Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
27/06/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
2
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
28/06/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
3
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
28/06/2017
|
The hard copy of the proposal containing original documents is not yet received in this office. The State Govt may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part V as in online web portal.
|
|
4
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
26/07/2017
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
02/08/2017
|
The correction have been made as per the instruction received. soft copy send your email id.
|
|
6
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
04/08/2017
|
Please upload the desired documents
|
|
7
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
04/08/2017
|
Eds reply dated 01-08-2017
soft copy send your email id.
|
|
8
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
10/08/2017
|
sir, please receive the proposal information.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
18/08/2017
|
find the letter attached
|
|
10
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
19/08/2017
|
please remove the objection
|
|
11
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
19/08/2017
|
Please remove the objection.
|
|
12
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
15/09/2017
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
18/09/2017
|
Sir, EDS reply date 16-09-2017.
|
|
14
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
19/09/2017
|
All objection removed please forward the proposal to higher level
|
|
15
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
06/10/2017
|
Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II.
2.user agency may fill the Details of Cost-Benefit analysis for the Project in new format 3.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.4.Please upload proper and detailed justification for the proposed project in forest area
5.uploaed Copy of non encumberence certificate for the forest land in seril-h is erroneous 6.The applicant details does not match with the authority letter issued to filled online form.
|
|
16
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
07/10/2017
|
Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 2.user agency may fill the Details of Cost-Benefit analysis for the Project in new format 3.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.4.Please upload proper and detailed justification for the proposed project in forest area 5.uploaed Copy of non encumberence certificate for the forest land in seril-h is erroneous 6.The applicant details does not match with the authority letter issued to filled online form.
|
|
17
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
07/10/2017
|
Approximate distance of proposed diversion area from the boundary of forest towards inside the forest is not filled in online Part II. 2.user agency may fill the Details of Cost-Benefit analysis for the Project in new format 3.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.4.Please upload proper and detailed justification for the proposed project in forest area 5.uploaed Copy of non encumberence certificate for the forest land in seril-h is erroneous 6.The applicant details does not match with the authority letter issued to filled online form.
|
|
18
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
03/11/2017
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
15/11/2017
|
Sir, EDS objection reply.
|
|
20
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
20/11/2017
|
Sir please receive the information of proposal.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
20/11/2017
|
1.user agency may fill the Details of Cost-Benefit analysis for the Project in new format 2.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.3.Please upload proper and detailed justification for the proposed project in forest area 4.uploaed Copy of non encumberence certificate for the forest land in seril-h is erroneous 5. figure given in para B-2.3 do not not tally with the figure given in B-2.4 which is required to be reviewed and corrected by the user agency
|
|
22
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
21/11/2017
|
1.user agency may fill the Details of Cost-Benefit analysis for the Project in new format 2.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.3.Please upload proper and detailed justification for the proposed project in forest area 4.uploaed Copy of non encumberence certificate for the forest land in seril-h is erroneous 5. figure given in para B-2.3 do not not tally with the figure given in B-2.4 which is required to be reviewed and corrected by the user agency
|
|
23
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
23/11/2017
|
1.user agency may fill the Details of Cost-Benefit analysis for the Project in new format 2.Employment details provided in online part-I appears incorrect. The user agency may review the same and provide correct details.3.Please upload proper and detailed justification for the proposed project in forest area 4.uploaed Copy of non encumberence certificate for the forest land in seril-h is erroneous 5. figure given in para B-2.3 do not not tally with the figure given in B-2.4 which is required to be reviewed and corrected by the user agency
|
|
24
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
01/12/2017
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
14/12/2017
|
please remove the objection.
|
|
26
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
16/12/2017
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
28/12/2017
|
Sir, eds reply.
|
|
28
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
15/01/2018
|
sir, please receive the information of the proposal.
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
08/02/2018
|
Hard copy of the proposal has still not been submitted by the State Govt., which may be submitted to this office. State Govt. is required to submit hard copy of the proposal containing all original/authenticated photocopies of all the documents. Since, the proposal is return back.
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
09/02/2018
|
Hard copy of the proposal has still not been submitted by the State Govt., which may be submitted to this office. State Govt. is required to submit hard copy of the proposal containing all original/authenticated photocopies of all the documents. Since, the proposal is return back.
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
09/02/2018
|
The correction have been made as per the instruction received
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
12/02/2018
|
The correction have been made as per the instruction received
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
01/03/2018
|
State Government may attend the shortcomings mentioned in the attached document.
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
05/03/2018
|
State Government may attend the shortcomings mentioned in the attached document.
|
|
35
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
07/03/2018
|
The state Govt may attend the shortcomings mentioned in attached document
|
|
36
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
09/03/2018
|
Please Remove the objection
|
|
37
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (pwdtharali@gmail.com)
|
09/03/2018
|
please remove the objection.
|
|
38
|
User Agency (pwdtharali@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
07/06/2018
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
18/06/2018
|
Sir, EDS objection removed.
|
|
40
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
26/06/2018
|
please attached the relevant file.
|
|
41
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
04/07/2018
|
Sir, EDS objection removed. soft copy send your email id.
|
|
42
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
09/07/2018
|
sir, please receive the information of the proposal.
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
13/07/2018
|
The correction have been made as per the instruction received
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
13/07/2018
|
please review the density at para-4 in part-2
|
|
45
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
13/07/2018
|
please review the density at para-4 in part-2
|
|
46
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
13/07/2018
|
please review the density at para-4 in part-2
|
|
47
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
13/07/2018
|
correct filled in NPV density at para-4 in part 2
|
|
48
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
16/07/2018
|
correct filled in NPV density at para-4 in part 2
|
|
49
|
Nodal Officer
|
REPLY
|
State secretary
|
16/07/2018
|
The correction have been made as per the instruction received
|
|
50
|
State secretary
|
REPLY
|
Regional Office
|
17/07/2018
|
The correction have been made as per the instruction received
|
|