TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/MP/IRRIG/33191/2018              (ii). Name of Project for which Forest Land is required : Mandliya Ghat Tank Project              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Mandliya ghat tank is situated at near by Mandliya village tehsil bajna district Ratlam. The Construction of Mandliya Ghat Tank is essential to required 14.61 hact. Forest Land are compartment No. PF-83 PF-84 and PF85              (iv). State : Madhya Pradesh              (v). Category of the Project : Irrigation              (vi). Shape of forest land proposed to be diverted : Non Linear              (vii). Area of forest land proposed for diversion(in ha.): 32.15
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/MP/IRRIG/33191/201818/04/201824/09/2018  11/09/2018  23/08/2018  20/04/2018   04/10/2018  22/09/2018  09/09/2018  14/08/2018   04/10/2018   26/10/2018 Ratlam(T) :27/10/2018Ujjain(T):
  07/03/2019 (Ratlam(T))

Madhya Pradesh:
16/03/2019
Madhya Pradesh:
30/03/2019
Bhopal:
30/04/2019
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhopal) on:27/05/2019  
Replied by State Government(Madhya Pradesh) on:13/09/2019  
Query raised by Regional Office (Bhopal) on:25/09/2019  
Replied by State Government(Madhya Pradesh) on:15/03/2023  
Query raised by Regional Office (Bhopal) on:30/05/2023  
Replied by State Government(Madhya Pradesh) on:08/07/2026  
Query raised by State Government (Madhya Pradesh) on:30/04/2019  
Replied by Nodal Officer (Madhya Pradesh) on:30/04/2019  
Query raised by State Government (Madhya Pradesh) on:29/05/2019  
Replied by Nodal Officer (Madhya Pradesh) on:13/09/2019  
Query raised by State Government (Madhya Pradesh) on:16/12/2019  
Replied by Nodal Officer (Madhya Pradesh) on:15/03/2023  
Query raised by State Government (Madhya Pradesh) on:01/06/2023  
Replied by Nodal Officer (Madhya Pradesh) on:08/07/2026  
Query raised by Nodal Officer (Madhya Pradesh) on:30/04/2019  
Replied by Circle(Ujjain(T)) on:30/04/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:29/05/2019  
Replied by Circle(Ujjain(T)) on:07/09/2019  
Query raised by Nodal Officer (Madhya Pradesh) on:16/12/2019  
Replied by Circle(Ujjain(T)) on:23/05/2022  
Query raised by Nodal Officer (Madhya Pradesh) on:24/06/2022  
Replied by Circle(Ujjain(T)) on:03/03/2023  
Query raised by Nodal Officer (Madhya Pradesh) on:01/06/2023  
Replied by Circle(Ujjain(T)) on:27/05/2026  
Query raised by Nodal Officer (Madhya Pradesh) on:15/06/2026  
Replied by Circle(Ujjain(T)) on:30/06/2026  
Query raised by Circle (Ujjain(T)) on:30/04/2019  
Replied by DFO (Ratlam(T)) on:30/04/2019  
Query raised by Circle (Ujjain(T)) on:29/05/2019  
Replied by DFO (Ratlam(T)) on:05/09/2019  
Query raised by Circle (Ujjain(T)) on:16/12/2019  
Replied by DFO (Ratlam(T)) on:01/07/2021  
Query raised by Circle (Ujjain(T)) on:06/07/2021  
Replied by DFO (Ratlam(T)) on:08/07/2021  
Query raised by Circle (Ujjain(T)) on:16/07/2021  
Replied by DFO (Ratlam(T)) on:17/05/2022  
Query raised by Circle (Ujjain(T)) on:24/06/2022  
Replied by DFO (Ratlam(T)) on:27/02/2023  
Query raised by Circle (Ujjain(T)) on:01/06/2023  
Replied by DFO (Ratlam(T)) on:25/05/2026  
Query raised by DFO (Ratlam(T)) on:04/12/2018  
Replied by UA on :08/02/2019  
Query raised by DFO (Ratlam(T)) on:30/04/2019  
Replied by UA on :30/04/2019  
Query raised by DFO (Ratlam(T)) on:29/05/2019  
Replied by UA on :03/09/2019  
Query raised by DFO (Ratlam(T)) on:16/12/2019  
Replied by UA on :16/02/2020  
Query raised by DFO (Ratlam(T)) on:16/03/2020  
Replied by UA on :12/06/2021  
Query raised by DFO (Ratlam(T)) on:16/07/2021  
Replied by UA on :29/03/2022  
Query raised by DFO (Ratlam(T)) on:01/04/2022  
Replied by UA on :06/04/2022  
Query raised by DFO (Ratlam(T)) on:18/04/2022  
Replied by UA on :19/04/2022  
Query raised by DFO (Ratlam(T)) on:24/06/2022  
Replied by UA on :11/02/2023  
Query raised by DFO (Ratlam(T)) on:01/06/2023  
Replied by UA on :27/11/2023  
Query raised by DFO (Ratlam(T)) on:30/11/2023  
Replied by UA on :02/05/2024  
Query raised by DFO (Ratlam(T)) on:02/05/2024  
Replied by UA on :10/06/2024  
Query raised by DFO (Ratlam(T)) on:11/06/2024  
Replied by UA on :30/04/2026  
NOTE:- Proposal is pending at Regional Office .