TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/JH/MIN/139492/2021              (ii). Name of Project for which Forest Land is required : Gondulpara Coal Mine              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Gondulpara Coal Mine, Location : Hazaribagh District, Jharkhand, Allotted to: Adani Enterprises Ltd Allotment Order No. : NA-104/10/2020-NA dated 08.03.2021 Block Area :513.18 Ha(Forest land 219.80 Ha, Mine Capacity : 4 MTPA.              (iv). File no. : 8-11/2025-FC              (v). State : Jharkhand              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 219.8
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/JH/MIN/139492/202126/03/202130/03/2021   10/06/2021   14/06/2021   18/06/2021 Hazaribagh West :18/06/2021Hazaribagh:
  15/09/2023 (Hazaribagh West)

Jharkhand:
22/09/2023
Jharkhand:
05/02/2024
16/10/2025
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 10/11/2025  
Query raised by State Government (Jharkhand) on:20/03/2024  
Replied by Nodal Officer (Jharkhand) on:15/01/2025  
Query raised by State Government (Jharkhand) on:05/02/2025  
Replied by Nodal Officer (Jharkhand) on:24/09/2025  
Query raised by State Government (Jharkhand) on:20/11/2025  
Query raised by Nodal Officer (Jharkhand) on:27/10/2023  
Replied by Circle(Hazaribagh) on:08/01/2024  
Query raised by Nodal Officer (Jharkhand) on:03/04/2024  
Replied by Circle(Hazaribagh) on:24/12/2024  
Query raised by Nodal Officer (Jharkhand) on:03/03/2025  
Replied by Circle(Hazaribagh) on:19/04/2025  
Query raised by Nodal Officer (Jharkhand) on:07/05/2025  
Replied by Circle(Hazaribagh) on:12/08/2025  
Query raised by Nodal Officer (Jharkhand) on:25/11/2025  
Replied by Circle() on:  
Query raised by Circle (Hazaribagh) on:21/09/2023  
Replied by DFO (Hazaribagh West) on:22/09/2023  
Query raised by Circle (Hazaribagh) on:30/10/2023  
Replied by DFO (Hazaribagh West) on:22/12/2023  
Query raised by Circle (Hazaribagh) on:04/04/2024  
Replied by DFO (Hazaribagh West) on:24/10/2024  
Query raised by Circle (Hazaribagh) on:14/11/2024  
Replied by DFO (Hazaribagh West) on:29/11/2024  
Query raised by Circle (Hazaribagh) on:07/03/2025  
Replied by DFO (Hazaribagh West) on:15/04/2025  
Query raised by Circle (Hazaribagh) on:13/05/2025  
Replied by DFO (Hazaribagh West) on:08/08/2025  
Query raised by Circle (Hazaribagh) on:27/11/2025  
Replied by DFO (Hazaribagh West) on:04/02/2026  
Query raised by DFO (Hazaribagh West) on:29/06/2021  
Replied by UA on :11/07/2023  
Query raised by DFO (Hazaribagh West) on:10/08/2023  
Replied by UA on :17/08/2023  
Query raised by DFO (Hazaribagh West) on:21/09/2023  
Replied by UA on :21/09/2023  
Query raised by DFO (Hazaribagh West) on:22/09/2023  
Replied by UA on :22/09/2023  
Query raised by DFO (Hazaribagh West) on:01/11/2023  
Replied by UA on :29/11/2023  
Query raised by DFO (Hazaribagh West) on:07/12/2023  
Replied by UA on :09/12/2023  
Query raised by DFO (Hazaribagh West) on:06/04/2024  
Replied by UA on :04/07/2024  
Query raised by DFO (Hazaribagh West) on:16/07/2024  
Replied by UA on :07/10/2024  
Query raised by DFO (Hazaribagh West) on:14/11/2024  
Replied by UA on :16/11/2024  
Query raised by DFO (Hazaribagh West) on:11/03/2025  
Replied by UA on :04/04/2025  
Query raised by DFO (Hazaribagh West) on:19/05/2025  
Replied by UA on :02/08/2025  
Query raised by DFO (Hazaribagh West) on:07/08/2025  
Replied by UA on :07/08/2025  
Query raised by DFO (Hazaribagh West) on:03/12/2025  
Replied by UA on :22/12/2025  
NOTE:- Proposal is pending at CF due to EDS raised by Head Office .