  (i). Proposal No. : FP/UK/ROAD/153125/2022              (ii). Name of Project for which Forest Land is required : Strengthening and Widening work of by Paved shoulder of Roorkee Laksar Balawali Road State Highway No. 26 in Km. 01 to 19 under CRF              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : It is a preconstructed Road which start from Dhandera Railway crossing road ends at km-29 of NH-334 A, Establishment of big Companies like IOCL are located at this road. The Traffic of light and heavy vehicles remains on this road day and night. At present the widening and strengthening work on this              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 7.32
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/153125/202204/03/2022aa04/03/2022   22/03/2022 Haridwar :23/03/2022Shivalik:
  26/05/2022 (Haridwar)

Uttarakhand:
05/07/2022
Uttarakhand:
08/09/2022
Dehradun:
20/09/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:04/10/2022  
Replied by State Government(Uttarakhand) on:23/12/2022  
Query raised by Regional Office (Dehradun) on:09/01/2023  
Replied by State Government(Uttarakhand) on:23/08/2024  
Query raised by Regional Office (Dehradun) on:19/12/2024  
Query raised by State Government (Uttarakhand) on:06/10/2022  
Replied by Nodal Officer (Uttarakhand) on:23/12/2022  
Query raised by State Government (Uttarakhand) on:10/01/2023  
Replied by Nodal Officer (Uttarakhand) on:17/08/2024  
Query raised by State Government (Uttarakhand) on:20/12/2024  
Query raised by Nodal Officer (Uttarakhand) on:12/07/2022  
Replied by Circle(Shivalik) on:17/08/2022  
Query raised by Nodal Officer (Uttarakhand) on:26/08/2022  
Replied by Circle(Shivalik) on:29/08/2022  
Query raised by Nodal Officer (Uttarakhand) on:07/10/2022  
Replied by Circle(Shivalik) on:17/12/2022  
Query raised by Nodal Officer (Uttarakhand) on:13/01/2023  
Replied by Circle(Shivalik) on:06/08/2024  
Query raised by Circle (Shivalik) on:27/05/2022  
Replied by DFO (Haridwar) on:13/06/2022  
Query raised by Circle (Shivalik) on:14/06/2022  
Replied by DFO (Haridwar) on:18/06/2022  
Query raised by Circle (Shivalik) on:20/06/2022  
Replied by DFO (Haridwar) on:24/06/2022  
Query raised by Circle (Shivalik) on:25/06/2022  
Replied by DFO (Haridwar) on:28/06/2022  
Query raised by Circle (Shivalik) on:30/06/2022  
Replied by DFO (Haridwar) on:30/06/2022  
Query raised by Circle (Shivalik) on:13/07/2022  
Replied by DFO (Haridwar) on:12/08/2022  
Query raised by Circle (Shivalik) on:07/10/2022  
Replied by DFO (Haridwar) on:13/12/2022  
Query raised by Circle (Shivalik) on:14/12/2022  
Replied by DFO (Haridwar) on:16/12/2022  
Query raised by Circle (Shivalik) on:16/01/2023  
Replied by DFO (Haridwar) on:18/05/2024  
Query raised by Circle (Shivalik) on:27/05/2024  
Replied by DFO (Haridwar) on:31/07/2024  
Query raised by DFO (Haridwar) on:07/04/2022  
Replied by UA on :11/05/2022  
Query raised by DFO (Haridwar) on:13/05/2022  
Replied by UA on :18/05/2022  
Query raised by DFO (Haridwar) on:25/05/2022  
Replied by UA on :26/05/2022  
Query raised by DFO (Haridwar) on:27/05/2022  
Replied by UA on :11/06/2022  
Query raised by DFO (Haridwar) on:14/06/2022  
Replied by UA on :17/06/2022  
Query raised by DFO (Haridwar) on:22/06/2022  
Replied by UA on :23/06/2022  
Query raised by DFO (Haridwar) on:28/06/2022  
Replied by UA on :28/06/2022  
Query raised by DFO (Haridwar) on:21/07/2022  
Replied by UA on :23/07/2022  
Query raised by DFO (Haridwar) on:23/07/2022  
Replied by UA on :26/07/2022  
Query raised by DFO (Haridwar) on:04/08/2022  
Replied by UA on :12/08/2022  
Query raised by DFO (Haridwar) on:12/10/2022  
Replied by UA on :24/11/2022  
Query raised by DFO (Haridwar) on:17/01/2023  
Replied by UA on :09/05/2024  
Query raised by DFO (Haridwar) on:29/05/2024  
Replied by UA on :25/06/2024  
Query raised by DFO (Haridwar) on:05/07/2024  
Replied by UA on :24/07/2024  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .