Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
06/07/2022
|
The Extent required to be diverted for the proposal varies in documents provided.Correct the extent and re upload.
|
|
2
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
14/09/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
16/11/2022
|
Upload the KML file in Part I at C.ii .b.Maps of forest land to be diverted
|
|
4
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
13/01/2023
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
16/01/2023
|
EDS was raised by this office for correcting the following errors in Part 1 of the Proposal :-
1. The segment wise extent in C ii (b) which is Zero has to be corrected.
2. The extent of Forest land to be diverted is mentioned as 16.36 Ha in DC letter FOR/CR: 04/2021-22, Dated 10.03.2022 which has to be corrected or if 16.36 Ha extent is correct then extent in Part 1 has to be corrected entirely.
We request you to correct these errors and send corrected documents in hard copies to this office and upload the same in Part-I of the proposal already submitted by you through Parivesh web portal.
Further, the link in Parivesh web portal is been transferred to you for necessary action in this regard.
|
|
6
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
04/02/2023
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
04/02/2023
|
Please reply to this EDS letter of this office dated 13.01.2023 through letter with uploaded copy of your EDS letter only after sorting out the extent in DC letter.
|
|
8
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
07/02/2023
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
21/02/2023
|
Please reply to this EDS letter of this office dated 13.01.2023 through letter with uploaded copy of your EDS letter only after sorting out the extent in DC letter.
|
|
10
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
27/02/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
02/03/2023
|
Please reply to this EDS letter of this office dated 13.01.2023 through letter with uploaded copy of your EDS letter only after sorting out the extent in DC letter.
|
|
12
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
14/03/2023
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
19/04/2023
|
Please reply to this EDS letter of this office dated 13.01.2023 through letter and correct the details in parivesh portal and send a hard copy as per our proposed site inspection recently
|
|
14
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
15/05/2023
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
04/07/2023
|
The eastern part of the to be diverted land is left out, include it and submit the corrected kml and maps concerned to this office.
|
|
16
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
07/07/2023
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
11/09/2023
|
Propose CA is not suitable as the department has already raised a plantation and even dugout a CPT in that area. We request you to provide alternate CA area for the proposal
|
|
18
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
25/09/2023
|
The correction have been made as per the instruction received
|
|
19
|
Nodal Officer
|
EDS
|
CF (Bangalore)
|
08/12/2023
|
proposal is found to be incomplete. The details are enclosed. provide details
|
|
20
|
CF (Bangalore)
|
EDS
|
DFO (Bangalore Rural)
|
14/12/2023
|
As per direction of PCCF FC, letter dated 06-12-2023, you are here by directed to obtain the essential information from user Agencey along with necessary documents and submit the revised proposal along with INK signed hard copies
|
|
21
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
19/01/2024
|
Toposheet and Village Map of alternate non-forest land to be identified and FRA certificate for 18.6Ha to be submitted to this office as per PCCF and CF directions.
|
|
22
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
23/01/2024
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
25/01/2024
|
Please take action as per the directions given to you in the PCCF FC letter dated 06-12-2023 where he clearly specifies that UA should provide alternate non-forest land.The correction made by you or letter sent by you cannot be accepted as it is against the directions of the PCCF FC.
|
|
24
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
30/01/2024
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
16/03/2024
|
Please taken as per the letter
|
|
26
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
16/03/2024
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
12/06/2024
|
Please take action as per the directions given to you in the PCCF FC letter dated 06-12-2023 where he clearly specifies that UA should provide alternate non-forest land.The correction made by you or letter sent by you cannot be accepted as it is against the directions of the PCCF FC.
|
|
28
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
01/07/2024
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
01/07/2024
|
Please take action as per the directions given to you in the PCCF FC letter dated 06-12-2023 where he clearly specifies that UA should provide alternate non-forest land.The correction made by you or letter sent by you cannot be accepted as it is against the directions of the PCCF FC.
|
|
30
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
26/08/2024
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Bangalore Rural)
|
REPLY
|
CF (Bangalore)
|
26/08/2024
|
As per the PCCF FC order CA suitability certificate, CA scheme details, Watering Charges details, Geo reference map, Topo sheet map with Kml File were procured from DCF kolar for raising CA plantation in 37.20 Ha in Sy No.73 of Diguvamarampalli and Sy 70 of Thimanahalli of Adagal-Nelavanki Jungle State Forest, Srinivaspura Range/Taluk, Kolar district and are updated in parivesh potal for further action.
|
|
32
|
CF (Bangalore)
|
REPLY
|
Nodal Officer
|
29/08/2024
|
Geo reference Map Survey of India Toposheet with GPS Co- ordinates Suitability certificate Format -B CA, Scheme with watering charges and KML files submitted by DCF, Bengaluru Rural and Letter dated 15-07-2024 of DCF, Bengaluru Rural, is submitted for kind perusal and necessary action.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Bangalore)
|
17/09/2024
|
Revised FRA certificate needs to be upload by User Agency in Part-I
|
|
34
|
CF (Bangalore)
|
EDS
|
DFO (Bangalore Rural)
|
17/09/2024
|
Revised FRA certificate needs to be upload by User Agency in Part-I
|
|
35
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
18/09/2024
|
Please update the FRA certificate in part 1 of your proposal
|
|
36
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
18/09/2024
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Bangalore Rural)
|
REPLY
|
CF (Bangalore)
|
18/09/2024
|
UA has uploaded the revised FRA certificate for 18.6 Ha
|
|
38
|
CF (Bangalore)
|
REPLY
|
Nodal Officer
|
21/09/2024
|
UA has uploaded the revised FRA certificate for 18.6 Ha
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
05/12/2024
|
State Government has been requested vide letter dated 05.12.2024 to furnish the recommendations of Project Steering Committee, comments on adverse effect on the ecosystem, status of NGT case, types of trees to be felled, justification, CB ratio, KML files of alternatives and CA land, site suitability certificate of DFL land etc.
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
05/12/2024
|
forest department has been requested vide letter dated 05.12.2024 to furnish the recommendations of Project Steering Committee, comments on adverse effect on the ecosystem, status of NGT case, types of trees to be felled, justification, CB ratio, KML files of alternatives and CA land, site suitability certificate of DFL land etc.
|
|
41
|
Nodal Officer
|
EDS
|
CF (Bangalore)
|
18/12/2024
|
Submit reply to the EDS raised by GoI.
|
|
42
|
CF (Bangalore)
|
EDS
|
DFO (Bangalore Rural)
|
31/12/2024
|
DCF, Bengaluru Rural , Devanahalli has been directed to obtain information from the user agency for the observations raised by Government of India Ministry of Environment, Forest & Climate Change, Regional Office Letter dated 3.12.2023 and submit 3 ink signed copies along with necessary documents .
|
|
43
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
01/03/2025
|
The UA is requested to provide clarifications for the observations made by the MOEF Office.
|
|
44
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
04/03/2025
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
05/03/2025
|
Please reply in letter mentioning clarifications for all the observations made by the MOEF Office
|
|
46
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
27/03/2025
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
27/03/2025
|
Please answer observations pertaining to UA
|
|
48
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
27/03/2025
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Bangalore Rural)
|
REPLY
|
CF (Bangalore)
|
07/04/2025
|
The EDS reply of UA for the observations made by MOEF and CC and clarifications by DCF,BRD to the same are submitted for further processing
|
|
50
|
CF (Bangalore)
|
EDS
|
DFO (Bangalore Rural)
|
22/04/2025
|
Your letter dated-07.04.2025 has been verified and directed to obtain the information for Point-1,3,5,6,7,8 & 11 from user agency and submit the information at the earliest
|
|
51
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
23/04/2025
|
please provide info as per the CF bangalore letter and as discussed in the meeting on 22.04.2025
|
|
52
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
01/05/2025
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Bangalore Rural)
|
EDS
|
User Agency (gm@kride.in)
|
02/05/2025
|
please provide info as per the CF bangalore letter and as discussed in the meeting on 22.04.2025
|
|
54
|
User Agency (gm@kride.in)
|
REPLY
|
DFO (Bangalore Rural)
|
02/05/2025
|
The correction have been made as per the instruction received
|
|
55
|
DFO (Bangalore Rural)
|
REPLY
|
CF (Bangalore)
|
03/05/2025
|
The User Agency has submitted their information for 11 observations to this office. DCF/BRD has also commented on the observations and attached it to this letter for your kind perusal and necessary action.
|
|
56
|
CF (Bangalore)
|
REPLY
|
Nodal Officer
|
06/05/2025
|
The Clarification submitted by User Agency and DCF has been submitted for kind perusal and necessary action .
|
|
57
|
Nodal Officer
|
REPLY
|
State secretary
|
13/05/2025
|
EDS reply has been submitted.
|
|
58
|
State secretary
|
REPLY
|
Regional Office
|
14/05/2025
|
sir/madam
please find the attachment regarding MoEFCC EDS query dated:03.12.2024.
The user agency and PCCF(FC) have informed their inability to upload KML files, accordingly KML files have been sent through the mail. dated:14.05.2025
|
|