TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/KL/ROAD/148616/2021              (ii). Name of Project for which Forest Land is required : Construction of Twin Tunnel (2+2 lane) with Four Lane Approaches (from existing roads) for providing direct connectivity between Aanakampoyil­ Kalladi-Meppadi in Kozhikode and Wayanad Districts of Ker              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The project road starts at Anakkampoyil at Design Ch: 0+000 km (11°27'2.04"N, 76° 6'5.61"E) and ends at Meppadi at Design Ch 8+735 (11°31'20.67"N, 76° 8'1.38"E), having total length of 8.735, out of which 8.11 km of the project alignment is proposed as tunnel. Proposed ROW of the approach roads vari              (iv). File no. : 4-KLC1368/2022-BAN              (v). State : Kerala              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 17.263
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KL/ROAD/148616/202122/10/202127/10/2021  27/10/2021   10/11/2021  27/10/2021   10/11/2021   11/11/2021

Kozhikode :12/11/2021


Wayanad South :12/11/2021

CCF Northern Circle:
  11/02/2022 (Wayanad South)

CCF Northern Circle:
  14/02/2022 (Kozhikode)

Kerala:
03/03/2022
Kerala:
19/07/2022
Bangalore:
01/08/2022
31/03/2023
By :Regional Office
Kerala
14/11/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:29/08/2022  
Replied by State Government(Kerala) on:28/02/2023  
Query raised by State Government (Kerala) on:06/09/2022  
Replied by Nodal Officer (Kerala) on:27/02/2023  
Query raised by Nodal Officer (Kerala) on:01/04/2022  
Replied by Circle(CCF Northern Circle) on:30/05/2022  
Query raised by Nodal Officer (Kerala) on:21/06/2022  
Replied by Circle(CCF Northern Circle) on:01/07/2022  
Query raised by Nodal Officer (Kerala) on:15/10/2022  
Replied by Circle(CCF Northern Circle) on:13/01/2023  
Query raised by Nodal Officer (Kerala) on:31/01/2023  
Replied by Circle(CCF Northern Circle) on:02/02/2023  
Query raised by Nodal Officer (Kerala) on:07/02/2023  
Replied by Circle(CCF Northern Circle) on:07/02/2023  
Query raised by Nodal Officer (Kerala) on:07/02/2023  
Replied by Circle(CCF Northern Circle) on:08/02/2023  
Query raised by Circle (CCF Northern Circle) on:16/02/2022  
Replied by DFO (Kozhikode) on:03/03/2022  
Query raised by Circle (CCF Northern Circle) on:01/04/2022  
Replied by DFO (Kozhikode) on:28/05/2022  
Query raised by Circle (CCF Northern Circle) on:30/05/2022  
Replied by DFO (Kozhikode) on:30/05/2022  
Query raised by Circle (CCF Northern Circle) on:30/05/2022  
Replied by DFO (Wayanad South) on:30/05/2022  
Query raised by Circle (CCF Northern Circle) on:30/05/2022  
Replied by DFO (Kozhikode) on:30/05/2022  
Query raised by Circle (CCF Northern Circle) on:30/05/2022  
Replied by DFO (Wayanad South) on:30/05/2022  
Query raised by Circle (CCF Northern Circle) on:30/05/2022  
Replied by DFO (Wayanad South) on:30/05/2022  
Query raised by Circle (CCF Northern Circle) on:21/06/2022  
Replied by DFO (Wayanad South) on:01/07/2022  
Query raised by Circle (CCF Northern Circle) on:01/07/2022  
Replied by DFO (Wayanad South) on:01/07/2022  
Query raised by Circle (CCF Northern Circle) on:01/07/2022  
Replied by DFO (Kozhikode) on:01/07/2022  
Query raised by Circle (CCF Northern Circle) on:01/07/2022  
Replied by DFO (Wayanad South) on:01/07/2022  
Query raised by Circle (CCF Northern Circle) on:15/10/2022  
Replied by DFO (Wayanad South) on:10/11/2022  
Query raised by Circle (CCF Northern Circle) on:15/10/2022  
Replied by DFO (Kozhikode) on:15/11/2022  
Query raised by Circle (CCF Northern Circle) on:02/12/2022  
Replied by DFO (Wayanad South) on:12/01/2023  
Query raised by Circle (CCF Northern Circle) on:13/01/2023  
Replied by DFO (Wayanad South) on:13/01/2023  
Query raised by Circle (CCF Northern Circle) on:07/02/2023  
Replied by DFO (Wayanad South) on:07/02/2023  
Query raised by Circle (CCF Northern Circle) on:08/02/2023  
Replied by DFO (Wayanad South) on:08/02/2023  
Query raised by DFO (Kozhikode) on:18/11/2021  
Replied by UA on :22/11/2021  
Query raised by DFO (Wayanad South) on:25/11/2021  
Replied by UA on :27/12/2021  
Query raised by DFO (Kozhikode) on:26/11/2021  
Replied by UA on :27/12/2021  
Query raised by DFO (Wayanad South) on:01/01/2022  
Replied by UA on :03/01/2022  
Query raised by DFO (Wayanad South) on:04/01/2022  
Replied by UA on :13/01/2022  
Query raised by DFO (Kozhikode) on:02/04/2022  
Replied by UA on :28/04/2022  
Query raised by DFO (Wayanad South) on:15/10/2022  
Replied by UA on :28/10/2022  
Query raised by DFO (Wayanad South) on:04/11/2022  
Replied by UA on :07/11/2022  
Query raised by DFO (Wayanad South) on:06/12/2022  
Replied by UA on :05/01/2023  
Query raised by DFO (Wayanad South) on:10/01/2023  
Replied by UA on :11/01/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Bangalore) on:28/11/2024  
Query raised by State Government (Kerala) on:17/12/2024  
Replied by Nodal Officer (Kerala) on:06/01/2025  
Query raised by State Government (Kerala) on:28/01/2025  
Replied by Nodal Officer (Kerala) on:02/05/2025  
Query raised by Nodal Officer on:06/02/2025  
Replied by UA on :10/02/2025  
NOTE:- Proposal is pending at State Government for verifying Compliance of Conditions due to EDS raised by RO for Stage-II .