Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
25/11/2021
|
Tress canopy is seen on area to be diverted whereas you reported that no trees are getting affected. Also send complefte information regarding violation.
|
|
2
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
22/12/2021
|
Respected Sir, No tree pole plants in proposed diversion forest land. FRA 2006 Certificate uploaded in Additional Information Detail of Online Part 2 of Hoshiarpur Division
|
|
3
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
03/01/2022
|
Please send report regarding final decision against damage report court case or compensation.
|
|
4
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
07/02/2022
|
Respected Sir, reply regarding damage report is attached
|
|
5
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
30/03/2022
|
eds
|
|
6
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
05/04/2022
|
Please provide required information.
|
|
7
|
DFO (Hoshiarpur)
|
EDS
|
User Agency (rohtashkj7@gmail.com)
|
18/04/2022
|
Kindly submit the documents required as per attachment of objections from Nodal Office FCA
|
|
8
|
User Agency (rohtashkj7@gmail.com)
|
REPLY
|
DFO (Hoshiarpur)
|
12/09/2022
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
12/09/2022
|
Respected Sir, Reply of the objections raised by Nodal Office FCA Punjab. These all documents also uploaded in Additional Information Detail of Online Part 2
|
|
10
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
15/09/2022
|
Correct the violated area
|
|
11
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
15/09/2022
|
eds
|
|
12
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
15/09/2022
|
Correct the violated area in online part 2
|
|
13
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
15/09/2022
|
Respected Sir, Correction done of violated area in Online Part 2.
|
|
14
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
19/09/2022
|
Objection removed by DFO Hoshiarpur
|
|
15
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
04/10/2022
|
eds
|
|
16
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
12/10/2022
|
Eds
|
|
17
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
24/11/2022
|
Sir, Objection removed as per attachment letter
|
|
18
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
25/11/2022
|
eds
|
|
19
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
25/11/2022
|
Correction done
|
|
20
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
25/11/2022
|
Objection Removed
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
06/03/2023
|
eds
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
07/03/2023
|
eds
|
|
23
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
07/03/2023
|
eds
|
|
24
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
14/03/2023
|
eds
|
|
25
|
DFO (Hoshiarpur)
|
EDS
|
User Agency (rohtashkj7@gmail.com)
|
17/03/2023
|
Kindly upload DGPS map
|
|
26
|
User Agency (rohtashkj7@gmail.com)
|
REPLY
|
DFO (Hoshiarpur)
|
18/03/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
21/03/2023
|
EDS reply vide letter No 3367 dated 20-03-2023 for objection raised by GOI
|
|
28
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
18/04/2023
|
eds
|
|
29
|
DFO (Hoshiarpur)
|
EDS
|
User Agency (rohtashkj7@gmail.com)
|
24/04/2023
|
Kindly remove the objection as per attached objection letter
|
|
30
|
User Agency (rohtashkj7@gmail.com)
|
REPLY
|
DFO (Hoshiarpur)
|
24/04/2023
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
28/04/2023
|
Respected Sir, Objections removed as per attachment letter
|
|
32
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
29/04/2023
|
Eds removed by dfo
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
08/05/2023
|
Reply
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
08/05/2023
|
Reply
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
29/05/2023
|
eds
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
30/05/2023
|
eds
|
|
37
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
30/05/2023
|
eds
|
|
38
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
05/06/2023
|
eds
|
|
39
|
DFO (Hoshiarpur)
|
EDS
|
User Agency (rohtashkj7@gmail.com)
|
08/06/2023
|
Kindly submit the required information and documents as per attached GOI objection letter
|
|
40
|
User Agency (rohtashkj7@gmail.com)
|
REPLY
|
DFO (Hoshiarpur)
|
12/06/2023
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
13/06/2023
|
EDS reply vide letter No 953 dated 12-06-2023 for objection raised by GOI
|
|
42
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
13/06/2023
|
Objection removed by DFO Hoshiarpur
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
20/06/2023
|
Reply
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
20/06/2023
|
Reply
|
|
45
|
Regional Office
|
EDS
|
State secretary
|
11/07/2023
|
EDS
|
|
46
|
State secretary
|
EDS
|
Nodal Officer
|
14/07/2023
|
eds
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
14/07/2023
|
reply
|
|
48
|
State secretary
|
REPLY
|
Regional Office
|
14/07/2023
|
reply
|
|
49
|
Regional Office
|
EDS
|
State secretary
|
02/08/2023
|
eds
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
09/08/2023
|
eds
|
|
51
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
09/08/2023
|
eds
|
|
52
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
16/08/2023
|
eds
|
|
53
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
22/08/2023
|
EDS reply vide letter No 1367dated 18-08-2023
|
|
54
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
22/08/2023
|
eds replied by DFO
|
|
55
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
11/09/2023
|
eds
|
|
56
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
15/09/2023
|
eds
|
|
57
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
06/10/2023
|
EDS reply vide letter No 1622 dated 05-10-2023
|
|
58
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
11/10/2023
|
eds
|
|
59
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
05/03/2024
|
EDS reply vide letter No 2706 dated 23-02-2024
|
|
60
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
05/03/2024
|
eds replied by dfo
|
|
61
|
Nodal Officer
|
REPLY
|
State secretary
|
26/03/2024
|
Reply
|
|
62
|
State secretary
|
REPLY
|
Regional Office
|
26/03/2024
|
Reply
|
|
63
|
Regional Office
|
EDS
|
State secretary
|
13/06/2024
|
EDS
|
|
64
|
State secretary
|
EDS
|
Nodal Officer
|
14/06/2024
|
eds
|
|
65
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
14/06/2024
|
eds
|
|
66
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
18/06/2024
|
eds
|
|
67
|
DFO (Hoshiarpur)
|
REPLY
|
CF (Shiwalik Circle)
|
19/06/2024
|
Respected Sir, As per attachment reply English translation letters uploaded as per AIGF EDS 13-06-2024. These reply documents also uploaded in Additional Information Detail of online Part 2
|
|
68
|
CF (Shiwalik Circle)
|
REPLY
|
Nodal Officer
|
19/06/2024
|
eds removed by dfo hoshiarpur
|
|
69
|
Nodal Officer
|
REPLY
|
State secretary
|
24/06/2024
|
Reply
|
|
70
|
State secretary
|
REPLY
|
Regional Office
|
24/06/2024
|
reply
|
|
71
|
Regional Office
|
EDS
|
State secretary
|
20/06/2025
|
EDS
|
|
72
|
State secretary
|
EDS
|
Nodal Officer
|
24/06/2025
|
eds
|
|
73
|
Nodal Officer
|
EDS
|
CF (Shiwalik Circle)
|
27/06/2025
|
eds
|
|
74
|
CF (Shiwalik Circle)
|
EDS
|
DFO (Hoshiarpur)
|
30/06/2025
|
eds
|
|