FORM - A
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
PART - I
(To be filled up by User Agency)
A. General Details
A-1. Project Details
  (i). Proposal No. : FP/UK/ROAD/10443/2015   (ii). Name of Project for which Forest Land is required : Construction of saboli bend - Toulbudhani motor road.   (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The new road is sanction for 24.00 Km length Under C.M. Ghosna vide Uttarakhand Govt. order No. 2488/III-2/08-03(MU.M.GHO.)/2008 dated 02-08-2003 to connect village Nainwal Pali, Kanwari, Erakote, Kungieel, Toulbudhani etc.   (iv). State : Uttarakhand   (v). Category of the Proposal : Road   (vi). Shape of forest land proposed to be diverted : Linear   (vii). Estimated cost of the Project(Rupees in lacs) : 840   (viii). Area of forest land proposed for diversion(in ha.): 7.077   (ix). Non-forest land required for this project(in ha.): 12.501   (x). Total period for which the forest land is proposed to be diverted(in years): 300
A-2. Details of User Agency
  (i). Name : EXECUTIVE ENGINEER   (ii). Address1 : Provincial Division P.W.D., Ranikhet   (iii). Address2 : Mall Raod Ranikhet   (iv). State : Uttarakhand   (v). District : Almora   (vi). Pin : 263645   (vii). Landmark : NIL   (viii). Email address : eepdrani@yahoo.com   (ix). Landline Telephone No. : 5966-220679   (x). Fax No. : NIL   (xi). Mobile No. : 7500540231   (xii). Website (if any) : NIL   (xiii). Legal status of User Agency : State Government
A-3. Details of Person Making Application
  (i). First Name: Lalit   (ii). Middle Name: Kumar   (iii). Last Name: Goel   (iv). Gender: Male   (v). Designation: Executive Engineer   (vi). Address 1: Provincial Division PWD, Ranikhet   (vii). Address 2: Mall Road Ranikhet   (viii). State: Uttarakhand   (ix). District: Almora   (x). Tehsil: NIL   (xi). Pin: 263645   (xii). Landmark: Ranikhet   (xiii). Email Address: eepdrani@yahoo.com   (xiv). Landline Telephone No.: 5966-220679   (xv). Fax No.: 05966220679   (xvi). Mobile No.: 9412919971   (xvii). Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency:
B. Details of land required for the Project
B-1. Details of proposal seeking prior approval of Central Government under the Act for diversion of forest land for the Project already submitted in the past
Proposal Submitted in Past
S.no Proposal Status. Proposal No. Moef File No. Area Proposed for Diversion(Ha.) Area Diverted(Ha.) Date of In-Principle Approval Date of Final Approval
1ApprovedFP/UK/ROAD/19725/20168B/UCP/06/173/2016/FC/19532.162.1629 Dec 201621 Feb 2018
Total 2.16 2.16
B-2. Details of forest land proposed to be diverted
B-2.1 Details of Divisions involved
Details of Divisions involved
S.no Division Name Forest Land(ha.) Non-Forest Land(ha.)
1.Almora7.07712.501
Total7.07712.501
B-2.2 Details of Districts involved
District wise breakup
S.no District Name Forest Land(ha.) Non-Forest Land(ha.)
1.Almora7.07712.501
Total7.07712.501
B-2.3 Village wise breakup
Villages wise breakup
S.no Village Forest Land(ha.) Non-Forest Land(ha.)
1nailwalpali05.31
2sansary0.2551.8
3ritoli0.1450.495
4erakot1.280.465
5kunheel0.630.8
6khaldo0.770.75
7Bungidhar0.7910.495
8Seema ristana0.210.666
9Basedi basnal0.9070.658
10toulbudhani0.7140.36
11Reserve forest0.70
12Musoli0.6750.702
Total 7.077 12.501
B-2.4 Component wise breakup
Component wise breakup
S.no Component Forest Land(ha.) Non-Forest Land(ha.)
1FOR ROAD KM 0 TO 247.07699710.740006
2for road (muck disposal yard km 5 to 6.644)01.7604
Total 7.076997 12.500406
C. Maps of forest land proposed to be diverted
Division 1. : Almora
  (i). Area of forest land proposed to be diverted(in ha.) : 7.077   (ii). Nature of the Project: Linear   (b). No. of Segments : One
Segment wise details
Segments Segment Area(in ha.) Kml File of Segments
(To view KML file on google the same may be downloaded and then open if in google earth install in your computer).
1.7.077    View File
  (iii). Copy of Survey of India Toposheet indicating boundary of forest land proposed to be diverted:   (iv). Scanned copy of the Geo-referenced map of the forest land proposed to be diverted prepared by using GPS or Total Station:
D. Justification for locating the Project in forest land and details of alternatives examined:
  (i). Copy of note containing justification for locating the Project in forest land:   (ii). Whether a copy of map indicating location of alternative examine is required to be provided: Yes   (a). Copy of map indicating location of alternative examined:
E. Employment likely to be generated
  (i). Whether the Project is likely to generate employment ?: Yes   (ii). Permanent/Regular Employment(Number of persons): 0   (iii). Temporary Employment(Number of person-days): 61200
F. Displacement of People due to the Project, if any
  (i). Whether Project involves displacement?: No
G. Details of Cost-Benefit analysis for the Project
  (i). Whether the Project requires Cost-Benefit analysis?: Yes   (a). Copy of Cost-Benefit analysis:
H. Status of Environmental Clearance
  (i). Whether the Project requires Clearance under the Environment (Protection) Act 1986 ? : No
I. Status of Wildelife Clearance
  (i). Whether the Project or a part thereof is located in any Protected Area or their Eco sensitive zone? : No
J. Applicability of special provisions governing Scheduled Areas
  (i).Whether the Project or a part thereof is located in a Scheduled Area? : No
K. Status of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted
  (i). Whether the process for settlement of Rights under the Forest Rights Acts 2006 on the forest land proposed to be diverted has been completed? : Yes   (a). Copy of documentry evidence in support of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted:
L. Details of land identified for Compensatory Afforestation
  (i). Whether non-forest or Revenue forest land is required to be provided by User Agency?: Yes   (ii). Whether the area of non-forest land or Revenue forest land required to be provided by User Agency for raising Compensatory Afforestation is less than area of forest land proposed to be diverted ?: No   (iii). No. of districts involved for raising Compensatory Afforestation: 1   (iv). No. of patches: Three
District 1. : Almora
  (a). Village: Bhitakot, Masniyabanj & Dungra   (b). Area(in ha.): 14.154   (c). Copy of KML file of the patch:     View File   (d). Khasra details: 1831-7.588,1815-3.20 & 277-3.366   (e). Present owner: User Agency   (f). Copy of Ownership proof: No Data
  (v). Scanned copy of the map of the land identified for creation of Compensatory Afforestation prepared by using GPS ot Total Station:   (vi). Copy of Survey of India Toposheet in 1:50,000 scale indicating location of the land identified for creation of Compensatory Afforestation:
Additional information Details
Documents
S.No Documents
Remarks
1A Short Narrative and Importance of the Project
2Administrative and Financial Sanction
3Preliminary Joint Inspection Report
4Comperative chart showing statement of both alignment or alternate site
5Certificate from the DM that no alternative suitable non-forest land
6Category wise land length
7Bar Chart With Index
8Certificate Regarding Undertaking by the user agency to bear the cost of CA
9Road Side/Gap Filling Plantation Estimate
10Undertaking by the User Agency to bear the cost of Road Side/Gap Filling Plantation
11Details of the trees with their scientific name in RF, Civil Soyam, Van panchayat, Private Notified land
12Certificate of felling minimum trees during the project work.
13Whather project area is a part of National Park or sanctuary and airal distance of the project from National Park or sanctuary signed by DFO
14No voilation has taken place, FC Act. 1980 reg.
15NOC from local Gram Sabhas
16Certificate work has not been started reg.
17Geologist Report
18Task Force Report
19Item wise details of works
20Certificate by user agency for complying the condition imposed in Manak Shartain
21Certificate by user agency for complying the condition imposed in geologist report/Task forcex
22No historical/monumental or relegeous place will be effected certificate reg.
23Undertaking regarding no animal will be effected adversely by the project
24Undertading to provide alternative fuel wood, kerosene or LPG to labours
25Benefited villagers/families/population certificate
26Undertaking of payment of NPV S. court increases the rates of NPV
27Cost of the forest land and lease rent certificate
28Undertaking of user agency to bear the cost for dimarcation work
29Check list/Fact Sheet
30PartI
31Uploaded signed copy of acknowledgement slip of receipt of hard copy at DFOs office.
32Obejection Removed vide this Office letter no. 2027/36C Date 31.08.2017 in reference of your letter no. 1014/12-1(2) date 26-08-2017
33Objection Removal by letter 2127/36c dated 06-09-2017
34objection removed by letter no. 2372/36c dated 04-10-2017 in ref of dfo letter no. 914/12-1 dated 21-09-2017 (Hard copy received to CC Almora)
35objection removed by letter no. 2790/36c dated 27-11-2017 in ref of dfo letter no. memo/12-1(2) dated 11-09-2017(Hard copy received to Nodal office)
36objection removed by letter no. 259/36c dated 01-01-2018 in ref of dfo letter no. memo/12-1(2) dated 28-12-2017
37NPV calculation certificate as per S. court
38objection removed by letter no. 351/36c dated 17-02-2018 in ref of dfo letter no. memo/12-1(2) dated 14-02-2018
39objection removed by letter no. 1283/36c dated 04-06-2018
40Objection removed by letter no. 2722/36c dated 09-10-2018 by letter no. memo/12-01(2) dated 26-06-2018
41FRA DC Attached
42Reply on objection raised by DFO office online on 17-10-2018, vide this office letter No 2793/36C dated 17-10-2018
43Objection removed by letter no 2944/36c dated 03-11-2018
44Reply on objection raised by DFO office letter No Memo/12-1(2) dated 12-12-2018, vide this office letter No 515/36C dated 20-02-2019
45Objection removed by letter no 948/36c dated 29-04-2019
46Category wise land length
47Objection removed by letter no 1373/36c dated 04-07-2019
48Objection removed by letter no 1495/36c dated 21-08-2020
49Land schedule
50Muck disposal scheme Naap Land
51Certificate Regarding suitability of indentified hand for CA
52Objection Removed by letter no 1766/36c dated 23-09-2020
53objection reply dated 20/05/2021
54objection removed dated 15.09.2021
55objection reply dated 26.10.2021
56Objection Removed by letter no 792/36c dated 09-05-2022
57This moter road ca detail. 1- Bhitakot, plot no.1831-7.588 2- Masniyabanj 3- Dungra
58this moter road objection remooved latter send to dfo almora
59Ca Scheem vill. Bhitakot, Masniyabanj & Dungra