TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/40734/2019              (ii). Name of Project for which Forest Land is required : C/o link road Chowk to Sandoa via Dharjol Ropri Dhar              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : There is a proposal for the C/o link road Chowk to Sandoa via Dharjol Ropri Dhar the Construction of the road shall be increase the economy of the area with the sufficient cheap and quick transportation of possible agriculture produce easy and emergency medical help also be improve.              (iv). File no. : FC/HPB/06/22/2021              (v). State : Himachal Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.8272
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/40734/201919/06/201916/09/2019  19/07/2019  06/07/2019  20/06/2019   31/10/2019  13/09/2019  09/07/2019  04/07/2019   04/11/2019   10/02/2020 Suket :10/02/2020Mandi:
  27/11/2020 (Suket)

Himachal Pradesh:
04/12/2020
Himachal Pradesh:
20/02/2021
Shimla:
31/08/2021
24/06/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:29/09/2021  
Replied by State Government(Himachal Pradesh) on:10/06/2022  
Query raised by Regional Office (Shimla) on:21/06/2022  
Replied by State Government(Himachal Pradesh) on:19/12/2022  
Query raised by Regional Office (Shimla) on:30/12/2022  
Replied by State Government(Himachal Pradesh) on:03/08/2023  
Query raised by Regional Office (Shimla) on:19/01/2024  
Replied by State Government(Himachal Pradesh) on:23/03/2024  
Query raised by Regional Office (Shimla) on:07/05/2024  
Replied by State Government(Himachal Pradesh) on:07/06/2024  
Query raised by State Government (Himachal Pradesh) on:29/09/2021  
Replied by Nodal Officer (Himachal Pradesh) on:10/06/2022  
Query raised by State Government (Himachal Pradesh) on:22/06/2022  
Replied by Nodal Officer (Himachal Pradesh) on:17/12/2022  
Query raised by State Government (Himachal Pradesh) on:30/12/2022  
Replied by Nodal Officer (Himachal Pradesh) on:20/07/2023  
Query raised by State Government (Himachal Pradesh) on:19/01/2024  
Replied by Nodal Officer (Himachal Pradesh) on:23/03/2024  
Query raised by State Government (Himachal Pradesh) on:15/05/2024  
Replied by Nodal Officer (Himachal Pradesh) on:07/06/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:28/12/2020  
Replied by Circle(Mandi) on:12/01/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:16/01/2021  
Replied by Circle(Mandi) on:30/01/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:29/09/2021  
Replied by Circle(Mandi) on:18/05/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:22/06/2022  
Replied by Circle(Mandi) on:03/10/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:05/11/2022  
Replied by Circle(Mandi) on:06/12/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:30/12/2022  
Replied by Circle(Mandi) on:30/05/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:06/06/2023  
Replied by Circle(Mandi) on:15/07/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:19/01/2024  
Replied by Circle(Mandi) on:18/03/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:15/05/2024  
Replied by Circle(Mandi) on:29/05/2024  
Query raised by Circle (Mandi) on:29/12/2020  
Replied by DFO (Suket) on:06/01/2021  
Query raised by Circle (Mandi) on:20/01/2021  
Replied by DFO (Suket) on:28/01/2021  
Query raised by Circle (Mandi) on:06/10/2021  
Replied by DFO (Suket) on:11/02/2022  
Query raised by Circle (Mandi) on:03/03/2022  
Replied by DFO (Suket) on:13/04/2022  
Query raised by Circle (Mandi) on:02/07/2022  
Replied by DFO (Suket) on:29/09/2022  
Query raised by Circle (Mandi) on:05/11/2022  
Replied by DFO (Suket) on:23/11/2022  
Query raised by Circle (Mandi) on:31/12/2022  
Replied by DFO (Suket) on:31/03/2023  
Query raised by Circle (Mandi) on:07/06/2023  
Replied by DFO (Suket) on:11/07/2023  
Query raised by Circle (Mandi) on:20/01/2024  
Replied by DFO (Suket) on:06/03/2024  
Query raised by Circle (Mandi) on:17/05/2024  
Replied by DFO (Suket) on:28/05/2024  
Query raised by DFO (Suket) on:13/03/2020  
Replied by UA on :02/09/2020  
Query raised by DFO (Suket) on:03/09/2020  
Replied by UA on :03/09/2020  
Query raised by DFO (Suket) on:04/09/2020  
Replied by UA on :07/09/2020  
Query raised by DFO (Suket) on:10/09/2020  
Replied by UA on :18/11/2020  
Query raised by DFO (Suket) on:21/10/2021  
Replied by UA on :31/01/2022  
Query raised by DFO (Suket) on:02/02/2022  
Replied by UA on :08/02/2022  
Query raised by DFO (Suket) on:04/03/2022  
Replied by UA on :12/04/2022  
Query raised by DFO (Suket) on:04/07/2022  
Replied by UA on :29/09/2022  
Query raised by DFO (Suket) on:07/11/2022  
Replied by UA on :17/11/2022  
Query raised by DFO (Suket) on:31/12/2022  
Replied by UA on :25/02/2023  
Query raised by DFO (Suket) on:13/03/2023  
Replied by UA on :24/03/2023  
Query raised by DFO (Suket) on:08/06/2023  
Replied by UA on :06/07/2023  
Query raised by DFO (Suket) on:23/01/2024  
Replied by UA on :02/03/2024  
Query raised by DFO (Suket) on:20/05/2024  
Replied by UA on :28/05/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .