Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
28/01/2020
|
Layout plan and dgps not correct
|
|
2
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
21/06/2020
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
27/11/2020
|
querryraisedbydfo
|
|
4
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
19/07/2021
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
20/08/2021
|
queeryraise
|
|
6
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
13/09/2021
|
The correction have been made as per the instruction received
|
|
7
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
30/09/2021
|
Letter attached.
|
|
8
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
13/10/2021
|
querry raise by high officers
|
|
9
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
14/10/2021
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
02/11/2021
|
essentialsoughtout
|
|
11
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
03/01/2022
|
Case Down
|
|
12
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
03/01/2022
|
Letter attached.
|
|
13
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
14/01/2022
|
query raised by dfo
|
|
14
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
08/03/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
04/04/2022
|
Essential Sought out
|
|
16
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
05/04/2022
|
upload information properly
|
|
17
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
05/04/2022
|
ESSENTIAL SOUGHT OUT
|
|
18
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
06/04/2022
|
Essential oughtout by DFO
|
|
19
|
Regional Office
|
EDS
|
State secretary
|
09/06/2022
|
EDS
|
|
20
|
State secretary
|
EDS
|
Nodal Officer
|
17/06/2022
|
forward to DFO for upload the information
|
|
21
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
17/06/2022
|
forward to DFO for upload the information
|
|
22
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
20/06/2022
|
Letter attached.
|
|
23
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
21/06/2022
|
query raised by dfo
|
|
24
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
02/08/2022
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
04/08/2022
|
please attach copy of letter
|
|
26
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
22/12/2022
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
03/01/2023
|
Essential sought out
|
|
28
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
20/01/2023
|
Letter attached.
|
|
29
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
07/03/2023
|
Essential sought out
|
|
30
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
09/03/2023
|
eds replied
|
|
31
|
Nodal Officer
|
REPLY
|
State secretary
|
28/06/2023
|
EDS Reply
|
|
32
|
State secretary
|
REPLY
|
Regional Office
|
30/06/2023
|
EDS resolved case sent to IRO MOEF
|
|
33
|
Regional Office
|
EDS
|
State secretary
|
02/08/2023
|
EDS
|
|
34
|
State secretary
|
EDS
|
Nodal Officer
|
02/08/2023
|
EDS raised by IRO MOEF
|
|
35
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
02/08/2023
|
Case down - EDS by IRO
|
|
36
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
02/08/2023
|
Letter attached.
|
|
37
|
DFO (Faridabad)
|
EDS
|
User Agency (mvnschool2019@gmail.com)
|
02/11/2023
|
Query raised by state Govt. Copy attached - After analysing the KML file, it has been observed that a multistorey building already exists on that land. please provide information about status of the building, its purpose, year of construction and if any permission under FC act already taken
|
|
38
|
User Agency (mvnschool2019@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
09/01/2024
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
15/01/2024
|
DFO letter with F.O.R and UA original reply
|
|
40
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
18/01/2024
|
DFO letter with F.O.R and UA original reply
|
|
41
|
Nodal Officer
|
REPLY
|
State secretary
|
25/01/2024
|
EDS Reply
|
|
42
|
State secretary
|
REPLY
|
Regional Office
|
25/01/2024
|
EDS resolved case sent to IRO MOEF
|
|
43
|
Regional Office
|
EDS
|
State secretary
|
15/02/2024
|
eds
|
|
44
|
State secretary
|
EDS
|
Nodal Officer
|
19/02/2024
|
EDS Raised by IRO MOEF
|
|
45
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
15/04/2024
|
Case down
|
|
46
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
16/04/2024
|
case down to send comments
|
|