Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
13/03/2020
|
Please Upload the 3D subsidence analysis study report as required in Serial No. M2 v a , and follow the letter
|
|
2
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
13/03/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
12/03/2021
|
Proposal reverted back for necessary modification as discussed during last joint field inspection on 3rd March, 2021
|
|
4
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
23/04/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
03/09/2021
|
Exclusion of Beat Office & Approach path from the Project Proposal
|
|
6
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
11/11/2021
|
The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
16/02/2022
|
1. The KML file of forest land proposed to be diverted, in C.a of Part-I, should not be shaded.
2. Survey of India toposheet, as in C.iii, is not clear
3. Georeferenced map, as in C.iv, the readings in left-top portion are not clear
3. CA is required. UA to rectify their Part-I, L. DFO to update the corresponding CA details in 13 of Part-II
4. Site Inspection Report of CCF is missing in Part-II pt.15
5. Part-III of CCF is missing in pt.16 of Part-II
|
|
8
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
04/03/2022
|
Tilaboni under ground project
|
|
9
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
04/03/2022
|
Details of CA and kml file missing. Pl upload
|
|
10
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
04/03/2022
|
Details of CA and kml file missing. Pl upload
|
|
11
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
14/03/2022
|
Returning herewith the proposal for clarification of CA issue & uploading of KML, Toposheet Maps etc. of proposed diverted Forest Land as objected by the Nodal Officer, FCA
|
|
12
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
30/04/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
05/05/2022
|
Proposal is sent back to review and upload necessary documents as directed by the Nodal Officer, FCA, W.B.
|
|
14
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
13/05/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
17/05/2022
|
Necessary details as sought for by the Nodal Officer FCA has been uploaded by the user agency & CA estimate details has been uploaded by the u/s in additional information.
|
|
16
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
18/05/2022
|
Details of CA and kml file missing. Pl upload
|
|
17
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
18/05/2022
|
CA estimate uploaded in the additional information
|
|
18
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
18/05/2022
|
CA estimate details
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
26/07/2022
|
Request to apply for total forest land in lease area
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
02/08/2022
|
Kindly give reply to the queries raised by MoEF
|
|
21
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
02/08/2022
|
get the issues raised in EDS addressed pl
|
|
22
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
31/08/2022
|
May be forwarded to user agency.
|
|
23
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
08/09/2022
|
Please find enclose and provide information/document as sought.
|
|
24
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
07/12/2022
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
16/12/2022
|
The correction have been made as per the instruction by User Agency
|
|
26
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
19/12/2022
|
Tilaboni Pdf
|
|
27
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
05/01/2023
|
CCF and DFO comments are needed. Pl. reply accordingly as detailed by IRO
|
|
28
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
17/01/2023
|
DFO comments are needed. Pl. reply accordingly as detailed by IRO
|
|
29
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
17/01/2023
|
Parawise comments against Diversion of 38.38 ha of Forest Land for Tilaboni UGP –reg
|
|
30
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
17/01/2023
|
Forwarded
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
17/01/2023
|
May kindly be forwarded to IRO Kolkata
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
20/01/2023
|
Reply to the EDS has been furnished
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
20/02/2023
|
EDS II
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
03/03/2023
|
Kindly upload information/documents as requested by MoEF
|
|
35
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
03/03/2023
|
pl reply to EDS
|
|
36
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
06/03/2023
|
PDF
|
|
37
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
06/03/2023
|
Cost Benefit analysis is done by User Agency, pl get it corrected. Upload details of CA land as requested in EDS
|
|
38
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
09/03/2023
|
Cost Benefit analysis is done by User Agency, pl get it corrected. Upload details of CA land as requested in EDS
|
|
39
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
13/03/2023
|
Cost Benefit analysis to be re done including cost of CA and NPV Forest density 0.7. CA will be over double degraded Forest land.
|
|
40
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
24/04/2023
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Durgapur)
|
EDS
|
User Agency (envecl@yahoo.com)
|
27/04/2023
|
Kindly correct the NPV rate Annexure-II , serial no. 1.
|
|
42
|
User Agency (envecl@yahoo.com)
|
REPLY
|
DFO (Durgapur)
|
28/04/2023
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
29/04/2023
|
Forwarded after necessary correction.
|
|
44
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
29/04/2023
|
Everything has been complied & submitted for necessary action.
|
|
45
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
01/05/2023
|
CA plantation with QGS or exotics 1600 per ha is not accerptable. Pl revise CA estimates with Sal and associated indegenous spp only with list of tree spp to be planted. CA estimate must be countersigned by CCF. Has Gram Sabha meeting been held for FRA yet since proposal is for diversion of NTFP rich sal forest
|
|
46
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
02/05/2023
|
For necessary Compliance.
|
|
47
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
03/05/2023
|
Forwarded subject to Pending Gram Sabha proceeding and NOC under Forest Right Act , 2006.
|
|
48
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
03/05/2023
|
All the required Queries have been duly complied.
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
04/05/2023
|
may pl be forwarded to IRO Kolkata
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
15/05/2023
|
change ca kml file
|
|
51
|
Nodal Officer
|
EDS
|
CF (South- East Circle)
|
15/05/2023
|
correct ca kml file
|
|
52
|
CF (South- East Circle)
|
EDS
|
DFO (Durgapur)
|
15/05/2023
|
Upload Kml file.
|
|
53
|
DFO (Durgapur)
|
REPLY
|
CF (South- East Circle)
|
16/05/2023
|
Forwarded the corrected KML file of Kalikapur Mouza,JL No.- 35, Plot No.- 56.
|
|
54
|
CF (South- East Circle)
|
REPLY
|
Nodal Officer
|
16/05/2023
|
Kml file has been modified as desired.
|
|
55
|
Nodal Officer
|
REPLY
|
State secretary
|
16/05/2023
|
May kindly be forwarded to IRO Kolkata
|
|
56
|
State secretary
|
REPLY
|
Regional Office
|
16/05/2023
|
correction has been made
|
|
57
|
Regional Office
|
EDS
|
State secretary
|
23/05/2023
|
Comments of the State Government needs to be submitted.
|
|
58
|
State secretary
|
REPLY
|
Regional Office
|
24/05/2023
|
Forwarded
|
|