TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/14525/2015              (ii). Name of Project for which Forest Land is required : Construction of New Bridge/Approach Road over Hindon River at Balaini              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of New Bridge/Approach Road Over Hindon River in Place of Narrow Bridge at Balaini              (iv). File no. : 8B/UP/06/23/2016/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.215
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/ROAD/14525/201522/08/201502/09/2015  31/08/2015  24/08/2015   02/09/2015  01/09/2015  31/08/2015   04/09/2015   08/09/2015 Baghpat :09/09/2015Meerut Circle Meerut:
  18/10/2015 (Baghpat)

Uttar Pradesh:
26/10/2015
Uttar Pradesh:
17/02/2016
Lucknow:
17/02/2016
28/09/2016
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:04/03/2016  
Replied by State Government(Uttar Pradesh) on:14/06/2016  
Query raised by Regional Office (Lucknow) on:12/07/2016  
Replied by State Government(Uttar Pradesh) on:22/08/2016  
Query raised by Regional Office (Lucknow) on:24/08/2016  
Replied by State Government(Uttar Pradesh) on:27/09/2016  
Query raised by State Government (Uttar Pradesh) on:15/03/2016  
Replied by Nodal Officer (Uttar Pradesh) on:14/06/2016  
Query raised by State Government (Uttar Pradesh) on:16/08/2016  
Replied by Nodal Officer (Uttar Pradesh) on:22/08/2016  
Query raised by State Government (Uttar Pradesh) on:24/08/2016  
Replied by Nodal Officer (Uttar Pradesh) on:27/09/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:03/11/2015  
Replied by Circle(Meerut Circle Meerut) on:23/11/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:30/11/2015  
Replied by Circle(Meerut Circle Meerut) on:17/12/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:18/12/2015  
Replied by Circle(Meerut Circle Meerut) on:11/02/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:11/02/2016  
Replied by Circle(Meerut Circle Meerut) on:11/02/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:16/03/2016  
Replied by Circle(Meerut Circle Meerut) on:12/05/2016  
Query raised by Nodal Officer (Uttar Pradesh) on:25/05/2016  
Replied by Circle(Meerut Circle Meerut) on:07/06/2016  
Query raised by Circle (Meerut Circle Meerut) on:03/11/2015  
Replied by DFO (Baghpat) on:21/11/2015  
Query raised by Circle (Meerut Circle Meerut) on:01/12/2015  
Replied by DFO (Baghpat) on:02/12/2015  
Query raised by Circle (Meerut Circle Meerut) on:22/12/2015  
Replied by DFO (Baghpat) on:11/02/2016  
Query raised by Circle (Meerut Circle Meerut) on:13/04/2016  
Replied by DFO (Baghpat) on:07/05/2016  
Query raised by Circle (Meerut Circle Meerut) on:27/05/2016  
Replied by DFO (Baghpat) on:03/06/2016  
Query raised by DFO (Baghpat) on:13/01/2016  
Replied by UA on :01/02/2016  
Query raised by DFO (Baghpat) on:10/02/2016  
Replied by UA on :10/02/2016  
Query raised by DFO (Baghpat) on:30/05/2016  
Replied by UA on :02/06/2016  
NOTE:- Stage-I Approval accorded by : Regional Office .