| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
21/05/2017
|
Query for CA Land Inspection
|
|
|
2
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
29/05/2017
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
29/05/2017
|
attached copy of Joint Inspection and certificate
|
|
|
4
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
04/07/2017
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
08/09/2017
|
plz upload site inspection report bacis on 24 points
|
|
|
6
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
09/09/2017
|
Your letter no. 2755 dt. 06.09.2017. query reply with 24 points of site inspection report attached
|
|
|
7
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
13/09/2017
|
please again upload site inspection report, 24 points
|
|
|
8
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
13/09/2017
|
Re upload site inspection report, 24 point
|
|
|
9
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
22/09/2017
|
plz prepared to new proposal with i/c area of mining area approach road
|
|
|
10
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
03/10/2017
|
Plz prepared to new proposal with mining area appriach road.
|
|
|
11
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
25/10/2017
|
The correction have been made as per the instruction received
|
|
|
12
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
06/11/2017
|
pls complete 5 point
|
|
|
13
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
02/07/2018
|
The correction have been made as per the instruction received
|
|
|
14
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
23/07/2018
|
pls watch query of 5 point
|
|
|
15
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
03/08/2018
|
The correction have been made as per the instruction received
|
|
|
16
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
11/09/2018
|
Marking of Road Area and non minable
|
|
|
17
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
04/10/2018
|
The correction have been made as per the instruction received
|
|
|
18
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
06/03/2019
|
pls watch 3 point of query.
|
|
|
19
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
12/03/2019
|
lt no 911 dt. 12-03-2019
|
|
|
20
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
01/06/2019
|
Corrected as per instruction given.
|
|
|
21
|
State secretary
|
EDS
|
Nodal Officer
|
20/08/2020
|
|
|
|
22
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
20/08/2020
|
|
|
|
23
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
20/08/2020
|
|
|
|
24
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
20/08/2020
|
|
|
|
25
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
07/11/2020
|
The correction have been made as per the instruction received
|
|
|
26
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
22/12/2020
|
|
|
|
27
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
03/05/2021
|
The correction have been made as per the instruction received
|
|
|
28
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
03/05/2021
|
|
|
|
29
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
03/05/2021
|
|
|
|
30
|
Nodal Officer
|
REPLY
|
State secretary
|
03/05/2021
|
|
|
|
31
|
Head Office
|
EDS
|
State secretary
|
27/05/2021
|
EDS
|
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
02/06/2021
|
|
|
|
33
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
02/06/2021
|
|
|
|
34
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
02/06/2021
|
|
|
|
35
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
02/06/2021
|
|
|
|
36
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
14/02/2022
|
The correction have been made as per the instruction received
|
|
|
37
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
16/12/2022
|
Corrected as per instruction given.
|
|
|
38
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
27/12/2022
|
Letter No. 1302 dt. 16.12.2022
|
|
|
39
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
11/07/2023
|
|
|
|
40
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
11/07/2023
|
|
|
|
41
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
11/07/2023
|
|
|
|
42
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
11/07/2023
|
|
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
04/09/2023
|
Nodal Officer letter dt. 31-08-2023 enclosed.
|
|
|
44
|
State secretary
|
REPLY
|
Head Office
|
04/09/2023
|
Nodal Officer letter dt. 31-08-2023 enclosed.
|
|
|
45
|
Head Office
|
EDS
|
State secretary
|
10/10/2023
|
EDS
|
|
|
46
|
State secretary
|
EDS
|
Nodal Officer
|
17/10/2023
|
|
|
|
47
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
17/10/2023
|
Nodal Officer letter dt. 17-10-2023 enclosed.
|
|
|
48
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
17/10/2023
|
Nodal Officer letter dt. 17-10-2023 enclosed.
|
|
|
49
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
10/11/2023
|
Complete information about the 3 point given in the Letter No. 4633 Dt. 17-10-2023
|
|
|
50
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
10/11/2023
|
forwarded
|
|
|
51
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
11/01/2024
|
|
|
|
52
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
11/01/2024
|
|
|
|
53
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
11/01/2024
|
|
|
|
54
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
11/01/2024
|
The correction have been made as per the instruction received
|
|
|
55
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
11/01/2024
|
|
|
|
56
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
11/01/2024
|
|
|
|
57
|
Nodal Officer
|
REPLY
|
State secretary
|
15/01/2024
|
|
|
|
58
|
State secretary
|
REPLY
|
Head Office
|
15/01/2024
|
Nodal Officer letter dt. 12-01-2024 enclosed.
|
|
|
59
|
Head Office
|
EDS
|
State secretary
|
03/02/2024
|
EDS
|
|
|
60
|
State secretary
|
EDS
|
Nodal Officer
|
13/02/2024
|
|
|
|
61
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
13/02/2024
|
Nodal Officer letter dt. 08-02-2024 enclosed.
|
|
|
62
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
13/02/2024
|
Nodal Officer letter dt. 08-02-2024 enclosed.
|
|
|
63
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
23/02/2024
|
|
|
|
64
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
23/02/2024
|
The correction have been made as per the instruction received
|
|
|
65
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
23/02/2024
|
|
|
|
66
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
23/02/2024
|
|
|
|
67
|
Nodal Officer
|
REPLY
|
State secretary
|
23/02/2024
|
|
|
|
68
|
State secretary
|
REPLY
|
Head Office
|
23/02/2024
|
Nodal Officer letter dated 23-2-24 uploaded
|
|
|
69
|
Head Office
|
EDS
|
State secretary
|
22/03/2024
|
EDS
|
|
|
70
|
State secretary
|
EDS
|
Nodal Officer
|
16/04/2024
|
|
|
|
71
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
16/04/2024
|
Nodal Officer letter dt. 15-04-2024 enclosed.
|
|
|
72
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
16/04/2024
|
Nodal Officer letter dt. 15-04-2024 enclosed.
|
|
|
73
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
27/08/2024
|
Letter No. F-1/MP/MIN/23750/2017/2073 dt. 15.04.2024 According to this letter, 3 point information.
|
|
|
74
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
02/09/2024
|
Forwarded
|
|
|
75
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
06/09/2024
|
|
|
|
76
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
06/09/2024
|
|
|
|
77
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
06/09/2024
|
|
|
|
78
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
06/09/2024
|
The correction have been made as per the instruction received
|
|
|
79
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
06/09/2024
|
|
|
|
80
|
CF (Balaghat (T))
|
REPLY
|
Nodal Officer
|
06/09/2024
|
|
|
|
81
|
Nodal Officer
|
REPLY
|
State secretary
|
13/09/2024
|
Nodal Officer letter dt. 13-09-2024 enclosed.
|
|
|
82
|
State secretary
|
REPLY
|
Head Office
|
13/09/2024
|
Nodal Officer letter dt. 13-09-2024 enclosed.
|
|
|
83
|
Head Office
|
EDS
|
State secretary
|
09/10/2024
|
EDS
|
|
|
84
|
State secretary
|
EDS
|
Nodal Officer
|
09/10/2024
|
|
|
|
85
|
Nodal Officer
|
EDS
|
CF (Balaghat (T))
|
09/10/2024
|
Nodal Officer letter dt. 09-10-2024 enclosed.
|
|
|
86
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
09/10/2024
|
Nodal Officer letter dt. 09-10-2024 enclosed.
|
|
|
87
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
06/05/2025
|
letter no. 2026 dt. 06.05.2025 pls reply
|
|
|
88
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
20/01/2026
|
The correction have been made as per the instruction received
|
|
|
89
|
DFO (North Balaghat)
|
EDS
|
User Agency (akhileshmalvi@gmail.com)
|
13/02/2026
|
Upload KML file and map as per EDS, point 9
|
|
|
90
|
User Agency (akhileshmalvi@gmail.com)
|
REPLY
|
DFO (North Balaghat)
|
14/02/2026
|
The correction have been made as per the instruction received
|
|
|
91
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
26/02/2026
|
GOVT of India Letter Date 09-10-2024 EDS Reply (9 point)
|
|
|
92
|
CF (Balaghat (T))
|
EDS
|
DFO (North Balaghat)
|
07/03/2026
|
Recheck and give the proper reason and justification of Point no. II and V
|
|
|
93
|
DFO (North Balaghat)
|
REPLY
|
CF (Balaghat (T))
|
29/04/2026
|
Point number 2 and 5 have been completed.
|
|