TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/ROAD/155493/2022              (ii). Name of Project for which Forest Land is required : Construction of road from Kandrikala to Kattipar Road under RCPLWEA scheme              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Construction of road from village Kandrikala to Kattipar under RCPLWEA scheme in Balaghat Dist.              (iv). File no. : 6-MPR019/2023-BHO              (v). State : Madhya Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 7.47
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MP/ROAD/155493/202218/05/202225/11/2022  21/06/2022  18/05/2022   30/11/2022  19/11/2022  20/06/2022   30/11/2022   09/12/2022 Balaghat South(T) :09/12/2022Balaghat (T):
  09/04/2023 (Balaghat South(T))

Madhya Pradesh:
09/04/2023
Madhya Pradesh:
20/04/2023
Bhopal:
12/05/2023
05/11/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhopal) on:21/07/2023  
Replied by State Government(Madhya Pradesh) on:15/09/2023  
Query raised by Regional Office (Bhopal) on:19/12/2023  
Replied by State Government(Madhya Pradesh) on:20/03/2024  
Query raised by Regional Office (Bhopal) on:15/04/2024  
Replied by State Government(Madhya Pradesh) on:26/06/2024  
Query raised by Regional Office (Bhopal) on:29/08/2024  
Replied by State Government(Madhya Pradesh) on:11/09/2024  
Query raised by State Government (Madhya Pradesh) on:27/07/2023  
Replied by Nodal Officer (Madhya Pradesh) on:15/09/2023  
Query raised by State Government (Madhya Pradesh) on:21/12/2023  
Replied by Nodal Officer (Madhya Pradesh) on:20/03/2024  
Query raised by State Government (Madhya Pradesh) on:18/04/2024  
Replied by Nodal Officer (Madhya Pradesh) on:26/06/2024  
Query raised by State Government (Madhya Pradesh) on:02/09/2024  
Replied by Nodal Officer (Madhya Pradesh) on:11/09/2024  
Query raised by Nodal Officer (Madhya Pradesh) on:27/07/2023  
Replied by Circle(Balaghat (T)) on:21/08/2023  
Query raised by Nodal Officer (Madhya Pradesh) on:24/08/2023  
Replied by Circle(Balaghat (T)) on:06/09/2023  
Query raised by Nodal Officer (Madhya Pradesh) on:11/09/2023  
Replied by Circle(Balaghat (T)) on:14/09/2023  
Query raised by Nodal Officer (Madhya Pradesh) on:21/12/2023  
Replied by Circle(Balaghat (T)) on:08/01/2024  
Query raised by Nodal Officer (Madhya Pradesh) on:25/01/2024  
Replied by Circle(Balaghat (T)) on:27/01/2024  
Query raised by Nodal Officer (Madhya Pradesh) on:18/04/2024  
Replied by Circle(Balaghat (T)) on:24/06/2024  
Query raised by Nodal Officer (Madhya Pradesh) on:02/09/2024  
Replied by Circle(Balaghat (T)) on:06/09/2024  
Query raised by Circle (Balaghat (T)) on:27/07/2023  
Replied by DFO (Balaghat South(T)) on:17/08/2023  
Query raised by Circle (Balaghat (T)) on:24/08/2023  
Replied by DFO (Balaghat South(T)) on:05/09/2023  
Query raised by Circle (Balaghat (T)) on:11/09/2023  
Replied by DFO (Balaghat South(T)) on:14/09/2023  
Query raised by Circle (Balaghat (T)) on:21/12/2023  
Replied by DFO (Balaghat South(T)) on:08/01/2024  
Query raised by Circle (Balaghat (T)) on:25/01/2024  
Replied by DFO (Balaghat South(T)) on:26/01/2024  
Query raised by Circle (Balaghat (T)) on:18/04/2024  
Replied by DFO (Balaghat South(T)) on:22/06/2024  
Query raised by DFO (Balaghat South(T)) on:13/01/2023  
Replied by UA on :09/02/2023  
Query raised by DFO (Balaghat South(T)) on:24/03/2023  
Replied by UA on :24/03/2023  
Query raised by DFO (Balaghat South(T)) on:27/07/2023  
Replied by UA on :11/08/2023  
Query raised by DFO (Balaghat South(T)) on:24/08/2023  
Replied by UA on :25/08/2023  
Query raised by DFO (Balaghat South(T)) on:12/09/2023  
Replied by UA on :14/09/2023  
Query raised by DFO (Balaghat South(T)) on:21/12/2023  
Replied by UA on :24/12/2023  
Query raised by DFO (Balaghat South(T)) on:25/01/2024  
Replied by UA on :25/01/2024  
Query raised by DFO (Balaghat South(T)) on:09/06/2024  
Replied by UA on :10/06/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...