| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Shahapur)
|
EDS
|
User Agency (jsw_maharashtra@enviroconcern.in)
|
26/08/2022
|
Comply shortcomings as per the letter attached herewith.
|
|
|
2
|
User Agency (jsw_maharashtra@enviroconcern.in)
|
REPLY
|
DFO (Shahapur)
|
26/12/2022
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Shahapur)
|
EDS
|
User Agency (jsw_maharashtra@enviroconcern.in)
|
24/11/2023
|
Please make the corrections in the proposal as per your request letter and submit the revised proposal.
|
|
|
4
|
User Agency (jsw_maharashtra@enviroconcern.in)
|
REPLY
|
DFO (Shahapur)
|
27/11/2023
|
The correction have been made as per the instruction received
|
|
|
5
|
DFO (Shahapur)
|
EDS
|
User Agency (bhavail.psp@jsw.in)
|
21/01/2025
|
As per your request letter Dt.20.01.2025 the praposal is sending back for necessary correction
|
|
|
6
|
User Agency (bhavail.psp@jsw.in)
|
REPLY
|
DFO (Shahapur)
|
29/03/2025
|
The correction have been made as per the instruction received
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Nashik)
|
16/05/2025
|
For Physical copy submission
|
|
|
8
|
Nodal Officer
|
EDS
|
CF (Thane)
|
16/05/2025
|
For Physical copy submission
|
|
|
9
|
CF (Thane)
|
REPLY
|
Nodal Officer
|
19/05/2025
|
physical copy submitted
|
|
|
10
|
CF (Nashik)
|
REPLY
|
Nodal Officer
|
20/05/2025
|
Recommended as mentioned in Part III & Site Inspection Report
|
|
|
11
|
State secretary
|
EDS
|
Nodal Officer
|
10/06/2025
|
EDS
|
|
|
12
|
Nodal Officer
|
EDS
|
CF (Nashik)
|
11/06/2025
|
Query raised by this office letter dated-05/06/2025
|
|
|
13
|
Nodal Officer
|
EDS
|
CF (Thane)
|
11/06/2025
|
Query raised by this office letter dated-05/06/2025
|
|
|
14
|
CF (Nashik)
|
EDS
|
DFO (West Nashik(Nashik))
|
11/06/2025
|
Query raised by this office letter dated-05/06/2025
|
|
|
15
|
DFO (West Nashik(Nashik))
|
EDS
|
User Agency (bhavail.psp@jsw.in)
|
21/06/2025
|
Letter No 278 dt 21.06.2025
|
|
|
16
|
User Agency (bhavail.psp@jsw.in)
|
REPLY
|
DFO (West Nashik(Nashik))
|
21/06/2025
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (West Nashik(Nashik))
|
REPLY
|
CF (Nashik)
|
22/06/2025
|
Replied to query raised by CCF office.
|
|
|
18
|
CF (Nashik)
|
REPLY
|
Nodal Officer
|
23/06/2025
|
DYCF West Nashik has complied the query
|
|
|
19
|
CF (Thane)
|
EDS
|
DFO (Shahapur)
|
23/06/2025
|
As per Request from DCF,Shahapur
|
|
|
20
|
DFO (Shahapur)
|
REPLY
|
CF (Thane)
|
09/07/2025
|
comply shortcomings as per the letter attached herewith
|
|
|
21
|
CF (Thane)
|
REPLY
|
Nodal Officer
|
09/07/2025
|
Query Compliance submitted By CCF Office Thane vide letter no.57 dt.08.07.2025
|
|
|
22
|
Nodal Officer
|
REPLY
|
State secretary
|
10/07/2025
|
Query Compliance
|
|
|
23
|
Head Office
|
EDS
|
State secretary
|
04/09/2025
|
EDS
|
|
|
24
|
State secretary
|
EDS
|
Nodal Officer
|
05/09/2025
|
EDS raised by GOI
|
|
|
25
|
Nodal Officer
|
EDS
|
CF (Nashik)
|
08/09/2025
|
Query raised by this office letter dated-04/09/2025
|
|
|
26
|
Nodal Officer
|
EDS
|
CF (Thane)
|
08/09/2025
|
Query raised by this office letter dated-04/09/2025
|
|
|
27
|
CF (Thane)
|
EDS
|
DFO (Shahapur)
|
10/09/2025
|
QUERY RAISED
|
|
|
28
|
DFO (Shahapur)
|
EDS
|
User Agency (bhavail.psp@jsw.in)
|
26/09/2025
|
comply shortcomings as per the letter attachted here with
|
|
|
29
|
User Agency (bhavail.psp@jsw.in)
|
REPLY
|
DFO (Shahapur)
|
13/10/2025
|
The correction have been made as per the instruction received
|
|
|
30
|
DFO (Shahapur)
|
EDS
|
User Agency (bhavail.psp@jsw.in)
|
27/10/2025
|
Comply Shortcomings as per the letter attachted here with
|
|
|
31
|
User Agency (bhavail.psp@jsw.in)
|
REPLY
|
DFO (Shahapur)
|
28/10/2025
|
The correction have been made as per the instruction received
|
|
|
32
|
DFO (Shahapur)
|
REPLY
|
CF (Thane)
|
06/11/2025
|
comply shortcoming as per the letter attached here with
|
|