  (i). Proposal No. : FP/UK/ROAD/40773/2019              (ii). Name of Project for which Forest Land is required : Construction of Kyark–Barsudi–Bhairon band to Jamethi motor road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Village-Kyark-barsudi (Jamethi) (total population 881), due to being deprived of the motorway, local people have to walk for basic amenities such as education, health. With the construction of the said motorway, the contact of local people of Kyark-barsudi (Jamethi) will be established from Tehsil h              (iv). File no. : 8b/UCP/06/70/2021/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.34
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/40773/201921/06/201914/11/2019  07/08/2019  08/07/2019   22/01/2020  13/11/2019  10/07/2019   25/01/2020   17/02/2020 Rudraprayag :19/02/2020Garhwal:
  19/12/2020 (Rudraprayag)

Uttarakhand:
23/12/2020
Uttarakhand:
03/05/2021
Dehradun:
22/06/2021
07/03/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:30/06/2021  
Replied by State Government(Uttarakhand) on:13/09/2021  
Query raised by Regional Office (Dehradun) on:23/09/2021  
Replied by State Government(Uttarakhand) on:21/08/2023  
Query raised by Regional Office (Dehradun) on:30/08/2023  
Replied by State Government(Uttarakhand) on:06/02/2024  
Query raised by State Government (Uttarakhand) on:01/07/2021  
Replied by Nodal Officer (Uttarakhand) on:13/09/2021  
Query raised by State Government (Uttarakhand) on:27/09/2021  
Replied by Nodal Officer (Uttarakhand) on:21/08/2023  
Query raised by State Government (Uttarakhand) on:01/09/2023  
Replied by Nodal Officer (Uttarakhand) on:01/02/2024  
Query raised by Nodal Officer (Uttarakhand) on:12/01/2021  
Replied by Circle(Garhwal) on:12/04/2021  
Query raised by Nodal Officer (Uttarakhand) on:01/07/2021  
Replied by Circle(Garhwal) on:28/08/2021  
Query raised by Nodal Officer (Uttarakhand) on:27/09/2021  
Replied by Circle(Garhwal) on:06/01/2022  
Query raised by Nodal Officer (Uttarakhand) on:13/01/2022  
Replied by Circle(Garhwal) on:08/08/2023  
Query raised by Nodal Officer (Uttarakhand) on:01/09/2023  
Replied by Circle(Garhwal) on:10/01/2024  
Query raised by Nodal Officer (Uttarakhand) on:25/01/2024  
Replied by Circle(Garhwal) on:27/01/2024  
Query raised by Circle (Garhwal) on:13/01/2021  
Replied by DFO (Rudraprayag) on:08/04/2021  
Query raised by Circle (Garhwal) on:02/07/2021  
Replied by DFO (Rudraprayag) on:26/08/2021  
Query raised by Circle (Garhwal) on:28/09/2021  
Replied by DFO (Rudraprayag) on:31/12/2021  
Query raised by Circle (Garhwal) on:14/01/2022  
Replied by DFO (Rudraprayag) on:31/07/2023  
Query raised by Circle (Garhwal) on:01/08/2023  
Replied by DFO (Rudraprayag) on:01/08/2023  
Query raised by Circle (Garhwal) on:05/09/2023  
Replied by DFO (Rudraprayag) on:13/12/2023  
Query raised by DFO (Rudraprayag) on:20/02/2020  
Replied by UA on :28/02/2020  
Query raised by DFO (Rudraprayag) on:30/03/2020  
Replied by UA on :25/08/2020  
Query raised by DFO (Rudraprayag) on:14/10/2020  
Replied by UA on :04/11/2020  
Query raised by DFO (Rudraprayag) on:13/01/2021  
Replied by UA on :07/04/2021  
Query raised by DFO (Rudraprayag) on:03/07/2021  
Replied by UA on :25/08/2021  
Query raised by DFO (Rudraprayag) on:28/09/2021  
Replied by UA on :23/12/2021  
Query raised by DFO (Rudraprayag) on:20/01/2022  
Replied by UA on :30/05/2022  
Query raised by DFO (Rudraprayag) on:31/05/2022  
Replied by UA on :16/06/2022  
Query raised by DFO (Rudraprayag) on:30/06/2022  
Replied by UA on :29/12/2022  
Query raised by DFO (Rudraprayag) on:19/01/2023  
Replied by UA on :23/05/2023  
Query raised by DFO (Rudraprayag) on:01/06/2023  
Replied by UA on :21/06/2023  
Query raised by DFO (Rudraprayag) on:30/06/2023  
Replied by UA on :30/06/2023  
Query raised by DFO (Rudraprayag) on:10/07/2023  
Replied by UA on :12/07/2023  
Query raised by DFO (Rudraprayag) on:13/09/2023  
Replied by UA on :17/11/2023  
Query raised by DFO (Rudraprayag) on:06/12/2023  
Replied by UA on :08/12/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...