Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
13/01/2023
|
Panjiyan & Processing fee Letter no 281, 282 dt 13-01-2023
|
|
2
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
09/02/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
24/03/2023
|
Lt No 281 Dt 13-01-2023
|
|
4
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
24/03/2023
|
The correction have been made as per the instruction received
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
21/07/2023
|
EDS letter on 21.07.2023
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
27/07/2023
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
27/07/2023
|
Nodal Officer letter dt. 27/07/2023 enclosed.
|
|
8
|
CF (Balaghat (T))
|
EDS
|
DFO (Balaghat South(T))
|
27/07/2023
|
Nodal Officer letter dt. 27/07/2023 enclosed.
|
|
9
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
27/07/2023
|
Nodal Officer letter dt. 27/07/2023 enclosed.
|
|
10
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
11/08/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Balaghat South(T))
|
REPLY
|
CF (Balaghat (T))
|
17/08/2023
|
Lt No 4405 Dt 08-08-2023
|
|
12
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
21/08/2023
|
Lt no 4405 Dt. 08-08-2023
|
|
13
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
24/08/2023
|
EDS for alternative alignment
|
|
14
|
CF (Balaghat (T))
|
EDS
|
DFO (Balaghat South(T))
|
24/08/2023
|
EDS for alternative alignment
|
|
15
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
24/08/2023
|
|
|
16
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
25/08/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Balaghat South(T))
|
REPLY
|
CF (Balaghat (T))
|
05/09/2023
|
FP/MP/Road/155493/2022
|
|
18
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
06/09/2023
|
Forwarded
|
|
19
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
11/09/2023
|
UPLOAD RDF CA LAND
|
|
20
|
CF (Balaghat (T))
|
EDS
|
DFO (Balaghat South(T))
|
11/09/2023
|
|
|
21
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
12/09/2023
|
|
|
22
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
14/09/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Balaghat South(T))
|
REPLY
|
CF (Balaghat (T))
|
14/09/2023
|
|
|
24
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
14/09/2023
|
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
15/09/2023
|
Nodal Officer letter dt. 15/09/2023 enclosed.
|
|
26
|
State secretary
|
REPLY
|
Regional Office
|
15/09/2023
|
Nodal Officer letter dt. 15/09/2023 enclosed.
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
19/12/2023
|
EDS letter on 18.12.2023
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
21/12/2023
|
|
|
29
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
21/12/2023
|
Nodal Officer letter dated 21-12-2023 enclosed.
|
|
30
|
CF (Balaghat (T))
|
EDS
|
DFO (Balaghat South(T))
|
21/12/2023
|
Nodal Officer letter dated 21-12-2023 enclosed.
|
|
31
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
21/12/2023
|
Lt No 5361, 5362 Dt 21-12-2023
|
|
32
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
24/12/2023
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Balaghat South(T))
|
REPLY
|
CF (Balaghat (T))
|
08/01/2024
|
FP/MP/Road/155493/2022
|
|
34
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
08/01/2024
|
lt.no. 31 date 08-01-2024
|
|
35
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
25/01/2024
|
|
|
36
|
CF (Balaghat (T))
|
EDS
|
DFO (Balaghat South(T))
|
25/01/2024
|
|
|
37
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
25/01/2024
|
|
|
38
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
25/01/2024
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Balaghat South(T))
|
REPLY
|
CF (Balaghat (T))
|
26/01/2024
|
FP/MP/Road/155493/2022
Corridor
|
|
40
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
27/01/2024
|
Attached Lt. no. 119 Dt. 27-01-2024
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
20/03/2024
|
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
20/03/2024
|
Nodal Officer letter dt. 20/03/2024 enclosed.
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
15/04/2024
|
EDS letter on12.04.2024
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
18/04/2024
|
|
|
45
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
18/04/2024
|
Nodal Officer letter dated 18-04-2024 enclosed.
|
|
46
|
CF (Balaghat (T))
|
EDS
|
DFO (Balaghat South(T))
|
18/04/2024
|
Nodal Officer letter dated 18-04-2024 enclosed.
|
|
47
|
DFO (Balaghat South(T))
|
EDS
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
09/06/2024
|
Lt No 3455 Dt 30-04-2024
|
|
48
|
User Agency (gm_bgtpiu1@rediffmail.com)
|
REPLY
|
DFO (Balaghat South(T))
|
10/06/2024
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Balaghat South(T))
|
REPLY
|
CF (Balaghat (T))
|
22/06/2024
|
Lt No 4189 Dt 21-06-2024
|
|
50
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
24/06/2024
|
Forwarded
|
|
51
|
Nodal Officer
|
REPLY
|
State secretary
|
26/06/2024
|
Nodal Officer letter dated 26-06-2024 enclosed.
|
|
52
|
State secretary
|
REPLY
|
Regional Office
|
26/06/2024
|
Nodal Officer letter dated 26-06-2024 enclosed.
|
|
53
|
Regional Office
|
EDS
|
State secretary
|
29/08/2024
|
EDS letter on 27.08.2024
|
|
54
|
State secretary
|
EDS
|
Nodal Officer
|
02/09/2024
|
|
|
55
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
02/09/2024
|
Nodal Officer letter dated 02-09-2024 enclosed.
|
|
56
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
06/09/2024
|
Forward
|
|
57
|
Nodal Officer
|
REPLY
|
State secretary
|
11/09/2024
|
Nodal officer letter dated 11-09-24
|
|
58
|
State secretary
|
REPLY
|
Regional Office
|
11/09/2024
|
Nodal officer letter dated 11-09-24
|
|