Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Basholi Forest Division)
|
EDS
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
24/12/2021
|
provide the requisite information
|
|
2
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
REPLY
|
DFO (Basholi Forest Division)
|
29/01/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Basholi Forest Division)
|
EDS
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
27/02/2022
|
This office has recieved the Revenue Papers for the area to be given in lieu for the diversion of forest land. As such, same may be identified on ground and handed over, enabling this office to prepare the CA scheme and further uploading on the portal.
|
|
4
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
REPLY
|
DFO (Basholi Forest Division)
|
05/04/2022
|
The correction have been made as per the instruction received
|
|
5
|
CF (East Circle Jammu)
|
EDS
|
DFO (Basholi Forest Division)
|
11/04/2022
|
1. Name of the project is not visible in the approval of the project.
2. In Part II, B2.4 Component wise breakup is not correct.
Please do the needful.
|
|
6
|
DFO (Basholi Forest Division)
|
EDS
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
11/04/2022
|
1. Name of the project is not visible in the approval of the project. 2. In Part II, B2.4 Component wise breakup is not correct. Please do the needful
|
|
7
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
REPLY
|
DFO (Basholi Forest Division)
|
11/04/2022
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Basholi Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
11/04/2022
|
he correction have been made as per the instruction received
|
|
9
|
CF (East Circle Jammu)
|
EDS
|
DFO (Basholi Forest Division)
|
13/04/2022
|
Kindly provide the requisite information as per EDS.
|
|
10
|
DFO (Basholi Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
16/04/2022
|
Report submitted for favour of information and necessary action please
|
|
11
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
02/05/2022
|
Please upload the requisite documents
|
|
12
|
CF (East Circle Jammu)
|
EDS
|
DFO (Basholi Forest Division)
|
05/05/2022
|
Kindly provide the requisite information as per EDS.
|
|
13
|
DFO (Basholi Forest Division)
|
EDS
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
05/05/2022
|
Kindly provide the requisite information as per EDS.
|
|
14
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
REPLY
|
DFO (Basholi Forest Division)
|
06/05/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Basholi Forest Division)
|
EDS
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
06/05/2022
|
Maps of forest land proposed to be diverted needed to upload in part C
|
|
16
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
REPLY
|
DFO (Basholi Forest Division)
|
09/05/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Basholi Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
10/05/2022
|
The correction have been made as per the instruction received
|
|
18
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
11/05/2022
|
Necessary corrections have been made by User Agency and DFO Basohli. Also reply to EDS raised by your good office vide No. PCCF/FCA/3409-1/655-58 dated 02.05.2022 has been uploaded on Parivesh Portal.
|
|
19
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
20/05/2022
|
Please upload the requisite documents
|
|
20
|
CF (East Circle Jammu)
|
EDS
|
DFO (Basholi Forest Division)
|
21/05/2022
|
Kindly provide the requisite information as per EDS.
|
|
21
|
DFO (Basholi Forest Division)
|
EDS
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
26/05/2022
|
Kindly provide the requisite information as per EDS.
|
|
22
|
User Agency (pmgsykathuaforestcase@gmail.com)
|
REPLY
|
DFO (Basholi Forest Division)
|
26/05/2022
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Basholi Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
29/05/2022
|
The correction have been made as per the instruction received
|
|
24
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
30/05/2022
|
Requisite corrections have been made by User Agency and DFO.
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
22/07/2022
|
EDS
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
25/07/2022
|
EDS
|
|
27
|
Nodal Officer
|
EDS
|
CF (East Circle Jammu)
|
25/07/2022
|
Please upload the requisite documents
|
|
28
|
CF (East Circle Jammu)
|
EDS
|
DFO (Basholi Forest Division)
|
25/07/2022
|
Kindly provide the requisite information as per EDS.
|
|
29
|
DFO (Basholi Forest Division)
|
REPLY
|
CF (East Circle Jammu)
|
22/08/2022
|
The correction have been made as per the instruction recived
|
|
30
|
CF (East Circle Jammu)
|
REPLY
|
Nodal Officer
|
23/08/2022
|
As per EDS, revised NPV calculation sheet has been uploaded at Add. information details (S.no. 6) of Part-II.
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
26/08/2022
|
The requisite information has been uploaded
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
29/08/2022
|
The requisite information has been uploaded
|
|