Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Boudh)
|
EDS
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
13/07/2021
|
Correction required on land involved
|
|
2
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
REPLY
|
DFO (Boudh)
|
15/07/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Boudh)
|
EDS
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
30/07/2021
|
Submission of hard copies of diversion project proposal
|
|
4
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
REPLY
|
DFO (Boudh)
|
17/08/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Boudh)
|
EDS
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
26/08/2021
|
Re-submission of Tree Enumeration List
|
|
6
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
REPLY
|
DFO (Boudh)
|
13/09/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Nayagarh)
|
EDS
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
18/09/2021
|
Included tunnel Map Part-I in Parivesh Portal.
|
|
8
|
User Agency (dycecon2@ecor.railnet.gov.in)
|
REPLY
|
DFO (Nayagarh)
|
19/09/2021
|
The correction have been made as per the instruction received
|
|
9
|
CF (Berhampur)
|
EDS
|
DFO (Boudh)
|
21/09/2021
|
Discrepancies in diversion proposal of KHR-Bolangir Railway
|
|
10
|
DFO (Boudh)
|
REPLY
|
CF (Berhampur)
|
22/09/2021
|
Shortcomings of the project proposal has been complied.
|
|
11
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
03/11/2021
|
Please comply EDS to the deficiencies pointed out vide this office Memo No.18551 & 18553 dated 02.11.2021.
|
|
12
|
Nodal Officer
|
EDS
|
CF (Bhubaneswar)
|
03/11/2021
|
Please comply EDS to the deficiencies pointed out vide this office Memo No.18551 & 18553 dated 02.11.2021.
|
|
13
|
CF (Berhampur)
|
EDS
|
DFO (Boudh)
|
06/11/2021
|
Submit the point wise compliance report on the points raised by Addl Pr,CCF Nodal
|
|
14
|
DFO (Boudh)
|
REPLY
|
CF (Berhampur)
|
02/12/2021
|
Shortcomings of the project proposal has been complied.
|
|
15
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
06/12/2021
|
Submitted the compliance of the deficiency / observation and revised CA scheme
|
|
16
|
CF (Bhubaneswar)
|
EDS
|
DFO (Nayagarh)
|
19/01/2022
|
You are requested to identify the degraded forest land below 0.4 canopy density over 118 ha...........
|
|
17
|
DFO (Nayagarh)
|
REPLY
|
CF (Bhubaneswar)
|
06/08/2022
|
Essential Details.
|
|
18
|
CF (Bhubaneswar)
|
REPLY
|
Nodal Officer
|
16/08/2022
|
The Nayagarh Forest Division has submitted the compliance of the CA Scheme over an area of 586 ha of forest land (1086.663 ha gross area in 8 no forest blocks) with a financial outlay of 16.02 core for 10 years @ Rs.326/ MD.
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
20/09/2022
|
EDS raised from IRO, MoEF&CC, BBSR
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
20/09/2022
|
For necessary compliance.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
27/09/2022
|
Please comply the EDS vide this office Memo No. 18571 dated 21.09.2022.
|
|
22
|
Nodal Officer
|
EDS
|
CF (Bhubaneswar)
|
27/09/2022
|
Please comply the EDS vide this office Memo No. 18571 dated 21.09.2022.
|
|
23
|
CF (Berhampur)
|
EDS
|
DFO (Boudh)
|
29/09/2022
|
Please comply the observation made by the MOEF
|
|
24
|
DFO (Boudh)
|
REPLY
|
CF (Berhampur)
|
01/12/2022
|
Observations raised by MoEF has been complied
|
|
25
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
03/12/2022
|
DFO Boudh Division has submitted the compliance of the observations of REC dated.15.09.2022
|
|
26
|
CF (Bhubaneswar)
|
REPLY
|
Nodal Officer
|
07/12/2022
|
Diversion of 594-618 Ha. (292.289 Ha. in Nayagarh Forest Division and 302.329 Ha. in Boudh Forest Division)
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
07/12/2022
|
EDS has been complied vide this office letter No. 24486 dated 03.12.2022 to MoEF & CC, GoI, IRO, BBSR
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
08/12/2022
|
The compliance submitted to the DDGF, GoI, MoEF&CC, IRO, Bhubaneswar vide Letter No.24041, dt.28.11.2022 of the PCCF FD&NO, FC Act may be uploaded immediately.
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
08/12/2022
|
EDS has been complied vide this office letter No. 24041 dated 28.11.2022 to GoI, MoEF & CC, IRO, BBSR
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
08/12/2022
|
Point-wise compliances furnished by the PCCF (FD&NO) FC Act, O/o the PCCF & HoFF, Odisha vide letter No.24041, dt.28.11.2022.
|
|