by User Agency on
|
:
|
23 Jul 2025
|
|
|
|
|
47
|
Rajasthan
|
FP/RJ/ROAD/6954/2014
|
8B/RJ/06/04/2015/FC
|
Road Work from Jalwara to Kishanpura
|
Road
|
PUBLIC WORKS DEPARTMENT
|
2.96
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
08 Sep 2014
|
Stage-I Approval on
|
:
|
23 Aug 2016
|
Compliance Report Submitted by User Agency on
|
:
|
05 Jun 2025
|
|
|
|
|
48
|
Rajasthan
|
FP/RJ/ROAD/7595/2014
|
1(51)Forest/2015
|
NH-12 to Rojya
|
Road
|
EXECUTIVE ENGINEER
|
0.95
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
16 Oct 2014
|
Stage-I Approval on
|
:
|
18 Mar 2015
|
Compliance Report Submitted by User Agency on
|
:
|
23 Jul 2025
|
|
|
|
|
49
|
Telangana
|
FP/TG/TRANS/34892/2018
|
4-TSB138/2018-CHN
|
Construction of 400kv QMDC Line from STPP (2 x 600MW), Jaipur Mandal to proposed 400 kv SS Nirmal in Jagitial District - 2.0401 Ha
|
Transmission Line
|
TSTRANSCO
|
2.0401
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
23 Jul 2018
|
Stage-I Approval on
|
:
|
07 Mar 2019
|
Compliance Report Submitted by User Agency on
|
:
|
01 Apr 2023
|
|
|
|
|
50
|
Telangana
|
FP/TG/ROAD/13068/2015
|
4-TSB107/2017-CHN
|
Widening and strengthing of NH 167 from 275/0 to 278/0 km in Apanapalli RF of Mahabubnagar division of 2.892 Ha
|
Road
|
EXICUTIVE ENGINEER
|
2.892
|
Pending at Nodal Officer after receiving Compliance of Conditions
|
Proposal received(at Nodal Officer)electronically on
|
:
|
04 Jun 2015
|
Stage-I Approval on
|
:
|
06 Oct 2017
|
Compliance Report Submitted by User Agency on
|
:
|
13 Aug 2024
|
|
|
|
|
|