Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Regional Office
|
EDS
|
State secretary
|
29/10/2021
|
As per attached EDS
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
29/10/2022
|
furnish replies on EDS as called for by the IRO
|
|
3
|
Nodal Officer
|
REPLY
|
State secretary
|
17/04/2023
|
EDS reply Submitted to State Government Vide Lr dt: 13.04.2023
|
|
4
|
State secretary
|
REPLY
|
Regional Office
|
18/04/2023
|
EDS Reply is forwarded to IRO, Hyderabad vide Lr dt: 18.04.2023
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
31/05/2023
|
EDS
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
04/08/2023
|
furnish replies as called for by the IRO
|
|
7
|
Nodal Officer
|
EDS
|
CF (Adilabad)
|
29/08/2023
|
pl sfurnish EDS replies
|
|
8
|
CF (Adilabad)
|
EDS
|
DFO (Asifabad)
|
17/10/2023
|
Pls submit EDS replies as called for by the Nodal Officer
|
|
9
|
DFO (Asifabad)
|
REPLY
|
CF (Adilabad)
|
17/10/2023
|
EDS replies furnished for ZP road to Naguguda
|
|
10
|
CF (Adilabad)
|
REPLY
|
Nodal Officer
|
17/10/2023
|
The EDS replies furnished for ZP road to Naguguda by the DFO, KB Asifabad is submitted herewith for kind perusal.
|
|
11
|
Nodal Officer
|
REPLY
|
State secretary
|
18/10/2023
|
EDS submitted
|
|
12
|
State secretary
|
REPLY
|
Regional Office
|
23/11/2023
|
EDS replies submitted vide letter dt:21.10.2023
|
|