| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
29/06/2021
|
Please take note to the query raised.
|
|
|
2
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
11/07/2023
|
The correction have been made as per the instruction received
|
|
|
3
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
10/08/2023
|
Please take note to the query raised.
|
|
|
4
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
17/08/2023
|
The correction have been made as per the instruction received
|
|
|
5
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
21/09/2023
|
Pease take note query raised by CF
|
|
|
6
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
21/09/2023
|
Pease take note query raised by CF
|
|
|
7
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
21/09/2023
|
The correction have been made as per the instruction received
|
|
|
8
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
22/09/2023
|
Uploaded Part-I PDF file in additional documents is not open. Please again upload Part-I PDF in additional documents.
|
|
|
9
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
22/09/2023
|
The correction have been made as per the instruction received
|
|
|
10
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
22/09/2023
|
The correction have been made as per instruction received
|
|
|
11
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
27/10/2023
|
please take note on EDS by Nodal Office
|
|
|
12
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
30/10/2023
|
Please take note on EDS by Nodal Office
|
|
|
13
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
01/11/2023
|
Please take note on EDS by Nodal Office
|
|
|
14
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
29/11/2023
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
07/12/2023
|
Please take note on EDS by DFO
|
|
|
16
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
09/12/2023
|
The correction have been made as per the instruction received
|
|
|
17
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
22/12/2023
|
The correction has been made as per the instruction received.
|
|
|
18
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
08/01/2024
|
The correction has been made as per instruction received.
|
|
|
19
|
State secretary
|
EDS
|
Nodal Officer
|
20/03/2024
|
Comment of CWLW, willingness of present order to transfer CA land as per the guidelines needs to be provided.
|
|
|
20
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
03/04/2024
|
Please take note on EDS by GOJ
|
|
|
21
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
04/04/2024
|
Please take note on EDS by GOJ
|
|
|
22
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
06/04/2024
|
Please take note on EDS by GOJ
|
|
|
23
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
04/07/2024
|
The correction have been made as per the instruction received
|
|
|
24
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
16/07/2024
|
Please take note on EDS by DFO
|
|
|
25
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
07/10/2024
|
The correction have been made as per the instruction received
|
|
|
26
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
24/10/2024
|
The correction have been made as per the instruction received
|
|
|
27
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
14/11/2024
|
Pease take note query raised by CF
|
|
|
28
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
14/11/2024
|
please take note of the query raised by CF Hazaribagh and submit reply
|
|
|
29
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
16/11/2024
|
The correction have been made as per the instruction received
|
|
|
30
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
29/11/2024
|
The correction have been made as per the instruction received.
|
|
|
31
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
24/12/2024
|
The correction have been made as per the instruction received.
|
|
|
32
|
Nodal Officer
|
REPLY
|
State secretary
|
15/01/2025
|
EDS Reply
|
|
|
33
|
State secretary
|
EDS
|
Nodal Officer
|
05/02/2025
|
Reply of query letter dated-04.02.2025.
|
|
|
34
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
03/03/2025
|
Pleast take note on EDS by Nodal Office
|
|
|
35
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
07/03/2025
|
Please take note on EDS by GOJ
|
|
|
36
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
11/03/2025
|
Please take note on EDS by GOJ
|
|
|
37
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
04/04/2025
|
The correction have been made as per the instruction received
|
|
|
38
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
15/04/2025
|
The user agency has submitted reply to the EDS raised.
|
|
|
39
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
19/04/2025
|
The correction have been made as per the instruction received.
|
|
|
40
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
07/05/2025
|
Please take note on EDS by Nodal officer
|
|
|
41
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
13/05/2025
|
Please take note on EDS by Nodal officer
|
|
|
42
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
19/05/2025
|
Please take note on EDS by Nodal officer
|
|
|
43
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
02/08/2025
|
The correction have been made as per the instruction received
|
|
|
44
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
07/08/2025
|
Please take note to the query raised by DFO
|
|
|
45
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
07/08/2025
|
The correction have been made as per the instruction received
|
|
|
46
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
08/08/2025
|
The correction have been made as per the instruction received
|
|
|
47
|
CF (Hazaribagh)
|
REPLY
|
Nodal Officer
|
12/08/2025
|
The correction have been made as per instruction received.
|
|
|
48
|
Nodal Officer
|
REPLY
|
State secretary
|
24/09/2025
|
EDS Reply
|
|
|
49
|
Head Office
|
EDS
|
State secretary
|
10/11/2025
|
EDS
|
|
|
50
|
State secretary
|
EDS
|
Nodal Officer
|
20/11/2025
|
Reply of query letter dated-10.11.2025.
|
|
|
51
|
Nodal Officer
|
EDS
|
CF (Hazaribagh)
|
25/11/2025
|
Please take note on EDS by gOI
|
|
|
52
|
CF (Hazaribagh)
|
EDS
|
DFO (Hazaribagh West)
|
27/11/2025
|
Please take note on EDS by GoJ
|
|
|
53
|
DFO (Hazaribagh West)
|
EDS
|
User Agency (gondulapara@adani.com)
|
03/12/2025
|
Pease take note queries raised by GoI
|
|
|
54
|
User Agency (gondulapara@adani.com)
|
REPLY
|
DFO (Hazaribagh West)
|
22/12/2025
|
The correction have been made as per the instruction received
|
|
|
55
|
DFO (Hazaribagh West)
|
REPLY
|
CF (Hazaribagh)
|
04/02/2026
|
The correction have been made as per the instruction received.
|
|