| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
29/07/2021
|
find the letter attached
|
|
|
2
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
03/09/2021
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
07/09/2021
|
plz kml file uploaded.
|
|
|
4
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/09/2021
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
16/09/2021
|
Send back
|
|
|
6
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
16/09/2021
|
plz find enclosed
|
|
|
7
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
01/10/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
|
8
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
04/10/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
|
9
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
12/10/2021
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
18/10/2021
|
plz find enclosed.
|
|
|
11
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/10/2021
|
As per letter no 1669/12-1 dated 23-10-2021
|
|
|
12
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
26/10/2021
|
As per letter no 1776/12-1 dated 26-10-2021
|
|
|
13
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
16/12/2021
|
The correction have been made as per the instruction received
|
|
|
14
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
22/12/2021
|
plz find enclosed
|
|
|
15
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
12/01/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
|
16
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
18/01/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
|
17
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
29/03/2022
|
The correction have been made as per the instruction received
|
|
|
18
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
30/03/2022
|
plz find enclosed.
|
|
|
19
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
22/04/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
|
20
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
09/05/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
|
21
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
28/06/2022
|
The correction have been made as per the instruction received
|
|
|
22
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
29/06/2022
|
p[lz find enclosed
|
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
06/07/2022
|
find the letter attached
|
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
27/07/2022
|
find the letter attached
|
|
|
25
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
29/07/2022
|
find the letter attached
|
|
|
26
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
06/05/2023
|
The correction have been made as per the instruction received
|
|
|
27
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
12/05/2023
|
plz find enclosed.
|
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
09/10/2023
|
AS pet letter no 920/12-1 dated 27-09-2023
|
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
27/02/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
29/02/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
|
31
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
29/02/2024
|
State Government is requested to attend the shortcomings as per the letter attached.
|
|
|
32
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
02/03/2024
|
attend the shortcomings as per the letter attached.
|
|
|
33
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
11/03/2024
|
attend the shortcomings as per the letter attached.
|
|
|
34
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
28/02/2025
|
The correction have been made as per the instruction received
|
|
|
35
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
18/03/2025
|
Detailed muck calculation and muck disposal scheme as approved by concerned DFO is not found submitted. State government shall submit the detailed muck disposal plan. ?????? ?????
|
|
|
36
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
30/12/2025
|
The correction have been made as per the instruction received
|
|
|
37
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
01/01/2026
|
Detailed muck calculation and muck disposal scheme as approved by concerned DFO is not found submitted. State government shall submit the detailed muck disposal plan.
|
|
|
38
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
29/04/2026
|
The correction have been made as per the instruction received
|
|
|
39
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
30/04/2026
|
plz find enclosed.
|
|
|
40
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
04/05/2026
|
send back
|
|
|
41
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
04/05/2026
|
PLZ FIND ENCOLSED
|
|
|
42
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
14/05/2026
|
send back
|
|
|
43
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
14/05/2026
|
plz find enclosed
|
|
|
44
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
14/05/2026
|
plz find enclosed.
|
|
|
45
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
18/05/2026
|
plz find enclosed
|
|
|
46
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
05/06/2026
|
As Per Letter No- 3498/12-1-2
Dt- 08-05-2026
|
|