TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/49169/2020              (ii). Name of Project for which Forest Land is required : Kalamang West (Northern Part) Block Iron Ore Mines of Tata Steel BSL Limited.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Forest Diversion Proposal over an area of 42.608 Ha of forest land (including safety zone 2.382 ha)under Section-2 (ii) of Forest (Conservation) Act, 1980 within the allotted mining lease over 92.875 ha in village Gandalpada under Barbil Tahasil & village Kalmanga & Ghodabudhani under Koira Tahasil              (iv). File no. : 8-13/2022-FC              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 42.608
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/OR/MIN/49169/202012/09/2020aa14/09/2020   09/10/2020

Keonjhar :12/10/2020


Bonai :12/10/2020

Rourkela:
  03/08/2021 (Bonai)

Rourkela:
  07/09/2021 (Keonjhar)

Orissa:
05/10/2021
Orissa:
02/06/2022
17/06/202221/12/2023
By :Head Office
Orissa
23/09/2024
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 14/07/2022  
Replied by State Government (Orissa) on:10/11/2022  
Query raised by MoEFCC,New Delhi on 27/12/2022  
Replied by State Government (Orissa) on:23/03/2023  
Query raised by MoEFCC,New Delhi on 11/05/2023  
Replied by State Government (Orissa) on:02/08/2023  
Query raised by MoEFCC,New Delhi on 04/09/2023  
Replied by State Government (Orissa) on:22/11/2023  
Query raised by State Government (Orissa) on:26/07/2022  
Replied by Nodal Officer (Orissa) on:04/11/2022  
Query raised by State Government (Orissa) on:21/01/2023  
Replied by Nodal Officer (Orissa) on:22/03/2023  
Query raised by State Government (Orissa) on:27/07/2023  
Replied by Nodal Officer (Orissa) on:31/07/2023  
Query raised by State Government (Orissa) on:21/09/2023  
Replied by Nodal Officer (Orissa) on:20/11/2023  
Query raised by Nodal Officer (Orissa) on:06/12/2021  
Replied by Circle(Rourkela) on:09/12/2021  
Query raised by Nodal Officer (Orissa) on:09/12/2021  
Replied by Circle(Rourkela) on:09/03/2022  
Query raised by Nodal Officer (Orissa) on:02/08/2022  
Replied by Circle(Rourkela) on:20/10/2022  
Query raised by Nodal Officer (Orissa) on:27/10/2023  
Replied by Circle(Rourkela) on:15/11/2023  
Query raised by Circle (Rourkela) on:09/12/2021  
Replied by DFO (Keonjhar) on:28/02/2022  
Query raised by Circle (Rourkela) on:09/12/2021  
Replied by DFO (Bonai) on:28/02/2022  
Query raised by Circle (Rourkela) on:02/08/2022  
Replied by DFO (Keonjhar) on:17/10/2022  
Query raised by Circle (Rourkela) on:02/08/2022  
Replied by DFO (Bonai) on:19/10/2022  
Query raised by Circle (Rourkela) on:30/10/2023  
Replied by DFO (Bonai) on:13/11/2023  
Query raised by Circle (Rourkela) on:30/10/2023  
Replied by DFO (Keonjhar) on:14/11/2023  
Query raised by DFO (Bonai) on:29/10/2020  
Replied by UA on :22/04/2021  
Query raised by DFO (Keonjhar) on:02/11/2020  
Replied by UA on :22/04/2021  
Query raised by DFO (Bonai) on:18/06/2021  
Replied by UA on :22/07/2021  
Query raised by DFO (Keonjhar) on:13/07/2021  
Replied by UA on :22/07/2021  
Query raised by DFO (Keonjhar) on:13/12/2021  
Replied by UA on :01/02/2022  
Query raised by DFO (Bonai) on:04/02/2022  
Replied by UA on :19/02/2022  
Query raised by DFO (Keonjhar) on:30/10/2023  
Replied by UA on :06/11/2023  
D. Essential Details Sought History (Stage-II)
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by MoEFCC,New Delhi 28/10/2024  
Query raised by State Government (Orissa) on:05/11/2024  
NOTE:- Proposal is pending at Nodal Officer after receiving Compliance of Conditions due to EDS raised by HO for Stage-II .