TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JK/ROAD/52321/2020              (ii). Name of Project for which Forest Land is required : Construction of road from Dabatli to Choatra Lahar & Sathla to Sarthan under NABARD              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Road connectivity from these villages to Distirct Head quarter of total 10000 soul              (iv). File no. : 9-JKB-057/2021-Jammu              (v). State : Jammu and Kashmir              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.0375
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/JK/ROAD/52321/202028/10/2020aa02/11/2020   12/11/2020 Kathua Forest Division :12/11/2020East Circle Jammu:
  06/01/2021 (Kathua Forest Division)

Jammu and Kashmir:
15/01/2021
Jammu and Kashmir:
28/05/2021
Jammu:
09/06/2021
09/02/2022
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Jammu) on:01/07/2021  
Replied by State Government(Jammu and Kashmir) on:17/12/2021  
Query raised by Regional Office (Jammu) on:31/12/2021  
Replied by State Government(Jammu and Kashmir) on:03/02/2022  
Query raised by State Government (Jammu and Kashmir) on:02/07/2021  
Replied by Nodal Officer (Jammu and Kashmir) on:13/12/2021  
Query raised by State Government (Jammu and Kashmir) on:31/12/2021  
Replied by Nodal Officer (Jammu and Kashmir) on:02/02/2022  
Query raised by Nodal Officer (Jammu and Kashmir) on:28/01/2021  
Replied by Circle(East Circle Jammu) on:10/03/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:20/03/2021  
Replied by Circle(East Circle Jammu) on:28/04/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:03/05/2021  
Replied by Circle(East Circle Jammu) on:21/05/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:05/07/2021  
Replied by Circle(East Circle Jammu) on:06/12/2021  
Query raised by Nodal Officer (Jammu and Kashmir) on:31/12/2021  
Replied by Circle(East Circle Jammu) on:15/01/2022  
Query raised by Nodal Officer (Jammu and Kashmir) on:19/01/2022  
Replied by Circle(East Circle Jammu) on:24/01/2022  
Query raised by Circle (East Circle Jammu) on:11/01/2021  
Replied by DFO (Kathua Forest Division) on:14/01/2021  
Query raised by Circle (East Circle Jammu) on:29/01/2021  
Replied by DFO (Kathua Forest Division) on:18/02/2021  
Query raised by Circle (East Circle Jammu) on:19/02/2021  
Replied by DFO (Kathua Forest Division) on:10/03/2021  
Query raised by Circle (East Circle Jammu) on:20/03/2021  
Replied by DFO (Kathua Forest Division) on:27/04/2021  
Query raised by Circle (East Circle Jammu) on:04/05/2021  
Replied by DFO (Kathua Forest Division) on:18/05/2021  
Query raised by Circle (East Circle Jammu) on:06/07/2021  
Replied by DFO (Kathua Forest Division) on:02/11/2021  
Query raised by Circle (East Circle Jammu) on:06/11/2021  
Replied by DFO (Kathua Forest Division) on:27/11/2021  
Query raised by Circle (East Circle Jammu) on:03/01/2022  
Replied by DFO (Kathua Forest Division) on:12/01/2022  
Query raised by Circle (East Circle Jammu) on:20/01/2022  
Replied by DFO (Kathua Forest Division) on:24/01/2022  
Query raised by DFO (Kathua Forest Division) on:09/12/2020  
Replied by UA on :06/01/2021  
Query raised by DFO (Kathua Forest Division) on:22/02/2021  
Replied by UA on :10/03/2021  
Query raised by DFO (Kathua Forest Division) on:20/03/2021  
Replied by UA on :27/04/2021  
Query raised by DFO (Kathua Forest Division) on:12/07/2021  
Replied by UA on :25/10/2021  
Query raised by DFO (Kathua Forest Division) on:09/11/2021  
Replied by UA on :20/11/2021  
Query raised by DFO (Kathua Forest Division) on:03/01/2022  
Replied by UA on :11/01/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
   Query raised by State Government (Jammu and Kashmir) on:05/12/2022  
Query raised by Nodal Officer on:28/12/2022  
NOTE:- Proposal is pending at User Agency due to EDS raised by State Government for verifying Compliance of Conditions .