Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
13/05/2022
|
send signed copies of part 1 in 5 copies
|
|
2
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
19/05/2022
|
The correction have been made as per the instruction received
|
|
3
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
26/05/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
4
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
03/06/2022
|
Hard copy has been sent.
|
|
5
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
27/06/2022
|
find the letter attached
|
|
6
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
30/06/2022
|
find the letter attached
|
|
7
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
02/07/2022
|
Remove objection as per letter attached.
|
|
8
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
12/08/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
26/08/2022
|
plz reupload the essential document as per point no. 2.
|
|
10
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
26/08/2022
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
29/08/2022
|
Plz remove objection
|
|
12
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
29/10/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
29/10/2022
|
objection remove
|
|
14
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
07/12/2022
|
please find the letter attached
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
19/01/2023
|
State Govt. may attend the following
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
26/01/2023
|
State Govt. may attend the following
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
26/01/2023
|
State Govt is requested to attend the shortcomings as per the letter attached.
|
|
18
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
27/01/2023
|
Do needful action as per EDS
|
|
19
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
04/02/2023
|
Remove objection.
|
|
20
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
14/07/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
27/07/2023
|
Objection removed.
|
|
22
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
23/08/2023
|
As per letter no 517 /12-1 dated 23-08-2023
|
|
23
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
01/09/2023
|
Remove objection.
|
|
24
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
23/09/2023
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
27/09/2023
|
remove objection & send back.
|
|
26
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
04/10/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
09/11/2023
|
provide the all necessary documents.
|
|
28
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
17/11/2023
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
06/12/2023
|
Objection removed.
|
|
30
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
14/12/2023
|
As per letter no 1465/12-1 dated 06-12-2023
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
20/12/2023
|
please find the letter attached
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
21/12/2023
|
please find the letter attached
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
06/02/2024
|
State Govt is requested to attend the shortcomings as per the letter attachment.
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
06/02/2024
|
State Govt is requested to attend the shortcomings as per the letter attachment.
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
21/02/2024
|
please find the letter attached
|
|
36
|
State secretary
|
REPLY
|
Regional Office
|
21/02/2024
|
please find the letter attached
|
|
37
|
RO/HQ
|
EDS
|
( RODEHR )
|
09/08/2024
|
E-file not received in ROHQ Division
|
|
38
|
Regional Office
|
EDS
|
State secretary
|
27/08/2024
|
EDS
|
|
39
|
State secretary
|
EDS
|
Nodal Officer
|
02/09/2024
|
Kindly attend EDS queries raised by MoEF&CC
|
|
40
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
29/10/2024
|
Kindly attend EDS queries raised by MoEF&CC
|
|
41
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
05/11/2024
|
Kindly attend EDS queries raised by MoEF&CC
|
|
42
|
DFO (Pithoragarh)
|
EDS
|
User Agency (ee.sbr.ujvn@gmail.com)
|
11/11/2024
|
remove objection.
|
|
43
|
User Agency (ee.sbr.ujvn@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
27/11/2024
|
The correction have been made as per the instruction received
|
|