Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Angul)
|
EDS
|
User Agency (eecidivnjobra@gmail.com)
|
11/09/2017
|
Necessary authenticated document is wanting
|
|
2
|
User Agency (eecidivnjobra@gmail.com)
|
REPLY
|
DFO (Angul)
|
25/01/2018
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Angul)
|
EDS
|
User Agency (eecidivnjobra@gmail.com)
|
27/01/2018
|
Letter No.596 dt.20.01.2018
|
|
4
|
User Agency (eecidivnjobra@gmail.com)
|
REPLY
|
DFO (Angul)
|
21/01/2021
|
The correction have been made as per the instruction received
|
|
5
|
Nodal Officer
|
EDS
|
CF (Angul)
|
30/07/2021
|
Please comply EDS to the deficiencies pointed out vide this office Memo No.12557 dated 30.07.2021.
|
|
6
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
07/08/2021
|
The observation compliance of 87.52 of Forest land of Hidsingh Irrigation Project
|
|
7
|
DFO (Angul)
|
EDS
|
User Agency (eecidivnjobra@gmail.com)
|
07/08/2021
|
Memo No.6123 dt.07.08.2021
|
|
8
|
User Agency (eecidivnjobra@gmail.com)
|
REPLY
|
DFO (Angul)
|
25/10/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
26/10/2023
|
Compliance report
|
|
10
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
13/11/2023
|
Point wise Compliance to the observation made vide your Memo No.13545 dated 11.07.202 forwarded.
|
|
11
|
Nodal Officer
|
EDS
|
CF (Angul)
|
04/12/2023
|
Please comply the EDS vide this office Letter No. 23623 dated 04.12.2023.
|
|
12
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
08/12/2023
|
DFO Angul to resubmit the plan dely the complying the observation
|
|
13
|
DFO (Angul)
|
EDS
|
User Agency (eecidivnjobra@gmail.com)
|
08/12/2023
|
EDS to UA
|
|
14
|
User Agency (eecidivnjobra@gmail.com)
|
REPLY
|
DFO (Angul)
|
28/12/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
09/01/2024
|
EDS reply
|
|
16
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
02/02/2024
|
The CATP of Hidsingh Project forwarded
|
|
17
|
State secretary
|
EDS
|
Nodal Officer
|
30/03/2024
|
For necessary compliance
|
|
18
|
Nodal Officer
|
EDS
|
CF (Angul)
|
05/04/2024
|
Please comply the EDS vide this office Memo No. 7498 dated 05.04.2024
|
|
19
|
CF (Angul)
|
EDS
|
DFO (Angul)
|
06/04/2024
|
DFO Angul to submit Compliance.
|
|
20
|
DFO (Angul)
|
EDS
|
User Agency (eecidivnjobra@gmail.com)
|
08/04/2024
|
EDS
|
|
21
|
User Agency (eecidivnjobra@gmail.com)
|
REPLY
|
DFO (Angul)
|
17/04/2024
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Angul)
|
REPLY
|
CF (Angul)
|
25/04/2024
|
EDS reply
|
|
23
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
06/05/2024
|
Compliance on the observation made by Govt. of Odisha FE &CC Department forwarded to PCCF Nodal.
|
|
24
|
Nodal Officer
|
REPLY
|
State secretary
|
21/05/2024
|
Compliance submitted to GoI, MOEF & C, RO, BBSR vide this office Letter No. 10498 dated 20.05.2024.
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
24/07/2024
|
EDS raised by RO, Bhubaneswar
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
01/08/2024
|
Kindly take necessary action so that the proposal can be sent to the GoI, MoEF&CC, New Delhi.
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
12/09/2024
|
The instant proposal may kindly be submitted to GoI, MoEF&CC, New Delhi for further course of action.
|
|