Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Tripura South)
|
EDS
|
DFO (South District Forest)
|
10/09/2021
|
The proposal is incomplete shape, Therefore, Proposal is returned herewith.
|
|
2
|
DFO (South District Forest)
|
REPLY
|
CF (Tripura South)
|
14/09/2021
|
The correction made as per instruction received.
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
23/11/2021
|
The State Govt. is requested to provide following additional information for further
processing of the case: -
1) The nearest distance of proposed diversion site from Trishna WLS is 12.642878 Km and
ESZ of Trishna WLS is 12.374388 Km, whereas in site inspection report the DFO has
mentioned as more than 20 Km.The State Govt may clarify the difference in the distance
mentioned.
2) It is observed that the State Govt has proposed the location of the facilities in two plots,
which may be done in a single compact plot in order to reduce the impact of project over
the forest area. The State Govt may re-examine the same.
3) The details i.e. length & width of the approach road to the drill site.
4) In the recommendation at PAR-V, the State Govt has recommended minimal damage to
widening,
|
|
4
|
State secretary
|
EDS
|
Nodal Officer
|
24/11/2021
|
UA was requested to kindly furnish the observation
|
|
5
|
Nodal Officer
|
EDS
|
CF (Tripura South)
|
24/11/2021
|
A was requested to kindly furnish the observation
|
|
6
|
CF (Tripura South)
|
EDS
|
DFO (South District Forest)
|
24/11/2021
|
UA was requested to kindly furnish the observation
|
|
7
|
DFO (South District Forest)
|
EDS
|
User Agency (78672@ongc.co.in)
|
24/11/2021
|
UA was requested to kindly furnish the observation
|
|
8
|
User Agency (78672@ongc.co.in)
|
REPLY
|
DFO (South District Forest)
|
20/12/2021
|
The correction have been made as per the instruction received
|
|
9
|
DFO (South District Forest)
|
REPLY
|
CF (Tripura South)
|
13/06/2022
|
Correction made
|
|
10
|
CF (Tripura South)
|
REPLY
|
Nodal Officer
|
13/06/2022
|
The correction made as per instruction received.
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
13/06/2022
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
13/06/2022
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|
13
|
Regional Office
|
EDS
|
State secretary
|
20/06/2022
|
I am to inform that the additional information along with KML Shape file in respect to the alternative compensatory afforestation site over 6.131 ha submitted by the State Govt vide letter dated 10.06.2022 has been examined. As per the report the CA area at 2 (two) locations i.e. 8.14 ha consists of 7.12 MDF & 1.02 ha Open Forest 4.12 consist of 3.09 ha MDF & 1.03 ha Open Forest. As, maximum CA area is falling under MDF, therefore⢠the State Govt is requested to have the site inspected by an officer not below the rank of Conservator of Forests for inspection with specific report on the density of the proposed CA site for all the patches or choose an alternate site.
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
19/07/2022
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
08/08/2022
|
After detailed discussion by the Committee the proposal was recommended for sending to Ministry for approval by the competent authority subject to submission of the following: 1. The State Govt shall prepare soil conservation and biodiversity measures in and around the 2 lakes below the drill site and submit the revised plan at the cost of Rs 25.00 Lakhs. 2. No damages to the forest during widening of the road particularly the adjacent patches of plantation. 3. The User Agency should provide income generation activities for livelihood of nearby villagers in consultation with the State Govt. 4. Fencing as the approach road passes through thick forests & plantation by the user agency, wherever required.
5. Additional information sought by IRO, Shillong vide letter dated 22.11.2021 including
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
12/08/2022
|
UA was requested to kindly furnish the observation
|
|
17
|
Nodal Officer
|
EDS
|
CF (Tripura South)
|
12/08/2022
|
UA was requested to kindly furnish the observation
|
|
18
|
CF (Tripura South)
|
EDS
|
DFO (South District Forest)
|
12/08/2022
|
UA was requested to kindly furnish the observation
|
|
19
|
DFO (South District Forest)
|
EDS
|
User Agency (am_tripura@ongc.co.in)
|
12/08/2022
|
UA was requested to kindly furnish the observation
|
|
20
|
User Agency (am_tripura@ongc.co.in)
|
REPLY
|
DFO (South District Forest)
|
07/02/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (South District Forest)
|
REPLY
|
CF (Tripura South)
|
14/02/2023
|
The correction have been made as per the instruction received.
|
|
22
|
CF (Tripura South)
|
REPLY
|
Nodal Officer
|
14/02/2023
|
The correction have been made as per the instruction received.
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
14/02/2023
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
14/02/2023
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|