  (i). Proposal No. : FP/KA/ROAD/120467/2021              (ii). Name of Project for which Forest Land is required : 4 L of Addahole (Near Gundya) to Bantwal Cross Section (Pkg-01) from Design Km. 255.140 to Design Km. 270.270 of NH-75 (Old NH-48)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 2.5315 Ha additional forest land for Four-Laning of the Bangalore-Mangalore section of NH-48 (New NH-75) from Design Chainage Km 255.140 to Km 270.270 passing through reserve forest stretch of Four laning of Addahole (Near Gundya) (Existing Chainage Km. 263.000, Design Chainage Km. 255.              (iv). File no. : F.No.4-KRB1313/2021-BAN              (v). State : Karnataka              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.5315
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/KA/ROAD/120467/202123/01/202116/03/2021  17/02/2021   23/03/2021  26/02/2021   15/04/2021   15/04/2021 Mangalore :17/04/2021Mangalore:
  15/07/2021 (Mangalore)

Karnataka:
17/07/2021
Karnataka:
07/08/2021
Bangalore:
07/09/2021
11/07/2023
By :Regional Office
Karnataka
26/12/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bangalore) on:29/09/2021  
Replied by State Government(Karnataka) on:01/04/2022  
Query raised by Regional Office (Bangalore) on:04/05/2022  
Replied by State Government(Karnataka) on:16/02/2023  
Query raised by Regional Office (Bangalore) on:06/03/2023  
Replied by State Government(Karnataka) on:23/05/2023  
Query raised by State Government (Karnataka) on:07/10/2021  
Replied by Nodal Officer (Karnataka) on:25/02/2022  
Query raised by State Government (Karnataka) on:19/05/2022  
Replied by Nodal Officer (Karnataka) on:07/02/2023  
Query raised by State Government (Karnataka) on:13/03/2023  
Replied by Nodal Officer (Karnataka) on:12/05/2023  
Query raised by Nodal Officer (Karnataka) on:03/08/2021  
Replied by Circle(Mangalore) on:04/08/2021  
Query raised by Nodal Officer (Karnataka) on:25/10/2021  
Replied by Circle(Mangalore) on:28/01/2022  
Query raised by Nodal Officer (Karnataka) on:23/05/2022  
Replied by Circle(Mangalore) on:10/10/2022  
Query raised by Nodal Officer (Karnataka) on:26/12/2022  
Replied by Circle(Mangalore) on:31/12/2022  
Query raised by Nodal Officer (Karnataka) on:16/03/2023  
Replied by Circle(Mangalore) on:20/04/2023  
Query raised by Circle (Mangalore) on:03/08/2021  
Replied by DFO (Mangalore) on:03/08/2021  
Query raised by Circle (Mangalore) on:26/10/2021  
Replied by DFO (Mangalore) on:22/01/2022  
Query raised by Circle (Mangalore) on:24/05/2022  
Replied by DFO (Mangalore) on:06/10/2022  
Query raised by Circle (Mangalore) on:27/12/2022  
Replied by DFO (Mangalore) on:29/12/2022  
Query raised by Circle (Mangalore) on:17/03/2023  
Replied by DFO (Mangalore) on:31/03/2023  
Query raised by DFO (Mangalore) on:26/10/2021  
Replied by UA on :02/12/2021  
Query raised by DFO (Mangalore) on:04/12/2021  
Replied by UA on :01/01/2022  
Query raised by DFO (Mangalore) on:25/05/2022  
Replied by UA on :16/09/2022  
Query raised by DFO (Mangalore) on:27/12/2022  
Replied by UA on :27/12/2022  
Query raised by DFO (Mangalore) on:20/03/2023  
Replied by UA on :30/03/2023  
Query raised by DFO (Mangalore) on:31/03/2023  
Replied by UA on :31/03/2023  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Bangalore) on:12/01/2024  
Query raised by State Government (Karnataka) on:22/01/2024  
Query raised by Nodal Officer on:14/02/2024  