TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/15503/2015              (ii). Name of Project for which Forest Land is required : Construction of Khunt-Kakrighat Motor Road to Village Thaat link Motor Road. (Length 4.00Km)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of Khunt-Kakrighat Motor Road to Village Thaat link Motor Road in someshwer consituncy Distt Almora. Construction of Khunt-Kakrighat Motor Road to Village Thaat link Road is proposed as a extension of Kut-Kakrighat motor road the sention lenth of proposed motor road is 4.00 km. The beni              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 0.983
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/15503/201520/01/201605/02/2016   06/02/2016   08/03/2016   02/04/2016 Almora :05/04/2016North Kumaun:
  29/04/2016 (Almora)

Uttarakhand:
02/05/2016
Uttarakhand:
30/06/2016
Dehradun:
11/07/2016
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:15/07/2016  
Replied by State Government(Uttarakhand) on:15/04/2019  
Query raised by Regional Office (Dehradun) on:10/05/2019  
Replied by State Government(Uttarakhand) on:13/09/2019  
Query raised by Regional Office (Dehradun) on:11/10/2019  
Replied by State Government(Uttarakhand) on:17/09/2021  
Query raised by Regional Office (Dehradun) on:28/09/2021  
Replied by State Government(Uttarakhand) on:05/04/2023  
Query raised by Regional Office (Dehradun) on:28/04/2023  
Query raised by State Government (Uttarakhand) on:18/07/2016  
Replied by Nodal Officer (Uttarakhand) on:27/03/2019  
Query raised by State Government (Uttarakhand) on:14/05/2019  
Replied by Nodal Officer (Uttarakhand) on:12/09/2019  
Query raised by State Government (Uttarakhand) on:26/10/2019  
Replied by Nodal Officer (Uttarakhand) on:17/09/2021  
Query raised by State Government (Uttarakhand) on:30/09/2021  
Replied by Nodal Officer (Uttarakhand) on:05/04/2023  
Query raised by State Government (Uttarakhand) on:28/04/2023  
Query raised by Nodal Officer (Uttarakhand) on:17/05/2016  
Replied by Circle(North Kumaun) on:18/06/2016  
Query raised by Nodal Officer (Uttarakhand) on:19/07/2016  
Replied by Circle(North Kumaun) on:06/03/2019  
Query raised by Nodal Officer (Uttarakhand) on:14/05/2019  
Replied by Circle(North Kumaun) on:07/09/2019  
Query raised by Nodal Officer (Uttarakhand) on:29/10/2019  
Replied by Circle(North Kumaun) on:27/01/2021  
Query raised by Nodal Officer (Uttarakhand) on:23/02/2021  
Replied by Circle(North Kumaun) on:14/09/2021  
Query raised by Nodal Officer (Uttarakhand) on:30/09/2021  
Replied by Circle(North Kumaun) on:27/03/2023  
Query raised by Nodal Officer (Uttarakhand) on:28/04/2023  
Replied by Circle() on:  
Query raised by Circle (North Kumaun) on:20/05/2016  
Replied by DFO (Almora) on:16/06/2016  
Query raised by Circle (North Kumaun) on:20/07/2016  
Replied by DFO (Almora) on:05/03/2019  
Query raised by Circle (North Kumaun) on:16/05/2019  
Replied by DFO (Almora) on:07/09/2019  
Query raised by Circle (North Kumaun) on:01/11/2019  
Replied by DFO (Almora) on:07/01/2021  
Query raised by Circle (North Kumaun) on:08/01/2021  
Replied by DFO (Almora) on:18/01/2021  
Query raised by Circle (North Kumaun) on:25/02/2021  
Replied by DFO (Almora) on:09/09/2021  
Query raised by Circle (North Kumaun) on:01/10/2021  
Replied by DFO (Almora) on:17/03/2023  
Query raised by Circle (North Kumaun) on:29/04/2023  
Replied by DFO () on:  
Query raised by DFO (Almora) on:24/05/2016  
Replied by UA on :16/06/2016  
Query raised by DFO (Almora) on:20/07/2016  
Replied by UA on :01/03/2019  
Query raised by DFO (Almora) on:23/05/2019  
Replied by UA on :12/07/2019  
Query raised by DFO (Almora) on:14/08/2019  
Replied by UA on :31/08/2019  
Query raised by DFO (Almora) on:07/11/2019  
Replied by UA on :25/08/2020  
Query raised by DFO (Almora) on:26/09/2020  
Replied by UA on :06/01/2021  
Query raised by DFO (Almora) on:14/01/2021  
Replied by UA on :18/01/2021  
Query raised by DFO (Almora) on:03/04/2021  
Replied by UA on :23/06/2021  
Query raised by DFO (Almora) on:23/10/2021  
Replied by UA on :29/11/2022  
Query raised by DFO (Almora) on:14/12/2022  
Replied by UA on :27/02/2023  
Query raised by DFO (Almora) on:01/03/2023  
Replied by UA on :01/03/2023  
Query raised by DFO (Almora) on:01/05/2023  
Replied by UA on :25/06/2026  
Query raised by DFO (Almora) on:27/06/2026  
Replied by UA on :01/07/2026  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .