TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/16306/2015              (ii). Name of Project for which Forest Land is required : Rawatsera-Dobargara-Dhari-Madhya-Raitoli motor road in District-Bageshwar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Proposal for diversion of 2.425 ha. forest land for construction of motor road. detail narrative attached form-11 (2.1) in additional enclosure.              (iv). File no. : 8B/UCP/06/248/2016/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.425
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/16306/201530/10/201529/08/2016  21/05/2016  05/04/2016  07/12/2015  06/11/2015   01/09/2016  02/08/2016  19/04/2016  14/03/2016  07/12/2015   17/08/2016   19/08/2016 Bageshwar :01/09/2016North Kumaun:
  25/10/2016 (Bageshwar)

Uttarakhand:
05/11/2016
Uttarakhand:
10/11/2016
Dehradun:
22/11/2016
12/01/2018
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:16/12/2016  
Replied by State Government(Uttarakhand) on:22/12/2017  
Query raised by State Government (Uttarakhand) on:27/12/2016  
Replied by Nodal Officer (Uttarakhand) on:21/12/2017  
Query raised by Nodal Officer (Uttarakhand) on:27/12/2016  
Replied by Circle(North Kumaun) on:21/02/2017  
Query raised by Nodal Officer (Uttarakhand) on:18/03/2017  
Replied by Circle(North Kumaun) on:01/12/2017  
Query raised by Circle (North Kumaun) on:28/12/2016  
Replied by DFO (Bageshwar) on:09/02/2017  
Query raised by Circle (North Kumaun) on:20/03/2017  
Replied by DFO (Bageshwar) on:30/11/2017  
Query raised by DFO (Bageshwar) on:02/09/2016  
Replied by UA on :17/10/2016  
Query raised by DFO (Bageshwar) on:28/12/2016  
Replied by UA on :04/02/2017  
Query raised by DFO (Bageshwar) on:27/03/2017  
Replied by UA on :15/07/2017  
Query raised by DFO (Bageshwar) on:23/08/2017  
Replied by UA on :10/10/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .